Question

Consider the following project network and activity times (in weeks): Start Finish Activity | A B C D E F G H Time 5 37 6 7 3

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

1. A - D - F - H

2. 22

3. NO, activity D is on the critical path.

4. YES, slack of C = 2

5. In the table below.

EXPLANATION

To utilize the CPM method, we will make use of a forward and backward pass of the project diagram and the activities to find the ES, EF, LS, and LF values.

The ES, EF values are calculated using a forward pass where the ES of the next activity is the maximum EF of all the predecessor activities.

The LS, LF values are calculated using a backward pass where the LS of the next activity is the minimum LF of all the predecessor activities.


ACTIVITY

TIME

ES

EF

LS

LF

SLACK

A

5

0

5

0

5

0

B

3

0

3

1

4

1

C

7

5

12

7

14

2

D

6

5

11

5

11

0

E

7

3

10

4

11

1

F

3

11

14

11

14

0

G

10

11

21

11

21

0

H

8

14

22

14

22

0


DURATION = CPM = A - D - F - H = 22


Add a comment
Know the answer?
Add Answer to:
Consider the following project network and activity times (in weeks): Start Finish Activity | A B C D E F G H Time 5 37...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT