Question

chedule the following activities using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 5
B A 3
C A 4
D B 6
E C

D
8
F D 2
G F 4
H E

G
3


b. What is the critical path?

  • A-B-D-E-H

  • A-B-D-F-G-H

  • A-C-E-F-G-H

  • A-C-E-H

c. How many weeks will it take to complete the project?

d. Which activities have slack, and how much?

  • B

    1 week

    H

    2 weeks

    F

    4 weeks.
  • C

    5 weeks

    F

    2 weeks

    G

    2 weeks.
  • A

    2 weeks

    C

    3 weeks

    F

    1 week.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

6 I - G 5 _DS critical fath? ABDEL as it has longest time Weeks Taken :- 25 slack in C-5 weeles F. 2 weeks G-2 weels

Add a comment
Know the answer?
Add Answer to:
chedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 5 B A...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT