Question

Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) PESSIMISTIC TIME days) MOST LIK

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.SLACK OF D = A. 2

EXPECTED TIME = (OPTIMISTIC TIME + (4 * MOST LIKELY TIME) + PESSIMISTIC TIME) / 6

VARIANCE = ((PESSIMISTIC TIME - OPTIMISTIC TIME) / 6)^2


ACTIVITY

EXPECTED TIME

VARIANCE

A

(5 + (4 * 10) + 15) / 6 = 10

((15 - 5) / 6)^2 = 2.7778

B

(10 + (4 * 12) + 14) / 6 = 12

((14 - 10) / 6)^2 = 0.4444

C

(10 + (4 * 10) + 10) / 6 = 10

((10 - 10) / 6)^2 = 0

D

(2 + (4 * 4) + 6) / 6 = 4

((6 - 2) / 6)^2 = 0.4444

E

(4 + (4 * 8) + 12) / 6 = 8

((12 - 4) / 6)^2 = 1.7778

F

(4 + (4 * 8) + 12) / 6 = 8

((12 - 4) / 6)^2 = 1.7778

G

(10 + (4 * 12) + 14) / 6 = 12

((14 - 10) / 6)^2 = 0.4444

I

(4 + (4 * 8) + 12) / 6 = 8

((12 - 4) / 6)^2 = 1.7778

J

(2 + (4 * 4) + 6) / 6 = 4

((6 - 2) / 6)^2 = 0.4444


CPM


ACTIVITY

DURATION

ES

EF

LS

LF

SLACK

A

10

0

10

0

10

0

B

12

0

12

2

14

2

C

10

0

10

4

14

4

D

4

12

16

14

18

2

E

8

10

18

10

18

0

F

8

10

18

18

26

8

G

12

18

30

18

30

0

I

8

18

26

26

34

8

J

4

30

34

30

34

0


FORWARD PASS: ES = MAXIMUM EF OF ALL PREDECESSOR ACTIVITIES; 0 IF NO PREDECESSORS ARE PRESENT. EF = ES + DURATION OF THE ACTIVITY.

BACKWARD PASS: LF = MINIMUM LS OF ALL SUCCESSOR ACTIVITIES; COMPLETION TIME OF THE PROJECT IF NO SUCCESSORS ARE PRESENT. LS = LF - DURATION OF THE ACTIVITY.

SLACK = LF - EF, OR, LS - ES

CRITICAL PATH = PATH WITH THE LONGEST COMBINED DURATION VALUE AND 0 SLACK.

CRITICAL PATH = AEGJ

DURATION OF PROJECT = 34

A Thumbs Up! would be really helpful for me. If you have any questions, please leave a comment, and I will get back to you as soon as possible.

Add a comment
Know the answer?
Add Answer to:
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) PESSIMISTIC TIME days) MOST LIKELY...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT