Question

For the network shown D(4) B(12) E(6) G(4) C(6) F(5) a-1. Determine the critical path A-C-E-G A-C-F-G A-B-D-G A-B-E-G a-2. Determine the early completion time in weeks for the project. Early completion time For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened weeks NORMAL NORMAL CRASH CRASH ACTIVITY TIME COST TIME COST $ 7,300 2$13,400 18,200 6,550 6,800 5,400 9,000 8,400 7 12 6 12,400 10 5,400 4,500 3,200 6,700 7,600 2

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The critical path is the longest path in the project. There are three paths in the project and their length are

ABDG = 7+12+4+4 = 27

ACEG = 7+6+6+4 = 23

ACFG = 7+6+5+4 = 22

a-1

The critical path is A-B-D-G

a-2

The earliest completion time for the project is the duration of critical path.

Early completion time is 27 weeks.

For crashing the project we need to minimize crash cost and also adhere to the duration of the crash. We need to crash it by 3 weeks. Since the critical path exceed the next longest path by more than 3 weeks, it will not change the critical path. This means we need to crash either of A, B, D, and G with 3 weeks in total.

First we need to determine the cost per week for crash for each of them. This is done by subtracting the normal cost from crash cost and dividing it with the difference between normal and crash time. Cost per week of crash is

A = (13400-7300)/(7-2) = 1220

B = (18200-12400)/(12-10) =2900

D = (6800-4500)/(4-2) = 1150

G = (8400-7600)/(4-3) = 800

b-1

We see that the cheapest crash is G. Hence we will start with G. But we can only crash one week with G. So we will choose the next cheapest option for crashing. That is D. and we can crash D by 2 weeks. Thus the answer is

G-D-D

b-2

The total cost to crash is the additional cost that will be borne. That is 800 + 1150 + 1150 = 3100

Resulting cost = $3100

Add a comment
Know the answer?
Add Answer to:
For the network shown D(4) B(12) E(6) G(4) C(6) F(5) a-1. Determine the critical path A-C-E-G...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A=8 B=6 E=5 G=4 C=7 F=9 D=7 The following activities are part of a project to...

    A=8 B=6 E=5 G=4 C=7 F=9 D=7 The following activities are part of a project to be scheduled using CPM. Determine the critical Path. How many weeks will it take to complete the project? Suppose F could be shortened by two weeks and B by one week. How would this affect the completion date? OBJECTIVE QUESTION 14 The following activities are part of a project to be scheduled using CPM. B-6 A-8 G-4 D-7 E-5 F-9 a. Determine the critical...

  • Question 6 - 8 Activity Depends on А B C D E F G A A...

    Question 6 - 8 Activity Depends on А B C D E F G A A А B C,D D, E, F Duration (Days) Normal Crash 5 4 7 5 8 5 11 8 6 4 4 3 7 5 Cost ($) Normal Crash 500 620 350 500 800 920 1000 1300 600 750 420 500 700 1000 6. Draw the node network for the above project using the following template. For each activity, show the computed value of early...

  • Use the following crashing table to answer Project time Period cost Cumulative cost A B C D E F G...

    Use the following crashing table to answer Project time Period cost Cumulative cost A B C D E F G H I J 37 0 0 36 60 120 1 35 80 200 1 1 34 80 280 2 2 33 80 360 3 2 32 135 495 3 1 2 1 31 180 675 1 4 1 2 1 30 180 855 2 5 1 2 1 29 733.33 1588.33 1 2 5 1 2 1 28 983.33 2571.67...

  • Path A -> B -> F C-> D -> E ----^ Activity Normal Time Crash Time...

    Path A -> B -> F C-> D -> E ----^ Activity Normal Time Crash Time Crash Cost per day A 6 6 --- B 10 8 $100 C 5 4 $300 D 4 1 $700 E 9 7 $500 F 2 1 $650 a.     Determine which activities should be crashed to shorten the project by 3 days. b.     What is the associated crash cost?

  • Problem 5-18 The following CPM network has estimates of the normal time in weeks listed for...

    Problem 5-18 The following CPM network has estimates of the normal time in weeks listed for the activities: CS 103 a. Identify the critical path. O A-C-D-E-G O A-C-D-F-G A-B-D-E-G O A-B-D-F-G b. What is the length of time to complete the project? Number of weeks c. Which activities have slack, and how much? OB, 2 week(s); F, 4 week(s). OC, 3 week(s); F. 3 week(s). OB, 2 week(s): E, 3 week(s). O C. 3 week(s); E, 3 week(s). Here...

  • Paragraph 2 Styles . 4 5 6 The "SUPER" project has the following activity lists, normal...

    Paragraph 2 Styles . 4 5 6 The "SUPER" project has the following activity lists, normal time and cost and crash time and cost. Predecessor Normal Time Crash Time Normal Cost Crash Cost Activity Activity (Weeks) (Weeks) A 4 3 8,000 9,000 B А 5 3 16,000 20,000 C A 4 3 12,000 14,000 D B 6 5 34,000 35,000 E 6 3 42,000 45,000 F D 5 4 16,000 16,500 E 7 5 66,000 72,000 9 H G 4...

  • What is the critical path? Start-A-D-G-End O Start-A-D-F-End Start-A-E-G-End O Start-B-E-G-End What is the EF (earliest...

    What is the critical path? Start-A-D-G-End O Start-A-D-F-End Start-A-E-G-End O Start-B-E-G-End What is the EF (earliest finish) of activity E? o o ООООО < N N What is the LS (latest start) of activity E? ООООО The list of activities, their times (in weeks), and precedence relationships for a new project are given below. Activity Immediate Predecessor Activity Time A L - L 4 B - 1 2 C - A, B F DL 4 G C, D, E What...

  • Q4 The network diagram of a project is shown below E.4 B.3 G.5 D.5 A.7 F.2 C.4 (a) Use two-pass method to determine the...

    Q4 The network diagram of a project is shown below E.4 B.3 G.5 D.5 A.7 F.2 C.4 (a) Use two-pass method to determine the critical path. (3 points) (b) What is the project duration? ( points) (c) What is the slack time of activity F? ( points) Q4 The network diagram of a project is shown below E.4 B.3 G.5 D.5 A.7 F.2 C.4 (a) Use two-pass method to determine the critical path. (3 points) (b) What is the project...

  • Consider the following project network and activity times (in weeks): Start Finish Activity | A B C D E F G H Time 5 37...

    Consider the following project network and activity times (in weeks): Start Finish Activity | A B C D E F G H Time 5 37 6 7 310 8 a. Identify the critical path. b. How much time will be needed to complete this project? c. Can activity D be delayed without delaying the entire project? If so, by how many weeks? d. Can activity C be delayed without delaying the entire project? If so, by how many weeks? What...

  • (3) Determine the critical path and critical time of the network shown below. Use the critical...

    (3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). (3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). po Problem . Example a 100 For all starting activities, ES is taken as 0. Activities 1-2, 1-3 gets ES of O. Find EF-ES +time. Activity Time ES E F LS L...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT