Question

You are considering a proposal to produce and market a new sluffing machine. The most likely...

You are considering a proposal to produce and market a new sluffing machine. The most likely outcomes for the project are as follows:

Expected sales: 115,000 units per year

Unit price: $220

Variable cost: $132

Fixed cost: $4,890,000

The project will last for 10 years and requires an initial investment of $16.70 million, which will be depreciated straight-line over the project life to a final value of zero. The firm’s tax rate is 30%, and the required rate of return is 12%.

However, you recognize that some of these estimates are subject to error. Sales could fall 30% below expectations for the life of the project and, if that happens, the unit price would probably be only $210. The good news is that fixed costs could be as low as $3,260,000, and variable costs would decline in proportion to sales.

a. What is project NPV if all variables are as expected?

NPV =

b. What is NPV in the worst-case scenario?

NPV =

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Part a:
Calculation of Net Present value of the project if all variables are as expected
Particulars 0 1 2 3 4 5 6 7 8 9 10
Initial Investment
Investment (A) -16700000
Operating Cash Flows
Sales Revenue
(115,000 * $220)
25300000 25300000 25300000 25300000 25300000 25300000 25300000 25300000 25300000 25300000
Less: Variable Costs
(115,000 * $132)
-15180000 -15180000 -15180000 -15180000 -15180000 -15180000 -15180000 -15180000 -15180000 -15180000
Less: Fixed Costs -4890000 -4890000 -4890000 -4890000 -4890000 -4890000 -4890000 -4890000 -4890000 -4890000
Less: Depreciation
($16700000/10 years)
-1670000 -1670000 -1670000 -1670000 -1670000 -1670000 -1670000 -1670000 -1670000 -1670000
Profit Before Tax 3560000 3560000 3560000 3560000 3560000 3560000 3560000 3560000 3560000 3560000
Less: Tax@30% -1068000 -1068000 -1068000 -1068000 -1068000 -1068000 -1068000 -1068000 -1068000 -1068000
Profit After Tax 2492000 2492000 2492000 2492000 2492000 2492000 2492000 2492000 2492000 2492000
Add back Depreciation 1670000 1670000 1670000 1670000 1670000 1670000 1670000 1670000 1670000 1670000
Net Operating Cash Flows (B) 4162000 4162000 4162000 4162000 4162000 4162000 4162000 4162000 4162000 4162000
Total Cash Flows (C = A+B) -16700000 4162000 4162000 4162000 4162000 4162000 4162000 4162000 4162000 4162000 4162000
Discount Factor @12% (D)
1/(1+12%)^n
n=0,1,2,3,4,5,6,7,8,9,10
1 0.89285714 0.79719388 0.71178025 0.63551808 0.56742686 0.50663112 0.45234922 0.40388323 0.36061002 0.32197324
Discounted Cash Flows (E = C*D) -16700000 3716071.43 3317920.92 2962429.39 2645026.24 2361630.57 2108598.73 1882677.43 1680961.99 1500858.92 1340052.61
Net Present value 6816228.24
Net Present value of the project if all variables are as expected is $6,816,228.24
Part b:
Sale Units = 115000 units - Reduction in Units (30%) = 80,500 units
Calculation of Net Present value of Worst Case Scenario
Particulars 0 1 2 3 4 5 6 7 8 9 10
Initial Investment
Investment (A) -16700000
Operating Cash Flows
Sales Revenue
(80,500 * $210)
16905000 16905000 16905000 16905000 16905000 16905000 16905000 16905000 16905000 16905000
Less: Variable Costs
(80,500 * $132)
-10626000 -10626000 -10626000 -10626000 -10626000 -10626000 -10626000 -10626000 -10626000 -10626000
Less: Fixed Costs -3260000 -3260000 -3260000 -3260000 -3260000 -3260000 -3260000 -3260000 -3260000 -3260000
Less: Depreciation
($16700000/10 years)
-1670000 -1670000 -1670000 -1670000 -1670000 -1670000 -1670000 -1670000 -1670000 -1670000
Profit Before Tax 1349000 1349000 1349000 1349000 1349000 1349000 1349000 1349000 1349000 1349000
Less: Tax@30% -404700 -404700 -404700 -404700 -404700 -404700 -404700 -404700 -404700 -404700
Profit After Tax 944300 944300 944300 944300 944300 944300 944300 944300 944300 944300
Add back Depreciation 1670000 1670000 1670000 1670000 1670000 1670000 1670000 1670000 1670000 1670000
Net Operating Cash Flows (B) 2614300 2614300 2614300 2614300 2614300 2614300 2614300 2614300 2614300 2614300
Total Cash Flows (C = A+B) -16700000 2614300 2614300 2614300 2614300 2614300 2614300 2614300 2614300 2614300 2614300
Discount Factor @12% (D)
1/(1+12%)^n
n=0,1,2,3,4,5,6,7,8,9,10
1 0.89285714 0.79719388 0.71178025 0.63551808 0.56742686 0.50663112 0.45234922 0.40388323 0.36061002 0.32197324
Discounted Cash Flows (E = C*D) -16700000 2334196.43 2084103.95 1860807.1 1661434.91 1483424.03 1324485.74 1182576.55 1055871.92 942742.788 841734.632
Net Present value -1928621.9
Net Present value of the worst case scenario of the project is ($1,928,621.9)
Add a comment
Know the answer?
Add Answer to:
You are considering a proposal to produce and market a new sluffing machine. The most likely...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The most likely outcomes for a particular project are estimated as follows: Unit price: $50 Variable...

    The most likely outcomes for a particular project are estimated as follows: Unit price: $50 Variable cost: $30 Fixed cost: $300,000 Expected sales: 30,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1 million, which will be depreciated straight-line over the...

  • You are considering a new product launch. The project will cost $750,000, have a four-year life,...

    You are considering a new product launch. The project will cost $750,000, have a four-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 180 units per year; price per unit will be $18,500, variable cost per unit will be $11,400, and fixed costs will be $522,000 per year. The required return on the project is 12 percent, and the relevant tax rate is 28 percent. a) Based on your experience, you think the...

  • You are considering a new product launch. The project will cost $920,000, have a 5-year life,...

    You are considering a new product launch. The project will cost $920,000, have a 5-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 310 units per year; price per unit will be $15,915, variable cost per unit will be $11,800, and fixed costs will be $605,000 per year. The required return on the project is 10 percent and the relevant tax rate is 24 percent. Based on your experience, you think the unit...

  • The most likely outcomes for a particular project are estimated as follows: Unit price: $50 Variable...

    The most likely outcomes for a particular project are estimated as follows: Unit price: $50 Variable cost: $30 Fixed cost: $300,000 Expected sales: 30,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1 million, which will be depreciated straight-line over the...

  • You are considering a new product launch. The project will cost $820,000, have a four-year life,...

    You are considering a new product launch. The project will cost $820,000, have a four-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 450 units per years; price per unit will be $18,000; variable cost per unit will be $15,400; and fixed costs will be $610,000 per year. The required return on the project is 15% and the tax rate is 35%. a) Based on your experience, you think the unit sales, variable...

  • You are considering a new product launch. The project will cost $720,000, have a 4-year life,...

    You are considering a new product launch. The project will cost $720,000, have a 4-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 380 units per year; price per unit will be $17,400; variable cost per unit will be $14,100; and fixed costs will be $680,000 per year. The required return on the project is 15 percent and the relevant tax rate is 21 percent. a. Based on your experience, you think the...

  • You are considering a new product launch. The project will cost $800,000, have a four-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 200 units per...

    You are considering a new product launch. The project will cost $800,000, have a four-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 200 units per year; price per unit will be $18,300, variable cost per unit will be $15,300, and fixed costs will be $630,000 per year. The required return on the project is 12 percent, and the relevant tax rate is 34 percent. a) Based on your experience, you think the...

  • You are considering a new product launch. The project will cost $1,600,000, have a four-year life,...

    You are considering a new product launch. The project will cost $1,600,000, have a four-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 160 units per year; price per unit will be $20,000, variable cost per unit will be $11,500, and fixed costs will be $470,000 per year. The required return on the project is 15 percent, and the relevant tax rate is 35 percent.    a. The unit sales, variable cost, and...

  • What are the best and worst case Variable cost? You are considering a new product launch....

    What are the best and worst case Variable cost? You are considering a new product launch. The project will cost $2,075,000, have a four- year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 220 units per year; price per unit will be $18,800, variable cost per unit will be $12,350, and fixed costs will be $610,000 per year. The required return on the project is 11 percent, and the relevant tax rate is...

  • The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60...

    The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60 Variable cost: $ 40 Fixed cost: $ 250,000 Expected sales: 30,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will be depreciated...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT