Question

2. Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest completion time (EF), latest comp
1 0
Add a comment Improve this question Transcribed image text
Answer #1

Below is the Network Diagram

B[5] A[4. FC51 Cs Scanned with CamScanner

The bold line is showing the critical path, while the dotted lines are the dummy activities.

The following table shows the EF, LF and Slack values

Expected Slack Activity Duration EF LF 4 4 4 0 B 5 9 31 22 6 10 17 7 D 11 11 0 E 6 17 17 0 F 5 22 22 0 4 22 21 1 3 20 26 6 4

Add a comment
Know the answer?
Add Answer to:
2. Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Provide step by step please thank you, no exce Assume you have a project with ten...

    Provide step by step please thank you, no exce Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest completion time (or early finish-EF), latest completion time (or late finish-LF), and slack for each of the following tasks (begin at time 0) the critical path on your network diagram. . Which tasks are on the critical path? Highligh Preceding Expected Critical Path? Activity Event Duration EF LF Slack A, D C,E D, E F, G...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • for each problem I have this setup so far. I need help on each part and im not too sure if I am on the right track for each question on the picture. this chapter is on project management for statisti...

    for each problem I have this setup so far. I need help on each part and im not too sure if I am on the right track for each question on the picture. this chapter is on project management for statistics 1. A project is shown by the following network. The durations of activities (in weeks) are indicated on the arrows. a. Identify all of the paths, compute the length of each, identify the critical path and the b. Determine...

  • Problem 5: For the given activity network, if there are 35 days required to complete the...

    Problem 5: For the given activity network, if there are 35 days required to complete the project, find the following Complete the network by filling in ES, LS, EF and LF Earliest start for activities D, E, F, H, G, L, M ill. Earliest finish for activities D, E, F, H,G,L,M Latest start for activities D, E, F, H, G, LM V. Latest finish activities D, E, F.H.GLM vi. Slack/Float time for each activities D, E, F, H, G, LM...

  • 1. The activities needed for a new project your company is undertaking are listed in the...

    1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...

  • also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity...

    also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...

  • .8-6. A project consists of 12 activities, represented by the project network below, where number by each arc repres...

    .8-6. A project consists of 12 activities, represented by the project network below, where number by each arc represents the duration (in days) of the associated activity 4 12 4 12 10 a) Find the earliest time, latest time, and slack for each event as well as the slack for each activity. Also identify the critical path. (b) The project has been scheduled to be completed in the minimum possible time.If all previous activities have begun as early as possible...

  • 11. In CPM/PERT, an activity that is on the critical path A. has equal values for...

    11. In CPM/PERT, an activity that is on the critical path A. has equal values for "Latest Start" and "Earliest Start" ( LS = ES ) B. has equal values for "Latest Finish" and "Earliest Finish" ( LF = EF ) C. is used in calculating total project duration D. has slack equal to zero E. all of the above 12. In CPM/PERT, the critical path through the network A. will require the most time of any path B. will...

  • : A network consists of the following list. Times are given in weeks. Activity Preceding Duration...

    : A network consists of the following list. Times are given in weeks. Activity Preceding Duration A -- 9 B A 2 C A 12 D A 5 E B 6 F B 8 G C, F 3 H D 2 I H 8 J G, I 6 K E, J 2 Draw the network diagram. Find ES, EF, LS, LF, and the slack times for each of the activities. Which activities are critical? Determine the critical path(s). What is...

  • (3) Determine the critical path and critical time of the network shown below. Use the critical...

    (3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). (3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). po Problem . Example a 100 For all starting activities, ES is taken as 0. Activities 1-2, 1-3 gets ES of O. Find EF-ES +time. Activity Time ES E F LS L...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT