Question

Given the following activities and precedents, draw a PERT/CPM diagram. ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A...

Given the following activities and precedents, draw a PERT/CPM diagram.

ACTIVITY

IMMEDIATE PREDECESSOR

DURATION (DAYS)

A

-

10

B

-

12

C

A

4

D

A, B

8

E

A, B

9

F

C

10

G

D, F

12

H

E, G

15

Answer the following:

  • What is the critical path?
  • How long will it take to complete this project?
  • Can activity E be delayed without delaying the completion of the project? If so, how many days?
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Activity ES EF LS LF Slack
A 0 10 0 10 0
B 0 12 4 16 4
C 10 14 10 14 0
D 12 20 16 24 4
E 12 21 27 36 15
F 14 24 14 24 0
G 24 36 24 36 0
H 36 51 36 51 0

Slack = LS-LF=EF-ES

Critical path is the longest path which is A-C-F-G-H with duration of 51 days

It will take 51 days to complete the project

Activity E has slack of 9 days so E can be delayed by maximum 9 days without delaying the completion of the project

Add a comment
Know the answer?
Add Answer to:
Given the following activities and precedents, draw a PERT/CPM diagram. ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT