QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questio...
Use the network activity diagram and table below to answer questions 45-53. Activity Optimistic Most Probable Pessimistic A 5 7 B 3 5 7 C 1 2 9 5 E 3 4 2 3 10 G 6 7 14 H 4 12 B G E H. C A. Finish Start F D Using the three time estimate approach, what is the value of uC? O 6 O4 None of the above are correct Use the network activity diagram and table...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End day 0 5 6 9 6 9 8 5 4 0 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days.. d) The critical activities are = (ex. Fill in answer as: ABCD) End Start
Given is a CPM project network diagram as shown below. A F Start E H End B D G Start H Activity day А 6 B 3 с 8 D 7 E 4 F 9 G 4 End 0 0 6 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G - days. c) The Latest Finish time, LF, of Acitivity - dayy d) The critical activities are (ex. Fill in answer as: ABCD)
QUESTION 5 Given is a CPM project network diagram as shown below. А F Start E H End B D G Start A B C D E F G H End Activity day 0 6 زر 8 7 4 9 4 6 0 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G= days. c) The Latest Finish time, LF, of Acitivity C = days. d) The critical activities are = (ex. Fill in...
Question 3 1 pts Consider the network described in the table below. Activity Preceding Optimistic Probable Pessimistic 11 14 |A,B 7 11 13 G D, E 10 DE Calculate the Variance of the project 1.78 1.36 4.14 5.82 None of the above
QUESTION 5 Given is a CPM project network diagram as shown below. A F Start H End B D G B Activity days Start 0 A 2 H D 3 E 4 F 2 G 3 6 8 End 0 2 a) The Project Completion time days. b) The Earliest Start time, ES, of Activity G - days. c) The Latest Finish time, LF, of Acitivity C- days. d) The critical activities are (ex. Fill in answer as: ABCD)
QUESTION 5 Given is a CPM project network diagram as shown below. A с F Start E H End B D Start A B E H End Activity day с 7 D 3 F 5 G 6 0 2 4 3 0 a) The Project Completion time = days. b) The Earliest Start time, Es, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C - days. d) The critical activities are (ex. Fill in answer...
Consider the following project network and activity times (in weeks): Start Finish Activity | A B C D E F G H Time 5 37 6 7 310 8 a. Identify the critical path. b. How much time will be needed to complete this project? c. Can activity D be delayed without delaying the entire project? If so, by how many weeks? d. Can activity C be delayed without delaying the entire project? If so, by how many weeks? What...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K, M 9 5 1 O K, M 10 7 4 P L, N 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path....
Given is a CPM project network diagram as shown below. A וד H End Start التا B D G A F H Activity day Start 0 B 8 с 3 D 5 E 6 وانما | End 0 8 4 a) The Project Completion time = days b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days d) The critical activities are = (ex. Fill in answer as:...