Question

QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15.

QUESTION 2 B G E. H. C A Finish Start F D Complete the network activity diagram using the table below to answer questions 1-1

QUESTION 3 B. G E A. Finish Start D Complete the network activity diagram using the table below to answer questions 1-15. The

QUESTION 4 B. G H. A. Finish Start F D Complete the network activity diagram using the table below to answer questions 1-15.

QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are correct ui
QUESTION 2 B G E. H. C A Finish Start F D Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Pessimistic Most Probable Optimistic Activity 7 6 A 12 8 4 E 12 5 C 7 5 C 20 15 10 E 18 6 13 6 G 11 8 5 H What is the early finish (EF) time for activity G? 22 28 35 38 None of the above are correct O O O O O
QUESTION 3 B. G E A. Finish Start D Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Pessimistic Most Probable Activity Optimistic 8 7 6 A 12 B 12 C 7 D 20 15 10 E 18 6 E 13 G 11 H What is the expected project completion time? 31 36 37 38 None of the above are correct
QUESTION 4 B. G H. A. Finish Start F D Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Pessimistic Most Probable Optimistic Activity 8 7 6 A 12. 4 B 12 4 C 7 3 20 15 10 E 18 6 13 5 G 11 5 H What is the late start (LS) time for activity F? 13 23 28 38 None of the above are correct wi
0 0
Add a comment Improve this question Transcribed image text
Answer #1

E F ES+ T TEF ALTIVITY ZSSOCKLE Slae LFEF SIJ 81 £ G 32 2 3g IS1530 5 12 0 30 38 7 3g 3 0 T 7 8 301 O 21 12 2 7 138 29 24 729(EF)G So, Nan f dR. above 3 C $3 38 4 he aboue are - 29 None CoTreet

Add a comment
Know the answer?
Add Answer to:
QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questio...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT