The following activities are part of a project to be scheduled using CPM.
Activity Immediate predecessors Time(Weeks)
A - 6
B A 3
C A 7
D C 2
E B,D 4
F D 3
G E,F 7
i) Draw the network
ii) What is the critical path?
iii) How many weeks will it take to complete the project?
iv) How much slack does activity B have?
We need at least 10 more requests to produce the answer.
0 / 10 have requested this problem solution
The more requests, the faster the answer.
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) А 7 B 6 2 3 B.D D b. What is the critical path? Оооо A-C-D-E-G A-B-D-F-G A-B-E-G O A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
Calibri | E Wrap Text Merge & Center inter Font Alignment X ✓ for C D E F G H ge 158, #7 with the following change FOR STUDENTS WITH EVEN NUMBERED STUDENT L NUMBERS, Change task G's time from 7 to Also dertly two tas that could possibly be crushed to speed 8. Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) Immo > Tacou w NNUNWA- EG a. Draw the network. h. What is the critical...
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 b. What is the critical path? A-B-D-F-G A-C-D-E-G A-C-D-F-G A-B-E-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
Can someone please help me with this Operations Management Question? The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) MO OWO 10ம் ONNON b. What is the critical path? O O O O A-C-D-E-G A-B-E-G A-B-D-F-G A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
I need help with the following problem. Schedule the following activities using CPM. ACTIVITY Immediate Predecessors Time in Weeks A ---- 2 B A 5 C A 4 D B 3 E C, D 6 F D 3 G F 3 H E, G 4 Draw the network diagram below using the square activity I have provided. Just select the object, then copy it and paste how many you need and then arrange them in the order you need and...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 3 B A 9 C A 5 D C 2 E B D 7 F D 6 G E F 4 b. What is the critical path? A-B-D-F-G A-B-E-G A-C-D-F-G A-C-D-E-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
Problem 5-7 (Algo) The following activities are part of a project to be scheduled using CPM ACTIVITY IMMEDIATE PREDECESSOR TIME (HEEKS) A 9 B A. 3 C A. 7 D C E BD 4 F 3 E F G a. What is the critical path? A-C-D-E-G O A-B-D-F-G A-B-E-G A-C-D-F-G b. How many weeks will it take to complete the project? Number of weeks <Prey 3 of 8 Next>
Module 5 Assisted Problems M5_A1. A farm owner is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations are given in the following table IMMEDIATE TIME ACTIVITY ACTIVITY DESCRIPTION (WEEKS) PREDECESSORS A Excavate 2 Erect building Install generator A 6 C A 4 Install tank A 2 Install maintenance equipment B 4 E Connect generator and tank to building Paint finish В, С, D P 5 3 Check...
und BOX your final answers to each part! part of the following questions. For full credit, you MUST 1) The following activities are part of a project to be se project to be scheduled using the critical path method. Activity Duration (hours) Immediate Predecessors None A Mole А с B.D D E,F (a) Draw the network using the AON method. (3 points) (b) Identify the critical path. Box your answer. (3 points) (c) Calculate the slack available at any n...
Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 6 6 N/A B none 5 2 $500 C A 3 2 $1000 D A, B 4 2 $2000 E C, D 5 2 $1250 F D 6 2 $1000 *Shortest possible time for the task 1. Draw the project network and list...