Question

Consider a project having the following six activities:                                  

Consider a project having the following six activities:

                                                     Immediate                                                  Max        Crash cost

            Activity                           Predecessors           Time (weeks)             Crash*    per week

                  A                                none                                    6                          6                N/A

                  B                                none                                    5                          2               $500

                  C                                A                                       3                          2             $1000

                  D                                A, B                                    4                          2             $2000

                  E                                 C, D                                    5                          2             $1250

                  F                                D                                       6                          2             $1000

                                                                                                *Shortest possible time for the task

1. Draw the project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task

2. List the tasks on the critical path

3. What is the expected project duration in weeks?

4. What is the slack for each activity? A:___ B:___ C:___ D:___ E:___ F:____  

5. The project needs to be crashed by 2 weeks. What are the activities crashed to achieve the 2 week crash at lowest cost?

List the new duration of each task and any associated crash costs Activity Duration Crash Cost A B C D E F

6. Draw the NEW project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task

7. List the tasks on the critical path

0 0
Add a comment Improve this question Transcribed image text
Answer #1

CPM

ACTIVITY

DURATION

ES

EF

LS

LF

SLACK

A

6

0

6

0

6

0

B

5

0

5

1

6

1

C

3

6

9

8

11

2

D

4

6

10

6

10

0

E

5

10

15

11

16

1

F

6

10

16

10

16

0

FORWARD PASS: ES = MAXIMUM EF OF ALL PREDECESSOR ACTIVITIES; 0 IF NO PREDECESSORS ARE PRESENT. EF = ES + DURATION OF THE ACTIVITY.

BACKWARD PASS: LF = MINIMUM LS OF ALL SUCCESSOR ACTIVITIES; COMPLETION TIME OF THE PROJECT IF NO SUCCESSORS ARE PRESENT. LS = LF - DURATION OF THE ACTIVITY.

SLACK = LF - EF, OR, LS - ES

CRITICAL PATH = PATH WITH THE LONGEST COMBINED DURATION VALUE AND 0 SLACK.

CRITICAL PATH = A-D-F

DURATION OF PROJECT = 16

2. CRASHING


ACTIVITY

NORMAL TIME

CRASH TIME

COST / PERIOD

TIMES CRASHED

# CRASH

CRASH COST

A

6

6

0

B

5

2

500

C

3

2

1000

D

4

2

2000

1

2ND

2000

E

5

2

1250

F

6

2

1000

1

1ST

1000

TOTAL

3000


3. NEW CRITICAL PATH


ACTIVITY

DURATION

ES

EF

LS

LF

SLACK

A

6

0

6

0

6

0

B

5

0

5

1

6

1

C

3

6

9

6

9

0

D

3

6

9

6

9

0

E

5

9

14

9

14

0

F

5

9

14

9

14

0

ALL CRITICAL PATHS:

ACE = 14

ADE = 14

ADF = 14


Add a comment
Know the answer?
Add Answer to:
Consider a project having the following six activities:                                  
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • for each problem I have this setup so far. I need help on each part and im not too sure if I am on the right track for each question on the picture. this chapter is on project management for statisti...

    for each problem I have this setup so far. I need help on each part and im not too sure if I am on the right track for each question on the picture. this chapter is on project management for statistics 1. A project is shown by the following network. The durations of activities (in weeks) are indicated on the arrows. a. Identify all of the paths, compute the length of each, identify the critical path and the b. Determine...

  • Problem 5: For the given activity network, if there are 35 days required to complete the...

    Problem 5: For the given activity network, if there are 35 days required to complete the project, find the following Complete the network by filling in ES, LS, EF and LF Earliest start for activities D, E, F, H, G, L, M ill. Earliest finish for activities D, E, F, H,G,L,M Latest start for activities D, E, F, H, G, LM V. Latest finish activities D, E, F.H.GLM vi. Slack/Float time for each activities D, E, F, H, G, LM...

  • Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity...

    Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity on Node (AON) diagram to reflect the flow of these activities. Calculate the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity. Calculate the slack for each activity. Identify all activities on the Critical Path. Use the data to calculate the probability the project will finish in 20 weeks (Hint: z-score). Activity A 8 с D E...

  • also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity...

    also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...

  • A Question 11 The following table provides a list of activities in a project, along with...

    A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...

  • 1. The activities needed for a new project your company is undertaking are listed in the...

    1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...

  • A project manager discovers that his team has neglected tocomplete the network diagram for the...

    A project manager discovers that his team has neglected to complete the network diagram for the project. the network diagram is shown below. however the project manager has some information available, specifically that each activity a-g, has a different duration between one and seven weeks. also the slack time for each of the activity is known as shown belowDuration (weeks): 1,2,3,4,5,6,7 Slack time (weeks): 0,0,0,1,1,3,7 A D E G B FINISH START C F Using the clues provided below, determine...

  • Provide step by step please thank you, no exce Assume you have a project with ten...

    Provide step by step please thank you, no exce Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest completion time (or early finish-EF), latest completion time (or late finish-LF), and slack for each of the following tasks (begin at time 0) the critical path on your network diagram. . Which tasks are on the critical path? Highligh Preceding Expected Critical Path? Activity Event Duration EF LF Slack A, D C,E D, E F, G...

  • 2. Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest...

    2. Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest completion time (EF), latest completion time (LF) and slack for each of the following tasks (begin at time 0). Which tasks are on the critical path? Highlight the critical path on your network diagram [5] Activity Preceding Expected EF LF Slack Critical Event Duration Path? A 4 A 5 C A 6 A 7 E A, D 6 C, E 4 G D, E...

  • Question 13 The following table provides a list of activities in a project, along with their...

    Question 13 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 B 3 с 2 D A,B 5 E CD F D 4 G E 2 1 Determine the duration of the project. a. 13 weeks b. 12 weeks OC. 11 weeks d. 10 weeks e. 9 weeks Question 14 Assume that activity F has the following times: Early start time (ES) =...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT