CHAPTER 6: LEARNING CURVE (MONDAY) 1. The unit improvement factor for a 60 percent learning curve at 25 units...

CHAPTER 6: LEARNING CURVE (MONDAY)

1. The unit improvement factor for a 60 percent learning curve at 25 units is 0.0933. The first and second timings of a person doing a job are 5 minutes and 3 minutes respectively. What is the learning-adjusted time estimate for unit number 25?

2. You have just timed a person doing a job a few times. The first time it took the person 25 minutes, the second time it took 20 minutes, and the third time it took 17.55 minutes. What learning curve unit improvement factor should you use?

3. You have determined that a 75 percent learning curve is appropriate for a task. If the initial timing of the person performing that job was 50 minutes, and if you need the job performed 500 times, how many minutes of work will be required?

4. With an 80 percent unit improvement factor learning curve and an initial time of 100 minutes to do a job, at what number of repetitions will the job take less than 50 minutes?

5. The 50th repetition of a job is timed at 100 minutes. If the learning curve for this job is 90 percent, what is the estimated time for the 100th repetition of this job?



# i want to know how to calculate the solution


0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Learning Curve:

1.

Learning curve rate = 60% = 0.6

Unit improvement factor at 25 units = 0.0933

Time required for 1st unit = 5 minutes

The unit time for the nth unit can be calculated using learning curve formula as follows:

Tn = T1 x C

T1 = time required for first unit

Tn = time required for nth unit

C = unit improvement factor

T25 = T1 x C = 5 x 0.0933 = 0.4665 minute

Learning-adjusted time estimate for unit number 25 = 0.4665 minute

2.

T1 = time required for first unit = 25 minutes

T2 = time required for 2nd unit = 20 minutes

T3 = time required for 3rd unit = 17.55 minutes

Tn = time required for nth unit

Learning rate from 1st to 2nd unit = Time required for 2nd unit/time required for 1st unit = L2/ L1

T2/ T1 = 20/25 = 0.80

Learning curve improvement of 80% is appropriate for given process.

To confirming 80% learning curve, determine the time required for third unit.

The unit improvement factor for 3rd unit of 80% curve = 0.7021

The unit time for the nth unit can be calculated using learning curve formula as follows:

Tn = T1 x C

T3 = 25 x 0.7021 = 17.5525 minutes

Since, the calculated time and given time for the third unit is sam, the learning curve rate of 80% is correct.

3.

T1 = time required for first unit = 50 minutes

Learning curve rate = 75%

Total time required to perform the job n times = Tn = cumulative improvement factor x T1

cumulative improvement factor for 500 units (75% rate) = 63.68

Total time required to perform the job 500 times = 63.68 x 50 = 3184 minutes

4.

Learning curve rate = 80%

T1 = 100 minutes

Tn = 50 minutes

Tn = T1 x C

50 = 100 x C

C = 50/100 = 0.5

For the Job number that take less than 50 minutes, the unit improvement factor should be less than 0.5

From the learning curve table, for rate of 80%, the 9th unit results in unit improvement factor 0.4930.

9th unit will require less than 50 minutes for 80% learning curve rate.

5.

Learning curve rate = 90%

T50 = 100 minutes

T100 = estimated time of 100th repetition

C50 = unit improvement factor for 50th unit = 0.5518

C100 = unit improvement factor for 100th unit = 0.4966

T50 = T1 x C50

T100 = T1 x C100

T50/C50 = T100/C100

T100 = (T50/C50) x C100 = (100/0.5518) x 0.4966

T100 = 89.99

Estimated time for the 100th repetition of this job = 89.99 minutes

Add a comment
Know the answer?
Add Answer to:
CHAPTER 6: LEARNING CURVE (MONDAY) 1. The unit improvement factor for a 60 percent learning curve at 25 units...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • (1) Let us suppose it costs $70 to produce the 80th unit, assuming a learning rate...

    (1) Let us suppose it costs $70 to produce the 80th unit, assuming a learning rate of 95%, determine the cost of the 160th unit. (2) If the 4th unit took 24 hours to produce, and the 20th unit took 19 hours to produce, what would the learning rate be? Note: Express your answer in decimal places, i.e., if your answer is 40.56%, enter in 0.4056. (3) Let us suppose it costs $500 to produce the 120th unit, assuming a...

  • Impulse and Momentum Name: Date: TA's Name: Learning Objectives: 1. Understanding force ys time curves for...

    Impulse and Momentum Name: Date: TA's Name: Learning Objectives: 1. Understanding force ys time curves for a collision. 2. Calculating impulse using force vs. time curves. 3. Understanding the relationship between impulse and momentum. 4. Applying conservation of momentum for inelastic collisions. Apparatus: Aluminum track, track legs, two smart carts, two cart stops, and small black rectangular cart masses. Part A: Collision of a moving cart with a fixed cart cart 1 Cart stop stationary cart cart stop Consider the...

  • only questions number: #3,6,8,16,19,22 Δι CH 122 - Practice Problems for Chapter 12 Do NOT use...

    only questions number: #3,6,8,16,19,22 Δι CH 122 - Practice Problems for Chapter 12 Do NOT use this problem set solely as test preparation. This problem set does NOT cover everything that we have discussed in class. You will still need to study class materials in order to do well on the learning assessment. 1. Of the following all are valid units for a reaction rate except A. moll B. M/S C. molhr D.g's E.molle 2. Which one of the following...

  • STEP 1: In your own words define problem employees and the categories they may fall into....

    STEP 1: In your own words define problem employees and the categories they may fall into. For the second or last paragraph provide your opinion on which employee type is the most difficult. DEFINITION : I think that "problem employees" are employees that either directly or indirectly hinder the organization's mission or vision, and break down into roughly four categories. In general, problem employees can be classified into two broad categories - employees creating problems for the organization and employees...

  • Fraud at Berry, CPA’s BERRY, CERTIFIED PUBLIC ACCOUNTANTS Brief History of the Firm In 1999, John...

    Fraud at Berry, CPA’s BERRY, CERTIFIED PUBLIC ACCOUNTANTS Brief History of the Firm In 1999, John Berry graduated from college with an accounting degree. After 10 years at an international accounting firm, John decided to start his firm, Berry, CPA’s. The firm, located in Oakwood, caters to local clients; specifically, John and his staff of four professionals specialize in non-public companies. The majority of the services provided by Berry, CPA’s are tax planning and preparation; however, the firm also performs...

  • Please read the article and answer about questions. You and the Law Business and law are...

    Please read the article and answer about questions. You and the Law Business and law are inseparable. For B-Money, the two predictably merged when he was negotiat- ing a deal for his tracks. At other times, the merger is unpredictable, like when your business faces an unexpected auto accident, product recall, or government regulation change. In either type of situation, when business owners know the law, they can better protect themselves and sometimes even avoid the problems completely. This chapter...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT