1. A - D - F - H
2. 22
3. NO, activity D is on the critical path.
4. YES, slack of C = 2
5. In the table below.
EXPLANATION
To utilize the CPM method, we will make use of a forward and backward pass of the project diagram and the activities to find the ES, EF, LS, and LF values.
The ES, EF values are calculated using a forward pass where the ES of the next activity is the maximum EF of all the predecessor activities.
The LS, LF values are calculated using a backward pass where the LS of the next activity is the minimum LF of all the predecessor activities.
ACTIVITY |
TIME |
ES |
EF |
LS |
LF |
SLACK |
A |
5 |
0 |
5 |
0 |
5 |
0 |
B |
3 |
0 |
3 |
1 |
4 |
1 |
C |
7 |
5 |
12 |
7 |
14 |
2 |
D |
6 |
5 |
11 |
5 |
11 |
0 |
E |
7 |
3 |
10 |
4 |
11 |
1 |
F |
3 |
11 |
14 |
11 |
14 |
0 |
G |
10 |
11 |
21 |
11 |
21 |
0 |
H |
8 |
14 |
22 |
14 |
22 |
0 |
DURATION = CPM = A - D - F - H = 22
Consider the following project network and activity times (in weeks): Start Finish Activity | A B C D E F G H Time 5 37...
These can be computed exactly using the normal distribution. Please show all working 6. Consider the following project network and activity times (in weeks): Start Finish Activity | A BC DEFG H Time 15 376 73 10 8 a. b. c. Identify the critical path. How much time will be needed to complete this project? Can activity D be delayed without delaying the entire project? If so, by how many weeks? d. Can activity C be delayed without delaying the...
A construction company has a project proposal, which takes 10 activities as follows: Activity Predecessors Activity Duration Time (In DAYS ) Early Start (ES) (In DAYS ) Early Finish (EF) (In DAYS ) Late Start (LS) (In DAYS ) Late Finish (LF) (In DAYS ) SLACK (In DAYS ) A - 14 B - 13 C A 11 D A 15 E B 14 F B 11 G D, E 13 H F 15 J C 12 K G,H 11...
Consider the following project. Activity ImmediateActivity Time (days) Predecessor CD E,F What is the critical path? O ACFG O ADFG OBEG ACDFG What is the latest finish time for activity F? 0 9 O 13 O 16 What is the latest possible time that Activity E can be started without delaying the completion of the project? What is the latest time that activity B can finish without delaying any other activities? 4 What is the latest time that activity B...
A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8 B - 10 C A 3 D A 7 E B, C 6 F B, C 7 G D, E 5 H F 3 Draw the AON diagram Identify all the possible paths What is the critical path? Can activity B be delayed without delaying the completion of the project? If so, by how many days?
Given the following network diagram for a project, determine each of the following (activity times are in weeks): a) Identify all paths in the network. b) Determine each path's length. c) Identify the Critical Path(s). d) Calculate the expected project duration. a. Path b. Path length c. Critical Path (CP) d. Project duration
1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 200 | 1200 | 500 | 700 | 1200 | 800 | 1800 | 1500 | 400 (a) Construct the activity-on-node (AoN) network for the relations among the activities in the (b) Using the activity-on-node (Ao) network developed in part (a), determine the critical path and the minimum time required to complete the project. Develop the earliest start and finish times, the latest finish...
20 The late finish time (LF) is a the latest possible date an activity can be completed without delaying the project's completion b c the maximum extent to which an activity can be delayed the latest possible date an activity can be completed before the activity becomes irrelevant d the latest possible time an activity can be completed on a given day 21 A critical path a is the longest individual path in a network b is the path of...
.8-6. A project consists of 12 activities, represented by the project network below, where number by each arc represents the duration (in days) of the associated activity 4 12 4 12 10 a) Find the earliest time, latest time, and slack for each event as well as the slack for each activity. Also identify the critical path. (b) The project has been scheduled to be completed in the minimum possible time.If all previous activities have begun as early as possible...
QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are...
Problem 5-14 (Static) Here is a CPM network with activity times in weeks: a. Determine the critical path. a. A-E-F-D b. A-E-G-C-D c. A-B-C-D b. How many weeks will the project take to complete? c. Suppose F could be shortened by two weeks and B by one week. By how many weeks would this reduce the project duration? B(5) E(4) F(8)