Choose an event or significant task and prepare an activities list following a format similar to that used in the text, Table 9.3, Chapter 9, page 391. Be sure to include the immediate predecessors.
Then, create a project network similar to that shown in Figure 9.7, Chapter 9, page 392.
Do NOT include times for the activities and do NOT attempt to determine the critical path.
Examples of events you might consider (there are many others):
formal dinner for 5 guests and yourself
graduation party
vacation or trip
construction or decorating project
lawn care
gardening project
auto maintenance or repair project
research project
Here are the figures from the book stated in the question to follow:
Home renovation project
Activity | Description | Predecessor activity | Duration ( Days) |
A | Analysis of tasks to be accomplished | None | 2 |
B | Looking out for options among professional renovation companies | A | 5 |
C | Select the partners ( Contractors) | B | 2 |
D | Preparation of budget with the contracting parties | C | 1 |
E | Removal of old paint, furniture, carpet, kitchen accessories etc | D | 3 |
F | Completion of construction work of Kitchen | E | 7 |
G | Completion of construction work of Living room | E | 10 |
H | Procurement of new accessories, furniture and appliances | E | 1 |
I | Fitment of kitchen accessories | F | 2 |
J | Painting, wallwork and interior decoration of the living room | G | 5 |
K | Installation of new carpet in the living room | J | 3 |
L | Finishing living room with new furniture | K | 2 |
M | Complete plumbing work of the kitchen | I | 3 |
N | Formal inspection and completion of work | M,L | 1 |
Choose an event or significant task and prepare an activities list following a format similar to...
You are responsible for managing a project with the following activities (all times are given in weeks): Optimistic Most Likely Pessimistic Immediate Time Predecessor(s) Time Activity Time 4 C, D D, E 12 4 8 6 4 What is the expected time of completion of the project? (weeks) (Include 1 decimal place, e.g.,3.1.) abs What is the probability that the project will be completed in 24 weeks or less? (Provide ab 2 decimal places, no 90 sign, e.g., 2.12 for...
QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are shown follow. Time Immediate Activity (weeks) Predecessor 2 5 В 4 C 5 В 6 В.С D,E F What are the slack times of Activities D and E? 0 and 0, respectively 1 and 1, respectively 2 and 0, respectively 0 and 1, respectively 1 and 0, respectively shown follow. A firm is planning a project for the...
Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...
A small software development project has eight major activities. The times are estimated and provided in the table below: Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 3 4 5 -- B 5 7 9 -- C 2 3 10 A D 2 5 8 B E 1 7 7 B F 3 5 7 C, D G 7 8 9 D, E H 2 6 10 F Answer the following questions based on above table 1-2...
Use Excel and show formulas used From the given table of activities and associated times, create a PERT/CPM diagram and complete the forward and backward passes Immediate Predecessor ActivityDescription Critical Path = Prepare Blue Print Receive Permits Prepare Ground Create Press ReleaseB Cement Work Steel Work Cut Ribbon Ceremony E Total Project Time C,D Pessimistic PERT Time Most Probable 17 12 4 Activit Optimistic 26 13 16 12 12 13
PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....
Hi, can you shaw haw yau 50t the answer. 2-1f need to pay extra let me ase Know. Steph Problem 1 R. C. COLEMAN R. C. Coleman distributes a variety of food products that are sold through grocery store and supermarket outlets. The company receives orders directly from the individual out- lets, with a typical order requesting the delivery of several cases of anywhere from 20 to 50 different products. Under the company's current warehouse operation, warehouse clerks dispatch order-picking...
1. Sid Orland is involved in planning a scientific research project. The activities are displayed in the following diagram. Optimistic, most likely, and pessimistic time estimates are displayed in the following table. Figure for Problem 1. r e 14 16 E 4 H 4 7 11 7 11 16 20 G 5 0 33 611 16 11 16 D 3 Most Likely Pessimistic Activity Optimistic 4 4 (a) Determine the expected times and variances for each activity along the critical...
5. A competitor of Kozar International, Inc. has begun marketing a new instant developing film project. Kozar has had a similar product under study in its R&D department but has not yet been able to begin production. Because of the competitor's action, top managers have asked for a speedup of R&D activities so that Kozar can produce and market instant film at the earliest possible date. The predecessor information and activity time estimates in months are shown in the next...
2. Consider the network described in the table below. Immediate Activity Predecessor(s)Pessimistic Probable Optimistic 15 10 8 K 9 8 7 L 10 6 5 M 3 3 3 N KM 9 5 1 O KM 10 7 4 P LN 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path. (c) Calculate the probability that the project will...