Question

Show step by step solutions.

Maritime Shipbuilding is set to start building the first of six ships and to finish this ship within one year. Since they have little experience with this particular design (but can draw on a long history of building other ships), they have decided to approach the building of this first vessel as a project. (The experience gathered will be applied towards building the remaining five ships, so those will be built using a somewhat different mode of production.) Production of the first ship has been broken down into the following activities, with their precedence relations and three time estimates Time estimates (weeks Most ikely Activity Predecessors Opt Pess ExpectedStd.dev.Var Variance 10 16 20 25 14 25 12 19 6 10 1.5 18 2.333333 5.444444 1.5 12.5 1.833333 3.361111 4 0.333333 0.111111 8.5 2.25 B,C 18 6.5 2.25 D,E 12

(a) Complete the expected duration, standard deviation and variance for activities A and B and enter them into the table (provided above).

(b) Draw the Activity-on-node (AON) including the Start & Finish diagram and use the expected activity durations to complete a forward and backward pass (show calculations for ES,EF,LS,LF), create a table and show your work.

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Show step by step solutions. (a) Complete the expected duration, standard deviation and variance for activities...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Choose an event or significant task and prepare an activities list following a format similar to...

    Choose an event or significant task and prepare an activities list following a format similar to that used in the text, Table 9.3, Chapter 9, page 391. Be sure to include the immediate predecessors. Then, create a project network similar to that shown in Figure 9.7, Chapter 9, page 392. Do NOT include times for the activities and do NOT attempt to determine the critical path. Examples of events you might consider (there are many others): formal dinner for 5...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT