Your firm has identified three potential investment projects. The projects and their cash flows are shown below:
Project |
Cash Flow Today (millions) |
Cash Flow in One Year (millions) |
||
A | -$7 | $15 | ||
B | $7 | $4 | ||
C | $19 | -$6 |
Suppose all cash flows are certain and the risk-free interest rate is 9%.
(a) The NPV of Project A is $Answermillion. (Round to two decimal places.)
(b) The NPV of Project B is $Answermillion. (Round to two decimal places.)
(c) The NPV of Project C is $Answermillion. (Round to two decimal places.)
(d) If the firm can choose only one of these projects, which should it choose based on the NPV decision rule?
Project C
Project A
Project B
Cannot tell
(e) If the firm can choose any two of these projects, which should it choose based on the NPV decision rule?
Project A and Project B
Project C and Project B
Project C and Project A
Cannot tell
a. The NPV of Project A is computed as shown below:
= - $ 7 million + $ 15 million / 1.09
= $ 6.76 million
b. The NPV of Project B is computed as shown below:
= $ 7 million + $ 4 million / 1.09
= 10.67 million Approximately
c. The NPV of Project C is computed as shown below:
= $ 19 million - $ 6 million / 1.09
= $ 13.50 million Approximately
d. If the firm can choose only one of these projects, it shall choose Project C, since it resulted in the highest NPV. So the correct answer is option of Project C.
e. If the firm can choose any two of these projects, it shall choose Project C and Project B, since the NPV's of these projects are greater than the NPV of project A. So the correct answer is option of Project C and Project B.
Feel free to ask in case of any query relating to this question
Your firm has identified three potential investment projects. The projects and their cash flows are shown...
Your firm has identified three potential investment projects. The projects and their cash flows are shown here: (Click on the icon located on the top-right corner of the data table below in order to copy its contents into a spreadsheet.) Project Cash Flow Today (millions) Cash Flow in One Year (millions) A -$15 $$16 B $4 $3 C $17 −$11 Suppose all cash flows are certain and the risk-free interest rate is 6%. a. What is the NPV of each...
Your firm has identified three potential investment projects. The projects and their cash flows are shown here: Cash Flow Today (millions) $7 $7 $18 Cash Flow in One Year (millions) $23 $3 -$8 Project Suppose all cash flows are certain and the risk-free interest rate is 11%. a. What is the NPV of each project? b. If the firm can choose only one of these projects, which should it choose? c. If the firm can choose any two of these...
U2 - 6 ?(Round to two decimal? places.) Your firm has identified three potential investment projects. The projects and their cash flows are shown here: Cash Flow Today (millions) -$14 $4 S22 Cash Flow in One Year (millions) 523 $4 - $7 Project Suppose all cash flows are certain and the risk-free interest rate is 9% a. What is the NPV of each project? b. If the firm can choose only one of these projects, which should it choose? c....
(1)Your firm has identified three potential investment projects. The projects and their cash flows are shown here (Project Cash Flow Today ($) Cash Flow in One Year ($)) A -10- 20 B 5 -5 C 20 -10 Suppose all cash flows are certain and the risk-free interest rate is 10%. a. What is the NPV of each project? b. If the firm can choose only one of these projects, which should it choose? c. If the firm can choose any...
Garage, Inc., has identified the following two mutually exclusive projects: Year ON+ Cash Flow (A) -$ 29,300 14,700 12,600 9,350 5,250 Cash Flow (B) $ 29,300 4,450 9,950 15,500 17,100 a-1 What is the IRR for each of these projects? (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) IRR Project A Project B a-2 Using the IRR decision rule, which project should the company accept? O Project A Project B...
Bruin, Inc., has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$ 29,700 –$ 29,700 1 15,100 4,650 2 13,000 10,150 3 9,550 15,900 4 5,450 17,500 a-1 What is the IRR for each of these projects? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) Project A ? Project B ? a-2 Using the IRR decision rule, which project should...
Garage, Inc., has identified the following two mutually exclusive projects: Year Cash Flow (A) -$ 29,300 14,700 12.600 9,350 5,250 Cash Flow (B) $ 29,300 4,450 9,950 15,500 17,100 a-1 What is the IRR for each of these projects? (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) IRR Project A Project B a-2 Using the IRR decision rule, which project should the company accept? O Project A O Project B...
Bruin, Inc., has identified the following two mutually exclusive projects: Year 0 هه Cash Flow (A) -$28,700 14,100 12,000 9,050 4,950 Cash Flow (B) -$28,700 4,150 9,650 14,900 16,500 م ليا 6.66 points ط eBook 8-1 What is the IRR for each of these projects? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places. e.a.. 32.16.) Print References Project A Project B a-2 Using the IRR decision rule, which project should the...
Bruin, Inc. has identified the following two mutually exclusive projects Cash Flow (A) -$28.700 14,100 12.000 9.050 4.950 Cash Flow (B) -$28,700 4,150 9.650 14.900 16.500 6-1 What is the IRR for each of these projects (Do not round Intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e... 32.16.) Project A Project B 2-2 Using the IRR decision rule, which project should the company accept? Project A Project B &-3 is this decision necessarily...
PLEASE SHOW WORK AND CALCULATIONS THANKS Bumble's Bees, Inc., has identified the following two mutually exclusive projects: Cash Flow (A) Cash Flow (B) Year 0 17,000 8,000 7,000 5,000 3,000 17,000 2,000 5,000 4 What is the IRR for each of these projects? If you apply the IRR decision rule, which project should the company accept? Is this decision necessarily correct? If the required return is 11%, what is the NPV for each of these projects? which project will you...