Rose is a project manager at the civil engineering consulting firm of sands, gravel, concrete, and waters, Inc. She has been collecting data on a project in which concrete pillars were being constructed, however not all the data are avaliable. She has been able to find out that the 8th pillar required 225 person hours to construct and that a 68% learning curve applied. She is interested in calculating the time required to construct the 1st and 25th pillars. Compute the values for her.
Rose is a project manager at the civil engineering consulting firm of sands, gravel, concrete, and...
Explain please. Rose is a project manager at the civil engineering consulting firm of Sands, Gravel, Concrete, and Waters, Inc. She has been collecting data on the project in which concrete pillars were being constructed, however not all the data are available. She has been able to find out that the 5th pillar required 150 person-hours to construct, and that a 80% learning curve applied If the time required to construct 1st pillar is 240, The time required to construct...