Question

Which one is not correct about the critical path method (CPM) in project management? Duration of...

Which one is not correct about the critical path method (CPM) in project management? Duration of a project is equal to the duration of its critical path. There could be more than one critical paths. Crashing a project is shortening the duration of the critical activities. The tasks on the critical path can be delayed without delaying the project duration. Slack times of activities on a critical path are zero.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. D. The tasks on the critical path can be delayed without delaying the entire project.


Critical path method works on the assumptions that there is a particular chain which has the longest duration and slack value of 0. Since we have made the following assumptions, we can say that any slack introduced to the chain would end up increasing the duration of the project.


**PLEASE RATE THE ANSWER WITH A POSITIVE FEEDBACK

Add a comment
Know the answer?
Add Answer to:
Which one is not correct about the critical path method (CPM) in project management? Duration of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT