If the learning rate is 75%, the percentge improvement with eaach doubling of production will be 100x (1-0.75) =25%.
Option D is right
If the learning rate for a process is 75%, what is the percentage improvement rate for...
The first unit of a product took 80 days for production. The learning rate for the production process is 75%. How long will it take to make the 17th unit? (You can use Table E.3 in Module E (Learning Curves) of the textbook.) from 22 to 23 days from 24 to 25 days from 21 to 22 days from 25 to 26 days from 23 to 24 days The first unit of a product took 80 days for production. The...
CHAPTER 6: LEARNING CURVE (MONDAY) 1. The unit improvement factor for a 60 percent learning curve at 25 units is 0.0933. The first and second timings of a person doing a job are 5 minutes and 3 minutes respectively. What is the learning-adjusted time estimate for unit number 25? 2. You have just timed a person doing a job a few times. The first time it took the person 25 minutes, the second time it took 20 minutes, and the...
a) What percentage improvement is needed in the supply chain strategy for profit to improve to $40,000? What is the cost of material with a $40,000 profit? A decrease of ___% in material (supply-chain) costs is required to yield a profit of $40,000 for a new material cost of $____. B) What percentage improvement is needed in the sales strategy for profit to improve to $40,000? What must sales be for profit to improve to $40,000? An increase of __%...
Question also asks: PLEASE ANSWER b) What percentage improvement is needed in the sales strategy for profit to improve to $20,000? What must sales be for profit to improve to 20,000? Hau Lee Furniture, Inc., spends 55% o its sales dollars in the supply chain and finds its current profit of $15.000 equipment. Hau would like to improve the profit line to $20,000 so he can obtain the ban's approval for the loan adequate. The bank is insisting on an...
What learning experience do you think contribute to your improvement
A club would like to know what the learning rate is for a certain welded assembly. They conducted a study on a total of four assembles. However, the data on samples 2 and 3 were corrupted. The records for sample 1 and sample 4 were 6 hours and 4.86 hours respectively. Determine the learning rate for this assembly using (a) doubling method and (b) formula method. this is the whole question, nothing was added to it.
The first unit of a product took 500 hours to build, and the learning rate for the production process is 78%. How long will it take to make the 256th unit? (Use at least five decimals in the exponent if you use the logarithmic approaches.) from 75 to 85 hours from 85 to 95 hours from 65 to 75 hours from 95 to 105 hours from 55 to 65 hours
. Samples of 20 products from a production line are selected every hour. Typically, 2% of the products require improvement. Let X denote the number of products in the sample of 25 that require improvement. A production problem is suspected if X exceeds its mean by more than 3 standard deviations. (a) If the percentage of products that require improvement remains at 2%, what is the probability that X exceeds its mean by more than 3 standard deviations? (b) If...
The following data give the percentage of women working in five companies in the retail and trade industry. The percentage of management jobs held by women in each company is also shown. % Working 6745 73 54 61 % Management 51 2364 4632 (a Develop a scatter diagram for these data with the percentage of women working in the company as the independent variable. 20 20 50 . . 50 20 60 50! 60 50 40 60 50 40 Management...
6. In 1870 what percentage of Americans lived in the country or in small towns? a.75 b.50 c.25 d.43