Question

Use the network activity diagram and table below to answer questions 45-53. Activity Optimistic Most Probable Pessimistic A 5

Use the network activity diagram and table below to answer questions 45-53. Optimistic Most Probable Pessimistic Activity 5 7

Use the network activity diagram and table below to answer questions 45-53. Optimistic Most Probable Pessimistic Activity 7 B

Use the network activity diagram and table below to answer questions 45-53. Activity Optimistic Most Probable Pessimistic A 5 7 B 3 5 7 C 1 2 9 5 E 3 4 2 3 10 G 6 7 14 H 4 12 B G E H. C A. Finish Start F D Using the three time estimate approach, what is the value of uC? O 6 O4 None of the above are correct
Use the network activity diagram and table below to answer questions 45-53. Optimistic Most Probable Pessimistic Activity 5 7 5 C 1 2 5 5 E 5 E 2 3 10 G 6 7 14 H 5 12 B G E H. C A Finish Start F. D. The standard deviation (o) needed to evaluate uncertainty in the entire project (round to two decimals) 2.03 2.78 1.45 1.67 None of the above are correct B A
Use the network activity diagram and table below to answer questions 45-53. Optimistic Most Probable Pessimistic Activity 7 B 3 5 7 C 2 5 5 5 E 3 4 5 2 3 10 G 6 7 14 4 H 12 B G A. Finish Start What is the probability that the project will take MORE THAN 26 days to complete? (round the Z calculation to one decimal AND then round your final answer to the nearest second decimal place)? O 15.75% 11.51% 83.77% 88.49% None of the above o an UA
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Date Tutorial No Subject Pessimistic te Most Que 20 ophimistic (to) Activity (tp) Probable ltm) 0.4-44 7 7 A 0.4.44 1.777 2.LC Critrcal Vayiance Vay (A) +yarB)+ var (E) +VartG) 044 4 t0 4 44 +0.111 - 2776 = L67 2 776 Std deviation- evaluate The stdDate Tutorial No.: Subject: - 2¢ Expected Projee t length AtetEG where 2.6-74 P(Z 1-197 0. 115| = |1.51% T67 SatisPied Thank

Add a comment
Know the answer?
Add Answer to:
Use the network activity diagram and table below to answer questions 45-53. Activity Optimistic Most Probable...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT