Question

Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...

  1. Consider the network described in the table below.

Activity

Immediate

Predecessor(s)

Pessimistic

Probable

Optimistic

J

--

15

10

8

K

--

9

8

7

L

J

10

6

5

M

J

3

3

3

N

K, M

9

5

1

O

K, M

10

7

4

P

L, N

10

8

3

Draw the network diagram and answer the following questions.

(a) Calculate the expected duration of each activity.

(b) Calculate the expected duration and variance of the critical path.

(c) Calculate the probability that the project will be completed in fewer than 30 time units.

Task

Early Start

Early Finish

Late

Start

Late Finish

Slack

Mean

Variance

J

0

K

0

L

M

N

O

P

Project

Project

Std.dev

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Below is the screenshot of the formula applied -

XUS 2020 - Excel FILE HOME INSERT PAGE LAYOUT FORMULAS DATA REVIEW VIEW Dynamics AX ? А e Define Name - Trace Precedents 15 S

Below is the screenshot of the result -

XUS 2020 - Excel FILE HOME INSERT PAGE LAYOUT FORMULAS DATA REVIEW VIEW Dynamics AX Trace Pre fx Σ Trace De Insert Function ?

Add a comment
Know the answer?
Add Answer to:
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT