Question

Estimated activity times and precedences are given below: Activity Optimistic Most Likely Pessimistic Required Precedence A...

Estimated activity times and precedences are given below:

Activity Optimistic Most Likely Pessimistic Required Precedence
A 6 7 14
B 8 10 12
C 2 3 4
D 6 7 8 A
E 5 5.5 9 B, C
F 5 7 9 B, C
G 4 6 8 D, E
H 2.7 3 3.5 F

What is the probability that the project will be completed within:

A. 21 Days

B. 22 Days

C. 25 Days

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Activity Optimistic time-a Expected completion time-m Pessimistic time-b Expected time= (a+4*m+ b)/6 Variance, (sigma)^2= (b-a/6)^2
A 6 7 14 8.00 1.78
B 8 10 12 10.00 0.44
C 2 3 4 3.00 0.11
D 6 7 8 7.00 0.11
E 5 5.5 9 6.00 0.44
F 5 7 9 7.00 0.44
G 4 6 8 6.00 0.44
H 2.7 3 3.5 3.03 0.02
Path Duration
ADG 21.00
BEG 23.00
BFH 20.03
CEG 15.00
CFH 13.03

Expected project duration is 23 days through BEG

Answer: the probability that the project will be completed within:

A. 21 Days: 0.0416

step 1 we will find the variance of the tasks which lie on critical path 1.33
step 2 mean project time (u) of critical path is= 23.00
step 3 Required completion time is 21
step 4 standard deviation= sqrt(variance)=   1.155
step 5 because Z= (given completion time- u)/standard deviation -1.732
step 6 P(z)= using NORM.S.DIST(z,true) 0.0416

Answer: the probability that the project will be completed within:

B. 22 Days: 0.1932

step 1 we will find the variance of the tasks which lie on critical path 1.33
step 2 mean project time (u) of critical path is= 23.00
step 3 Required completion time is 22
step 4 standard deviation= sqrt(variance)=   1.155
step 5 because Z= (given completion time- u)/standard deviation -0.866
step 6 P(z)= using NORM.S.DIST(z,true) 0.1932

Answer: the probability that the project will be completed within:

C. 25 Days: 0.9584

step 1 we will find the variance of the tasks which lie on critical path 1.33
step 2 mean project time (u) of critical path is= 23.00
step 3 Required completion time is 25
step 4 standard deviation= sqrt(variance)=   1.155
step 5 because Z= (given completion time- u)/standard deviation 1.732
step 6 P(z)= using NORM.S.DIST(z,true) 0.9584

Please ask, if you have any doubts through the comment section

Do rate the answer

Add a comment
Know the answer?
Add Answer to:
Estimated activity times and precedences are given below: Activity Optimistic Most Likely Pessimistic Required Precedence A...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Given the following activity list and times in days: (15 points) Activity           Optimistic       Most Likely     Pessimistic...

    Given the following activity list and times in days: (15 points) Activity           Optimistic       Most Likely     Pessimistic                         Time                Time                Time A                     7                      10                    12 B                     6                      8                      14 C                     5                      9                      12 D                     12                    14                    21 E                      10                    12                    15 F                      4                      5                      8 G                     1                      3                      8 H                     12                    15                    17 NOTE 1: ASSUME THE CRITTCAL PATH IS “B-E-H”. Calculate the schedule duration of the critical path in days. What is the probability of the project being completed...

  • 123) Given (Time in weeks): Activity Optimistic Most Likely Pessimistic A 3 4 5 B 6...

    123) Given (Time in weeks): Activity Optimistic Most Likely Pessimistic A 3 4 5 B 6 7 14 C 2 3 10 D 6 9 12 E 4 5 12 F 1 3 11 G 1 2 9 H 2 5 8 I 1 4 7 Determine: (a) the critical path. ( HOW DO I DO THIS WITH OUT A PREDECESSOR?) (b) the probability that the project will be completed in 22 weeks.

  • The following table shows estimates of activity times (weeks) for a project: Activity Optimistic Time Most...

    The following table shows estimates of activity times (weeks) for a project: Activity Optimistic Time Most Probable Time Pessimistic Time A 3 4.5 9 B 1.5 2 2.5 C 5 6 7 D 4 4.5 8 E 5 6 7 F 1 2.5 7 G 7 9 11 Suppose that the critical path is A-B-D-F-G. Use Appendix A to answer the questions. Do not round intermediate calculations. Round your answers to three decimal places. What is the probability that the...

  • Suppose that the following estimates of activity times (in weeks) were provided for the network shown...

    Suppose that the following estimates of activity times (in weeks) were provided for the network shown below: Activity Optimistic Most Probable Pessimistic A 4 6 8 B 2.5 4.5 5.5 C 5 6.5 8 D 4 5.5 8 E 6.5 7.5 9 F 2 3.5 5 G 7 9 12 H 5 6 13 What is the probability that the project will be completed. If required, round your answers to four decimal places. Within 20 weeks? Within 22.5 weeks? Within...

  • Activity Predecessor Optimistic time Most likely time Pessimistic time A - 3 5 8 B -...

    Activity Predecessor Optimistic time Most likely time Pessimistic time A - 3 5 8 B - 4 6 10 C A,B 2 5 8 D B 3 5 9 E A,C 3 6 9 F C,E 1 3 5 G C,D 3 4 9 H D 4 6 10 I F,G 3 4 9 J H 2 4 6 A).Draw the project network b).what is the expected completion time of the project. c) after your calculation, if you find one...

  • (15 points) Activity Immediate Predecessor Optimistic Time Most likely Time Pessimistic Time A NONE 4 7...

    (15 points) Activity Immediate Predecessor Optimistic Time Most likely Time Pessimistic Time A NONE 4 7 9 B A 2 4 6 C A 6 9 9 D B, C 5 5 5 E C 2 5 9 F D, E 3 3 6 Use both the longest path method and ES/EF; LS/LF method for the following questions (e) What are the slack values for non-critical activities? (4 points)       (f) What is the probability that the project will be...

  • Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) PESSIMISTIC TIME days) MOST LIKELY...

    Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) PESSIMISTIC TIME days) MOST LIKELY TIME (days) 10 10 10 B.C DE The total slack for activity D is O 2 O O O

  • TIMES (days) Activity Start Node Finish Node OPTIMISTIC to MOST LIKELY tm PESSIMISTIC tp A 1...

    TIMES (days) Activity Start Node Finish Node OPTIMISTIC to MOST LIKELY tm PESSIMISTIC tp A 1 2 24 30 42 B 1 3 20 23 32 C 2 5 15 27 39 D 3 4 25 43 61 E 4 5 15 42 69 Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity A………te = 31 Standard Deviation = 3 Activity B………te = Standard Deviation = Activity C………te...

  • Activity Predecessor Optimistic Time (a) Most Probable Time (m) Pessimistic Time (b) A None 2 6...

    Activity Predecessor Optimistic Time (a) Most Probable Time (m) Pessimistic Time (b) A None 2 6 10 B None 2 4 6 C A 2 4 6 D A 4 6 8 E B 6 8 22 F B 6 8 10 G C,D 2 8 12 H E,F 2 7 12 I G,H 4 8 16 Question for Blank 1: What is the Critical Path? Question for Blank 2: What is the Expected Duration of the Project? round to...

  • Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m...

    Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m b Time (t) o 2 3 2 1 B с D NWN mlm A 1 A,B 2 4 1 6 7 9 F 1 с с DE F,G 4 2 5 3 G 4 12 H 2 4 From the table above find the flowing answers. 1. Construct the project Network 2. Find the expected duration and Variance of each activity 3. Find the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT