Question

I need help with the following problem. Schedule the following activities using CPM. ACTIVITY Immediate Predecessors...

I need help with the following problem.

Schedule the following activities using CPM.

ACTIVITY

Immediate Predecessors

Time in Weeks

A

----

2

B

A

5

C

A

4

D

B

3

E

C, D

6

F

D

3

G

F

3

H

E, G

4

  1. Draw the network diagram below using the square activity I have provided. Just select the object, then copy it and paste how many you need and then arrange them in the order you need and insert arrows to show direction.
  1. What is the critical Path?
  2. How many weeks will it take to complete the project?
  3. Which activities have slack and how much?
0 0
Add a comment Improve this question Transcribed image text
Answer #1

CPM refers to critical path method where shortest path is taken to plan the project. The steps in CPM schedule include: -

  • Individual activities are specified.
  • Sequence of those activities are determined.
  • Drawing a network diagram.
  • Completion time of each activity is estimated.
  • Critical path is identified.
  • CPM diagram is updated.

Add a comment
Know the answer?
Add Answer to:
I need help with the following problem. Schedule the following activities using CPM. ACTIVITY Immediate Predecessors...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...

    The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 3 B A 9 C A 5 D C 2 E B D 7 F D 6 G E F 4 b. What is the critical path? A-B-D-F-G A-B-E-G A-C-D-F-G A-C-D-E-G c. How many weeks will it take to complete the project? Number of weeks             d. How much slack does activity B have? Slack of activity B             week(s)

  • Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY...

    Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) А 7 B 6 2 3 B.D D b. What is the critical path? Оооо A-C-D-E-G A-B-D-F-G A-B-E-G O A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)

  • Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY...

    Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 b. What is the critical path? A-B-D-F-G A-C-D-E-G A-C-D-F-G A-B-E-G c. How many weeks will it take to complete the project? Number of weeks             d. How much slack does activity B have? Slack of activity B             week(s)

  • Schedule the following activities using CPM: Table 2 ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A                    — 8...

    Schedule the following activities using CPM: Table 2 ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A                    — 8 B                    A 4 C                    A 4 D                    C 8 E                    B, D 2 F                    D 6 G                    E, F 2 Question 25 (1 point) What is the critical path? (Show your diagram and calculations) Question 25 options: A-C-D-E-G A-B-E-G A-B-D-E-G A-C-D-F-G A-B-D-F-G How many weeks will it take to complete the project? What is B slack time?

  • Operation management

    The following activities are part of a project to be scheduled using CPM.Activity Immediate predecessors Time(Weeks)A - 6B A 3C A 7D C 2E B,D 4F D 3G E,F 7i) Draw the networkii) What is the critical path?iii) How many weeks will it take to complete the project?iv) How much slack does activity B have?

  • chedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 5 B A...

    chedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 5 B A 3 C A 4 D B 6 E C D 8 F D 2 G F 4 H E G 3 b. What is the critical path? A-B-D-E-H A-B-D-F-G-H A-C-E-F-G-H A-C-E-H c. How many weeks will it take to complete the project? d. Which activities have slack, and how much? B 1 week H 2 weeks F 4 weeks. C 5 weeks F 2...

  • Problem 5-7 (Algo) The following activities are part of a project to be scheduled using CPM...

    Problem 5-7 (Algo) The following activities are part of a project to be scheduled using CPM ACTIVITY IMMEDIATE PREDECESSOR TIME (HEEKS) A 9 B A. 3 C A. 7 D C E BD 4 F 3 E F G a. What is the critical path? A-C-D-E-G O A-B-D-F-G A-B-E-G A-C-D-F-G b. How many weeks will it take to complete the project? Number of weeks <Prey 3 of 8 Next>

  • Can someone please help me with this Operations Management Question? The following activities are part of...

    Can someone please help me with this Operations Management Question? The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) MO OWO 10ம் ONNON b. What is the critical path? O O O O A-C-D-E-G A-B-E-G A-B-D-F-G A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)

  • From this schedule of activities: Activity Immediate Predecessor Activity Time A --- 4 B A 2...

    From this schedule of activities: Activity Immediate Predecessor Activity Time A --- 4 B A 2 C B 3 D B 5 E A 1 F C, D 3 G E, F 2 a. Draw the PERT/CPM network b. Complete the forward and backward pass c. Determine the critical path d. Determine the total duration of the project.

  • Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A...

    Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT