Answers are in BOLD
Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | Total cost | |
Gross requirements GR | 30 | 0 | 30 | 0 | 30 | 60 | 20 | 0 | 20 | 70 | 0 | 60 | ||
Scheduled receipts SR | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||
safety stock, SS=0 | on hand at the end PIOH | 10 | 10 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Beginning inventory-280 | on hand at the beginning IOH | 40 | 10 | 10 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Requirement | -10 | -10 | 20 | 0 | 30 | 60 | 20 | 0 | 20 | 70 | 0 | 60 | ||
Net requirements NR | 0 | 0 | 20 | 0 | 30 | 60 | 20 | 0 | 20 | 70 | 0 | 60 | ||
Q = 100 | Planned order receipts (PR) | 0 | 0 | 20 | 0 | 30 | 60 | 20 | 0 | 20 | 70 | 0 | 60 | |
Lead Time LT=1 | Planned order releases POR | 0 | 20 | 0 | 30 | 60 | 20 | 0 | 20 | 70 | 0 | 60 | 0 | |
Holding cost= $1.5* PIOH | 15 | 15 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 30 | |
setup cost (whenever there is new order reciept) | 0 | 0 | 200 | 0 | 200 | 200 | 200 | 0 | 200 | 200 | 0 | 200 | 1400 |
Answer b: Total cost= cost of setup + cost of holding imventory= 30+1400= $1430
repeat these steps for every week | |||
step 1 | IOH= | PIOH of last week | |
step 2 | Requirement= | GR-IOH-SR+SS | |
step 3 | NR= | is equal to requirement (if requirement>0) OR 0 (if requirement is negative) | |
step 4 | PR= | in L4L PR=NR | more than or equal to NR in multiples of lot size |
step 5 | PIOH= | IOH+PR-GR-SR | |
step 6 | POR= | PR of preceding week | |
step 7 (After completing whole MRP) | Holding cost= | 1.5$*PIOH |
Please ask, if you have any doubts through the comment section. Do rate the answer
B. TOTAL COST________ Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements...
Problem 14.22 Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table Period 1 2 3 4 5 6 789 10 11 12 Gross requirements 30 40 40 70 20 10 80 60 Holding cost$1.50unit/week; setup cost $150; lead time 1 week; beginning inventory 40 Develop a lot-for-lot solution (enter your responses as whole numbers). Period 1 2 3 4 5 6 78 9 0 11 12 Gross requirements 40 40 70 20...
Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table*. Period | 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements | 30 40 30 70 30 20 70 50 *Holding cost = $3.50/unit/week; setup cost = $150; lead time = 1 week; beginning inventory = 40. Develop a lot-for-lot solution (enter your responses as whole numbers). 2 4 8 11 3 40 5 30 6 70 7...
Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table Period 1 23 4 5 6 7 89 10 12 Gross requirements 30 40 40 70 20 10 80 60 Holding cost $1.50/unit/week; setup cost $150; lead time 1 week; beginning inventory 40 Develop a lot-for-lot solution (enter your responses as whole numbers) Period 1 2 3 45 6 7 8 9 10 111 Gross requirements 30 40 40 70 20 10 80...
3. Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table" Period 1 2 3 4 5 6 789 10 12 Gross requirements20 40 40 70 30 10 70 50 Holding cost- $3.50/unit/week; setup cost $150; lead time 1 week; beginning inventory 40 Develop a lot-for-lot solution (enter your responses as whole numbers) Period Gross 3 4 5 6 9 20 40 40 70 30 10 uirements On-hand at beginning of On-hand at...
The total cost is $____ )enter your response as a whole number) Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table*. Period 1 6 11 12 2 4 7 8 10 Gross requirements 30 70 30 10 80 20 30 60 Holding cost= $3.50/unit/week; setup cost = $150; lead time= week; beginning inventory 40. Develop a lot-for-lot solution (enter your responses as whole numbers). Period 1 2 3 6 7 10 12...
second question to this is What is the total cost? thank you. Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table" Period 12 3 4 5 6 7 8 9 10 11 12 Gross requirements20 30 40 60 20 10 80 60 Holding cost $2.50/unit/week, setup cost $150; lead time 1 week, beginning inventory 40 Develop a lot-for-lot solution (enter your responses as whole numbers). Period Gross requirements On-hand at beginning of...
What will the total cost be? (nearest whole number) Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table". Period 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements 20 40 40 60 30 10 80 50 "Holding cost = $3.50/unit/week; setup cost = $200; lead time = 1 week; beginning inventory = 40. Develop a lot-for-lot solution (enter your responses as whole numbers). Period 1 2 3...
Best-Appliance makes high-powered industrial strength microwave oven and wants to create an MRP for their oven assembly with a minimum cost possible. Following table show gross requirements of their product for twelve weeks. Develop a Part Period Balancing (PPB) solution and calculate the total relevant costs for the plan Week 1 2 3 4 5 6 8 10 11 12 7 Gross requirements 20 40 40 70 30 10 80 40 Also, for this plan the Holding cost $2.50/unit/week; setup...
Sigma Electronics produces telephone cameras for cell phone. The production manager would like to create an MRP for their cell phone cameras with a minimum cost possible. The following table show gross requirements of the product Develop a Part Period Balancing (PPB) solution and calculate the total relevant costs for the MRP. 2 4 8 11 Period Gross requirements 1 20 3 40 5 40 6 60 7 30 9 20 10 70 12 50 Also, for this plan the...
Best-Appliance makes high-powered industrial strength microwave oven and wants to create an MRP for their oven assembly with a minimum cost possible. Following table show gross requirements of their product for twelve weeks. Develop a Part Period Balancing (PPB) solution and calculate the total relevant costs for the plan. Week 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements 20 30 40 60 20 10 80 40 Also, for this plan the Holding cost =$2.50/unit/week;...