Question

Problem 5-14 (Static)

Here is a CPM network with activity times in weeks:

B(5) E(4) F(8)

a. Determine the critical path.

a. A-E-F-D

b. A-E-G-C-D

c. A-B-C-D


b. How many weeks will the project take to complete?


c. Suppose F could be shortened by two weeks and B by one week. By how many weeks would this reduce the project duration?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer: a. A-E-G-C-D

The given network paths are

A-E-F-D = 7+4+8+6 = 25 weeks

A-B-C-D = 7+5+6+6 = 24 weeks

A-E-G-C-D = 7+4+3+6+6 = 26 weeks

The critical path is A-E-G-C-D with the duration of 26 weeks

Answer b: The project takes 26 weeks to complete

This is based on the critical path of the project. The duration of critical path is 26 weeks

Answer c. 0 weeks

The activity B and F are not on the critical path and hence, it will not make any difference to the critical path.

Add a comment
Know the answer?
Add Answer to:
Problem 5-14 (Static) Here is a CPM network with activity times in weeks: a. Determine the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT