Activity D on a PERT network has an optimistic duration of 3 days, a most likely duration of 5 days and a pessimistic duration of 13 days. What is the expected duration of activity D?
Formula: Expected Activity time: t = (a + 4m + b)/6
a. |
5 days |
|
b. |
6 days |
|
c. |
7 days |
|
d. |
10 days |
|
e. |
12 days |
IF YOU HAVE ANY DOUT COMMENT PLS...
PLS GIVE A POSTIVE RATING....
Activity D on a PERT network has an optimistic duration of 3 days, a most likely...
An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and pessimistic = 10. What is its expected activity time and variance? A. 5; 1.78 B. 4; 1.78 C. 5; 10.67 D. 4; 10.67 E. None of the above.
An activity on a PERT network has an optimistic time of 10 hours, a most likely time of 13 hours, and a pessimistic time of 28 hours. Find its VARIANCE. 20.25 hour2 25 hour? 9 hour2 16 hour2 12.25 hour2
Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m b Time (t) o 2 3 2 1 B с D NWN mlm A 1 A,B 2 4 1 6 7 9 F 1 с с DE F,G 4 2 5 3 G 4 12 H 2 4 From the table above find the flowing answers. 1. Construct the project Network 2. Find the expected duration and Variance of each activity 3. Find the...
Given the following activity list and times in days: (15 points) Activity Optimistic Most Likely Pessimistic Time Time Time A 7 10 12 B 6 8 14 C 5 9 12 D 12 14 21 E 10 12 15 F 4 5 8 G 1 3 8 H 12 15 17 NOTE 1: ASSUME THE CRITTCAL PATH IS “B-E-H”. Calculate the schedule duration of the critical path in days. What is the probability of the project being completed...
Given an activity's optimistic, most likely, and pessimistic time estimates of 5, 7, and 15 days respectively, compute the PERT expected activity time (t) and variance of activity completion time (Var) for this activity. 1. t = 8, and Var = 2.78 2. t = 7, and Var = 1.78 3. t = 14, and Var = 2.78 4. t = 8, and Var = 1.78
Given an activity's optimistic, most likely, and pessimistic time estimates of 6, 12, and 18 days respectively, compute the PERT variance for this activity
PERT: Calculate the probability of finishing the project in 25 days or less Activity 10-20 10-30 20-40 30-40 20-30 16 15 10 12 10 13 4 10 Dummy a is the optimistic duration m is the most likely duration b is the pessimistic duration
Use the network activity diagram and table below to answer questions 45-53. Activity Optimistic Most Probable Pessimistic A 5 7 B 3 5 7 C 1 2 9 5 E 3 4 2 3 10 G 6 7 14 H 4 12 B G E H. C A. Finish Start F D Using the three time estimate approach, what is the value of uC? O 6 O4 None of the above are correct Use the network activity diagram and table...
QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are...
Given an activity's optimistic, most likely, and pessimistic time estimates of 5, 10, and 15 days respectively, compute the PERT variance for this activity