1.SLACK OF D = A. 2
EXPECTED TIME = (OPTIMISTIC TIME + (4 * MOST LIKELY TIME) + PESSIMISTIC TIME) / 6
VARIANCE = ((PESSIMISTIC TIME - OPTIMISTIC TIME) / 6)^2
ACTIVITY |
EXPECTED TIME |
VARIANCE |
A |
(5 + (4 * 10) + 15) / 6 = 10 |
((15 - 5) / 6)^2 = 2.7778 |
B |
(10 + (4 * 12) + 14) / 6 = 12 |
((14 - 10) / 6)^2 = 0.4444 |
C |
(10 + (4 * 10) + 10) / 6 = 10 |
((10 - 10) / 6)^2 = 0 |
D |
(2 + (4 * 4) + 6) / 6 = 4 |
((6 - 2) / 6)^2 = 0.4444 |
E |
(4 + (4 * 8) + 12) / 6 = 8 |
((12 - 4) / 6)^2 = 1.7778 |
F |
(4 + (4 * 8) + 12) / 6 = 8 |
((12 - 4) / 6)^2 = 1.7778 |
G |
(10 + (4 * 12) + 14) / 6 = 12 |
((14 - 10) / 6)^2 = 0.4444 |
I |
(4 + (4 * 8) + 12) / 6 = 8 |
((12 - 4) / 6)^2 = 1.7778 |
J |
(2 + (4 * 4) + 6) / 6 = 4 |
((6 - 2) / 6)^2 = 0.4444 |
CPM
ACTIVITY |
DURATION |
ES |
EF |
LS |
LF |
SLACK |
A |
10 |
0 |
10 |
0 |
10 |
0 |
B |
12 |
0 |
12 |
2 |
14 |
2 |
C |
10 |
0 |
10 |
4 |
14 |
4 |
D |
4 |
12 |
16 |
14 |
18 |
2 |
E |
8 |
10 |
18 |
10 |
18 |
0 |
F |
8 |
10 |
18 |
18 |
26 |
8 |
G |
12 |
18 |
30 |
18 |
30 |
0 |
I |
8 |
18 |
26 |
26 |
34 |
8 |
J |
4 |
30 |
34 |
30 |
34 |
0 |
FORWARD PASS: ES = MAXIMUM EF OF ALL PREDECESSOR ACTIVITIES; 0 IF NO PREDECESSORS ARE PRESENT. EF = ES + DURATION OF THE ACTIVITY.
BACKWARD PASS: LF = MINIMUM LS OF ALL SUCCESSOR ACTIVITIES; COMPLETION TIME OF THE PROJECT IF NO SUCCESSORS ARE PRESENT. LS = LF - DURATION OF THE ACTIVITY.
SLACK = LF - EF, OR, LS - ES
CRITICAL PATH = PATH WITH THE LONGEST COMBINED DURATION VALUE AND 0 SLACK.
CRITICAL PATH = AEGJ
DURATION OF PROJECT = 34
A Thumbs Up! would be really helpful for me. If you have any questions, please leave a comment, and I will get back to you as soon as possible.
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) PESSIMISTIC TIME days) MOST LIKELY...
Estimated activity times and precedences are given below: Activity Optimistic Most Likely Pessimistic Required Precedence A 6 7 14 B 8 10 12 C 2 3 4 D 6 7 8 A E 5 5.5 9 B, C F 5 7 9 B, C G 4 6 8 D, E H 2.7 3 3.5 F What is the probability that the project will be completed within: A. 21 Days B. 22 Days C. 25 Days
Given an activity's optimistic, most likely, and pessimistic time estimates of 5, 10, and 15 days respectively, compute the PERT variance for this activity
Given an activity's optimistic, most likely, and pessimistic time estimates of 6, 12, and 18 days respectively, compute the PERT variance for this activity
(15 points) Activity Immediate Predecessor Optimistic Time Most likely Time Pessimistic Time A NONE 4 7 9 B A 2 4 6 C A 6 9 9 D B, C 5 5 5 E C 2 5 9 F D, E 3 3 6 Use both the longest path method and ES/EF; LS/LF method for the following questions (e) What are the slack values for non-critical activities? (4 points) (f) What is the probability that the project will be...
Given the following activity list and times in days: (15 points) Activity Optimistic Most Likely Pessimistic Time Time Time A 7 10 12 B 6 8 14 C 5 9 12 D 12 14 21 E 10 12 15 F 4 5 8 G 1 3 8 H 12 15 17 NOTE 1: ASSUME THE CRITTCAL PATH IS “B-E-H”. Calculate the schedule duration of the critical path in days. What is the probability of the project being completed...
Given an activity's optimistic, most likely, and pessimistic time estimates of 5, 7, and 15 days respectively, compute the PERT expected activity time (t) and variance of activity completion time (Var) for this activity. 1. t = 8, and Var = 2.78 2. t = 7, and Var = 1.78 3. t = 14, and Var = 2.78 4. t = 8, and Var = 1.78
Assume all activities A, B, D are on the critical path. Activity Optimistic Time Most Likely Time Pessimistic Time A 1 4 10 B 4 9 10 C 12 17 28 D 4 5 6 The expected time for activity B is? 18.0 4.5 8.33 6.17 What is the standard deviation for the project? 4.43 2.11 1.67 2.80
Activity D on a PERT network has an optimistic duration of 3 days, a most likely duration of 5 days and a pessimistic duration of 13 days. What is the expected duration of activity D? Formula: Expected Activity time: t = (a + 4m + b)/6 a. 5 days b. 6 days c. 7 days d. 10 days e. 12 days
TIMES (days) Activity Start Node Finish Node OPTIMISTIC to MOST LIKELY tm PESSIMISTIC tp A 1 2 24 30 42 B 1 3 20 23 32 C 2 5 15 27 39 D 3 4 25 43 61 E 4 5 15 42 69 Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity A………te = 31 Standard Deviation = 3 Activity B………te = Standard Deviation = Activity C………te...
PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....