As path A-C-D-E-G has no slack, this is the critical path.
ES - Early Start, EF - Early finish
LS- Late Start, LF - Late finish
5 morom The following activities are part of a project to be scheduled using What is...
Problem 5-7 (Algo) The following activities are part of a project to be scheduled using CPM ACTIVITY IMMEDIATE PREDECESSOR TIME (HEEKS) A 9 B A. 3 C A. 7 D C E BD 4 F 3 E F G a. What is the critical path? A-C-D-E-G O A-B-D-F-G A-B-E-G A-C-D-F-G b. How many weeks will it take to complete the project? Number of weeks <Prey 3 of 8 Next>
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) А 7 B 6 2 3 B.D D b. What is the critical path? Оооо A-C-D-E-G A-B-D-F-G A-B-E-G O A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 b. What is the critical path? A-B-D-F-G A-C-D-E-G A-C-D-F-G A-B-E-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 3 B A 9 C A 5 D C 2 E B D 7 F D 6 G E F 4 b. What is the critical path? A-B-D-F-G A-B-E-G A-C-D-F-G A-C-D-E-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
A=8 B=6 E=5 G=4 C=7 F=9 D=7 The following activities are part of a project to be scheduled using CPM. Determine the critical Path. How many weeks will it take to complete the project? Suppose F could be shortened by two weeks and B by one week. How would this affect the completion date? OBJECTIVE QUESTION 14 The following activities are part of a project to be scheduled using CPM. B-6 A-8 G-4 D-7 E-5 F-9 a. Determine the critical...
Can someone please help me with this Operations Management Question? The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) MO OWO 10ம் ONNON b. What is the critical path? O O O O A-C-D-E-G A-B-E-G A-B-D-F-G A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
The following activities are part of a project to be scheduled using CPM.Activity Immediate predecessors Time(Weeks)A - 6B A 3C A 7D C 2E B,D 4F D 3G E,F 7i) Draw the networkii) What is the critical path?iii) How many weeks will it take to complete the project?iv) How much slack does activity B have?
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Activity Duration (weeks) Precedes A (start) 2 B, C B 2 E C 6 F E 3 F F (end) 4 — This exercise contains only parts b, c, and d. b) Define the critical path, listing all critical activities in chronological order. Critical path activities are the activities that lie on the longest...
I need help with the following problem. Schedule the following activities using CPM. ACTIVITY Immediate Predecessors Time in Weeks A ---- 2 B A 5 C A 4 D B 3 E C, D 6 F D 3 G F 3 H E, G 4 Draw the network diagram below using the square activity I have provided. Just select the object, then copy it and paste how many you need and then arrange them in the order you need and...
Schedule the following activities using CPM: Table 2 ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 8 B A 4 C A 4 D C 8 E B, D 2 F D 6 G E, F 2 Question 25 (1 point) What is the critical path? (Show your diagram and calculations) Question 25 options: A-C-D-E-G A-B-E-G A-B-D-E-G A-C-D-F-G A-B-D-F-G How many weeks will it take to complete the project? What is B slack time?