Question

PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A -...

PERT Analysis: The following represents a project with four activities. All times are in weeks.

Activity

Immediate

Predecessor

Optimistic

Time

Most

Likely

Time

Pessimistic

Time

A

-

3

8

14

B

-

8

8

8

C

A

6

9

18

D

B

6

11

17

According to the data in the above Table:

What is the critical path?

What is the minimum expected completion time for the project?

According to the above Table, there are four activities in the project. Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time. If you wished to find the probability of finishing the project in 20 weeks or fewer, it would be necessary to find the variance and then the standard deviation to be used with the normal distribution. What is the probability of completing this project in 20 weeks or fewer?

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Activi Most likel Expected time Optimistic Pessimistic Variance ((D2-B2)/6)42 ((D3-B3)/6)42 (D4-B4)/6)A2 ((D5-B5)/6)42 B2+C2*

13 1 Activity Optimistic Most likely Pessimistic Expected time Variance 1A 8.17 8.00 10.00 3.361 U.KX) 생.(XX) 3.361 18 17

R-11 IIT 9.1千 9 IT

To delamini piobabilty, e E) cp X→ Xia, duration inquest On , X, 2,0 20-19-)# 0-453 -833

Add a comment
Know the answer?
Add Answer to:
PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A -...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT