Item Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 30 | 0 | 40 | 0 | 30 | 70 | 30 | 0 | 20 | 70 | 0 | 50 |
Projected on hand at beginning 40 | 40 | 10 | 10 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Projected on hand at end of period | 10 | 10 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Net requirements | 0 | 0 | 30 | 0 | 30 | 70 | 30 | 0 | 20 | 70 | 0 | 50 |
Planned order receipts | 0 | 30 | 0 | 30 | 70 | 30 | 0 | 20 | 70 | 0 | 50 | |
Planned order release | 0 | 30 | 0 | 30 | 70 | 30 | 0 | 20 | 70 | 0 | 50 | 0 |
Number of set ups = 7
set up cost =150x7 =1050
AVg inventory =40
Inventory cost =3.5 x40 = 140
Total cost = 1190
Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following...
Problem 14.22 Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table Period 1 2 3 4 5 6 789 10 11 12 Gross requirements 30 40 40 70 20 10 80 60 Holding cost$1.50unit/week; setup cost $150; lead time 1 week; beginning inventory 40 Develop a lot-for-lot solution (enter your responses as whole numbers). Period 1 2 3 4 5 6 78 9 0 11 12 Gross requirements 40 40 70 20...
3. Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table" Period 1 2 3 4 5 6 789 10 12 Gross requirements20 40 40 70 30 10 70 50 Holding cost- $3.50/unit/week; setup cost $150; lead time 1 week; beginning inventory 40 Develop a lot-for-lot solution (enter your responses as whole numbers) Period Gross 3 4 5 6 9 20 40 40 70 30 10 uirements On-hand at beginning of On-hand at...
B. TOTAL COST________ Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table*. Period 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements | 30 30 30 60 20 20 70 60 *Holding cost = $1.50/unit/week; setup cost = $200; lead time = 1 week; beginning inventory = 40. Develop a lot-for-lot solution (enter your responses as whole numbers). 11 9 20 10 70 12 60 Period 1...
Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table Period 1 23 4 5 6 7 89 10 12 Gross requirements 30 40 40 70 20 10 80 60 Holding cost $1.50/unit/week; setup cost $150; lead time 1 week; beginning inventory 40 Develop a lot-for-lot solution (enter your responses as whole numbers) Period 1 2 3 45 6 7 8 9 10 111 Gross requirements 30 40 40 70 20 10 80...
The total cost is $____ )enter your response as a whole number) Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table*. Period 1 6 11 12 2 4 7 8 10 Gross requirements 30 70 30 10 80 20 30 60 Holding cost= $3.50/unit/week; setup cost = $150; lead time= week; beginning inventory 40. Develop a lot-for-lot solution (enter your responses as whole numbers). Period 1 2 3 6 7 10 12...
What will the total cost be? (nearest whole number) Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table". Period 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements 20 40 40 60 30 10 80 50 "Holding cost = $3.50/unit/week; setup cost = $200; lead time = 1 week; beginning inventory = 40. Develop a lot-for-lot solution (enter your responses as whole numbers). Period 1 2 3...
second question to this is What is the total cost? thank you. Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table" Period 12 3 4 5 6 7 8 9 10 11 12 Gross requirements20 30 40 60 20 10 80 60 Holding cost $2.50/unit/week, setup cost $150; lead time 1 week, beginning inventory 40 Develop a lot-for-lot solution (enter your responses as whole numbers). Period Gross requirements On-hand at beginning of...
Best-Appliance makes high-powered industrial strength microwave oven and wants to create an MRP for their oven assembly with a minimum cost possible. Following table show gross requirements of their product for twelve weeks. Develop a Part Period Balancing (PPB) solution and calculate the total relevant costs for the plan Week 1 2 3 4 5 6 8 10 11 12 7 Gross requirements 20 40 40 70 30 10 80 40 Also, for this plan the Holding cost $2.50/unit/week; setup...
Using gross requirements schedule below, prepare an alternative ordering system that always orders 100 units the week prior to a shortage (a fixed order quantity of 100) as a Lot Sizing technique. What is the cost of this ordering system? Period Gross requirements 25 20 50 0 10 40 30 0 30 65 1 2 3 45 6 7 8 9 10 Holding cost $1/unitweek; setup cost $200; lead time 1 week beginning inventory 25 units. Prepare a net requirements...
Sigma Electronics produces telephone cameras for cell phone. The production manager would like to create an MRP for their cell phone cameras with a minimum cost possible. The following table show gross requirements of the product Develop a Part Period Balancing (PPB) solution and calculate the total relevant costs for the MRP. 2 4 8 11 Period Gross requirements 1 20 3 40 5 40 6 60 7 30 9 20 10 70 12 50 Also, for this plan the...