Chapter 9 Applying Excel (B) Saved Requirement 2: Revise the data in your worksheet to reflect the results for the subsequenta. What is the activity variance for revenue? (Indicate the effect of each variance by selecting F for favorable, U for ub. What is the spending variance for the cost of ingredients? (Indicate the effect of each variance by selecting F for favoc. What is spending variance for wages and salaries? (Indicate the effect of each variance by selecting F for favorable, Ud. What is spending variance for total expenses? (Indicate the effect of each variance by selecting F for favorable, U fo

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans:

a                          
Activity variance for revenue =Actual revenue-Planning budgeted revenue= (1800*16.50)-(1700*16.50)=1650   F  
b                          
Spending variance for the cost of ingredients = Actual  Cost of Ingredients-Budgeted cost for actual meals served= 11140-(1800*6.25)=110   F  
c                          
Spending variance for wages and salaries =Actual  Cost of wages and salaries-Budgeted cost =10640-10400=240   U  
d                          
Actual total expenses =11140+10640+1170+220+2005=27155                   27155      
Flexible budget total expenses = (1800*6.25)+10400+800+(1800*0.2)+2200+600+(1800*0.8)=27050                           27050
Spending variance for total expenses = 27155-27050=105 U                          

Add a comment
Know the answer?
Add Answer to:
Chapter 9 Applying Excel (B) Saved Requirement 2: Revise the data in your worksheet to reflect...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Revise the data in your worksheet to reflect the results for the subsequent period as shown below: Chapter 9:...

    Revise the data in your worksheet to reflect the results for the subsequent period as shown below: Chapter 9: Applying Excel Data Revenue $16.50 q Cost of ingredients $6.25 q Wages and salaries $10,400 Utilities $800 + $0.20 q Rent $2,200 Miscellaneous $600 + $0.80 q Actual results: Revenue $29,445 Cost of ingredients $11,425 Wages and salaries $10,605 Utilities $1,190 Rent $2,200 Miscellaneous $2,045 Planning budget activity 1,700 meals served Actual activity 1,800 meals served a. What is the activity...

  • Revise the data in your worksheet to reflect the results for the subsequent period as shown...

    Revise the data in your worksheet to reflect the results for the subsequent period as shown below: a. What is the activity variance for revenue? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance)). b. What is the spending variance for the cost of ingredients? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance))....

  • revise the data in your worksheet to reflect the results for the subsequent period as shown...

    revise the data in your worksheet to reflect the results for the subsequent period as shown below: a. What is the activity variance for revenue? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance)). b. What is the spending variance for the cost of ingredients? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance))....

  • Chapter 10: Applying Excel: Exercise (Part 2 of 2) Requirement 2: Revise the data in your...

    Chapter 10: Applying Excel: Exercise (Part 2 of 2) Requirement 2: Revise the data in your worksheet to reflect the results for the subsequent period as shown below: A 1 Chapter 10: Applying Excel 3 4 Data Exhibit 10-1: Standard Cost Card Inputs 6 Direct materials Standard Quantity 3.0 pounds 0.50 hours 0.50 hours Standard Price 4.00 per pound 22.00 per hour 6.00 per hour 7 Direct labor Variable manufacturing overhead 8 9 10 Actual results: 11 Actual output Actual...

  • Requirement 2: Revise the data in your worksheet to reflect the results for the subsequent period...

    Requirement 2: Revise the data in your worksheet to reflect the results for the subsequent period as shown below: Chapter 10: Applying Excel M Data Exhibit 10-1: Standard Cost Card Inputs Direct materials Direct labor Variable manufacturing overhead 6 Standard Quantity 3.0 pounds 0.50 hours 0.50 hours $ $ $ Standard Price 4.00 per pound 22.00 per hour 6.00 per hour 8 10 Actual results: Actual output Actual variable manufacturing overhead cost 12 $ 13 14 2,050 units 6,526.50 Actual...

  • Chapter 9: Applying Excel $16.50 9 $6.25 9 Data Revenue Cost of ingredients Wages and salaries...

    Chapter 9: Applying Excel $16.50 9 $6.25 9 Data Revenue Cost of ingredients Wages and salaries Utilities Rent Miscellaneous $0.20 g $10,400 $800 $2,200 $600 $0.80 g Actual results: Revenue Cost of ingredients Wages and salaries Utilities Rent Miscellaneous $27.920 $11,110 $10,130 $1.080 $2,200 $2,240 Planning budget activity Actual activity 1.800 meals served 1,700 meals served Enter a formula into each of the cells marked with a ? below Review Problem: Variance Analysis Using a Flexible Budget Construct a flexible...

  • Revise the data in your worksheet to reflect the results for the subsequent period as shown...

    Revise the data in your worksheet to reflect the results for the subsequent period as shown below: A B C D E 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Chapter 09: Applying Excel Data Exhibit 9-8: Standard Cost Card Inputs Standard Quantity Standard Price Direct materials 3.0 pounds $4.00 per pound Direct labor 0.50 hours $22.00 per hour Variable manufacturing overhead 0.50 hours $6.00 per hour Actual results: Actual output 2,040 units...

  • Check my work TB Problem Qu. 9-389 Bickel Corporation uses customers served as... Bickel Corporation uses...

    Check my work TB Problem Qu. 9-389 Bickel Corporation uses customers served as... Bickel Corporation uses customers served as its measure of activity. The following report compares the planning budget to the actual operating results for the month of November: Bickel Corporation Comparison of Actual Results to Planning Budget For the Month Ended November 30 Actual Planning Budget 34,000 Variances Results Customers served Revenue ($3.50q) Expenses: Wages and salaries ($23,400 + $1.24q) Supplies ($0.64q) Insurance ($5,300) Miscellaneous expense ($4,300 +...

  • Adger Corporation is a service company that measures its output based on the number of customers...

    Adger Corporation is a service company that measures its output based on the number of customers served. The company provided the following fixed and variable cost estimates that it uses for budgeting purposes and the actual results for May as shown below: Fixed Element per Month Variable Element per Customer Served Actual Total for May Revenue $ 5,700 $ 209,500 Employee salaries and wages $ 64,000 $ 1,100 $ 106,400 Travel expenses $ 560 $ 19,000 Other expenses $ 43,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT