The following activities are part of a project to be scheduled using CPM:
ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
A | — | 3 |
B | A | 9 |
C | A | 5 |
D | C | 2 |
E | B D | 7 |
F | D | 6 |
G | E F | 4 |
b. What is the critical path?
A-B-D-F-G | |
A-B-E-G | |
A-C-D-F-G | |
A-C-D-E-G |
c. How many weeks will it take to complete the project?
Number of weeks
d. How much slack does activity B have?
Slack of activity B week(s)
step 1 | find early start, and early finish from the start of the project for each activity | ||||
step 2 | Find Maximum EF and keep it as the LF of last activities. Max of EF's is 23 | ||||
step 3 | calculate LS for each activity after calculating its EF |
Activity | Duration, D | Early start, ES=Max of early finish of preceding activities | Early finish, EF = ES + D | Late finish, LF= Min of LS of successor activities | Late start, LS= LF - D | Total slack= LF-EF | Critical activity, activities with 0 slack time |
A | 3 | 0 | 3 | 3 | 0 | 0 | Yes |
B | 9 | 3 | 12 | 12 | 3 | 0 | Yes |
C | 5 | 3 | 8 | 10 | 5 | 2 | No |
D | 2 | 8 | 10 | 12 | 10 | 2 | No |
E | 7 | 12 | 19 | 19 | 12 | 0 | Yes |
F | 6 | 10 | 16 | 19 | 13 | 3 | No |
G | 4 | 19 | 23 | 23 | 19 | 0 | Yes |
b. Hence the critical path is A-B-E-G
c. it will take 23 weeks
d. slack of B is 0.
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) А 7 B 6 2 3 B.D D b. What is the critical path? Оооо A-C-D-E-G A-B-D-F-G A-B-E-G O A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 b. What is the critical path? A-B-D-F-G A-C-D-E-G A-C-D-F-G A-B-E-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
Problem 5-7 (Algo) The following activities are part of a project to be scheduled using CPM ACTIVITY IMMEDIATE PREDECESSOR TIME (HEEKS) A 9 B A. 3 C A. 7 D C E BD 4 F 3 E F G a. What is the critical path? A-C-D-E-G O A-B-D-F-G A-B-E-G A-C-D-F-G b. How many weeks will it take to complete the project? Number of weeks <Prey 3 of 8 Next>
Schedule the following activities using CPM: Table 2 ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 8 B A 4 C A 4 D C 8 E B, D 2 F D 6 G E, F 2 Question 25 (1 point) What is the critical path? (Show your diagram and calculations) Question 25 options: A-C-D-E-G A-B-E-G A-B-D-E-G A-C-D-F-G A-B-D-F-G How many weeks will it take to complete the project? What is B slack time?
Can someone please help me with this Operations Management Question? The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) MO OWO 10ம் ONNON b. What is the critical path? O O O O A-C-D-E-G A-B-E-G A-B-D-F-G A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
chedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 5 B A 3 C A 4 D B 6 E C D 8 F D 2 G F 4 H E G 3 b. What is the critical path? A-B-D-E-H A-B-D-F-G-H A-C-E-F-G-H A-C-E-H c. How many weeks will it take to complete the project? d. Which activities have slack, and how much? B 1 week H 2 weeks F 4 weeks. C 5 weeks F 2...
Given the following activities and precedents, draw a PERT/CPM diagram. ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A - 10 B - 12 C A 4 D A, B 8 E A, B 9 F C 10 G D, F 12 H E, G 15 Answer the following: What is the critical path? How long will it take to complete this project? Can activity E be delayed without delaying the completion of the project? If so, how many days?
I need help with the following problem. Schedule the following activities using CPM. ACTIVITY Immediate Predecessors Time in Weeks A ---- 2 B A 5 C A 4 D B 3 E C, D 6 F D 3 G F 3 H E, G 4 Draw the network diagram below using the square activity I have provided. Just select the object, then copy it and paste how many you need and then arrange them in the order you need and...
The following activities are part of a project to be scheduled using CPM.Activity Immediate predecessors Time(Weeks)A - 6B A 3C A 7D C 2E B,D 4F D 3G E,F 7i) Draw the networkii) What is the critical path?iii) How many weeks will it take to complete the project?iv) How much slack does activity B have?
A=8 B=6 E=5 G=4 C=7 F=9 D=7 The following activities are part of a project to be scheduled using CPM. Determine the critical Path. How many weeks will it take to complete the project? Suppose F could be shortened by two weeks and B by one week. How would this affect the completion date? OBJECTIVE QUESTION 14 The following activities are part of a project to be scheduled using CPM. B-6 A-8 G-4 D-7 E-5 F-9 a. Determine the critical...