OBJECTIVE QUESTION 14 The following activities are part of a project to be scheduled using CPM. B-6 A-8 G-4 D-7 E-5 F-9 a. De

A=8

B=6

E=5

G=4

C=7

F=9

D=7

The following activities are part of a project to be scheduled using CPM.

  1. Determine the critical Path.
  2. How many weeks will it take to complete the project?
  3. Suppose F could be shortened by two weeks and B by one week. How would this affect the completion date?
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Determine the critical Path.

The various paths are given as:-

A-B-C-D =8+6+7+7=28

A-E-G-C-D =8+5+4+7+7 =31

A-E-F-D=8+5+9+7 =29

As the longest duration is of path A-E-G-C-D so this is the critical path.

  1. How many weeks will it take to complete the project?

Answer:- 31 weeks

  1. Suppose F could be shortened by two weeks and B by one week. How would this affect the completion date?

In this case, the duration of F=9-2=7 and B=6-1=5

Now the duration of various paths,

A-B-C-D =8+5+7+7=27

A-E-G-C-D =8+5+4+7+7 =31

A-E-F-D=8+5+7+7 =27

So despite the deduction in the duration of activities B and E, there will be no change on the completion date.

KINDLY RATE THE ANSWER AS THUMBS UP. THANKS A LOT.

Add a comment
Know the answer?
Add Answer to:
A=8 B=6 E=5 G=4 C=7 F=9 D=7 The following activities are part of a project to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY...

    Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) А 7 B 6 2 3 B.D D b. What is the critical path? Оооо A-C-D-E-G A-B-D-F-G A-B-E-G O A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)

  • Problem 5-7 (Algo) The following activities are part of a project to be scheduled using CPM...

    Problem 5-7 (Algo) The following activities are part of a project to be scheduled using CPM ACTIVITY IMMEDIATE PREDECESSOR TIME (HEEKS) A 9 B A. 3 C A. 7 D C E BD 4 F 3 E F G a. What is the critical path? A-C-D-E-G O A-B-D-F-G A-B-E-G A-C-D-F-G b. How many weeks will it take to complete the project? Number of weeks <Prey 3 of 8 Next>

  • Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY...

    Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 b. What is the critical path? A-B-D-F-G A-C-D-E-G A-C-D-F-G A-B-E-G c. How many weeks will it take to complete the project? Number of weeks             d. How much slack does activity B have? Slack of activity B             week(s)

  • The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...

    The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 3 B A 9 C A 5 D C 2 E B D 7 F D 6 G E F 4 b. What is the critical path? A-B-D-F-G A-B-E-G A-C-D-F-G A-C-D-E-G c. How many weeks will it take to complete the project? Number of weeks             d. How much slack does activity B have? Slack of activity B             week(s)

  • For the network shown D(4) B(12) E(6) G(4) C(6) F(5) a-1. Determine the critical path A-C-E-G...

    For the network shown D(4) B(12) E(6) G(4) C(6) F(5) a-1. Determine the critical path A-C-E-G A-C-F-G A-B-D-G A-B-E-G a-2. Determine the early completion time in weeks for the project. Early completion time For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened weeks NORMAL NORMAL CRASH CRASH ACTIVITY TIME COST TIME COST $ 7,300 2$13,400 18,200 6,550 6,800 5,400 9,000 8,400 7 12 6 12,400 10 5,400 4,500 3,200 6,700...

  • 5 morom The following activities are part of a project to be scheduled using What is...

    5 morom The following activities are part of a project to be scheduled using What is the critical path? A-B-E-G A-C-D-EG A-B-D-FG AC-D-F-G b. How many weeks will it take to complete the project? Number of weeks Prex 5 of 20 Next MacBook Air 80

  • Can someone please help me with this Operations Management Question? The following activities are part of...

    Can someone please help me with this Operations Management Question? The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) MO OWO 10ம் ONNON b. What is the critical path? O O O O A-C-D-E-G A-B-E-G A-B-D-F-G A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)

  • Problem 5-14 (Static) Here is a CPM network with activity times in weeks: a. Determine the...

    Problem 5-14 (Static) Here is a CPM network with activity times in weeks: a. Determine the critical path. a. A-E-F-D b. A-E-G-C-D c. A-B-C-D b. How many weeks will the project take to complete? c. Suppose F could be shortened by two weeks and B by one week. By how many weeks would this reduce the project duration? B(5) E(4) F(8)

  • Calibri | E Wrap Text Merge & Center inter Font Alignment X ✓ for C D...

    Calibri | E Wrap Text Merge & Center inter Font Alignment X ✓ for C D E F G H ge 158, #7 with the following change FOR STUDENTS WITH EVEN NUMBERED STUDENT L NUMBERS, Change task G's time from 7 to Also dertly two tas that could possibly be crushed to speed 8. Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) Immo > Tacou w NNUNWA- EG a. Draw the network. h. What is the critical...

  • A construction project is broken down into the following 10 activities:

    Problem 5-13 A construction project is broken down into the following 10 activities:b-1. What is the critical path? 1-4-7-9-10 1-3-6-9-10 1-2-5-8-10 1-3-5-8-10 b-2. How many weeks will the project take to complete? Number of weeks _______ c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which activities would you shorten to cut the project by four weeks? (You may select more than one answer. Single-click the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT