Question

1. When finding the approximate probability of project duration, it is necessary to know which of...

1. When finding the approximate probability of project duration, it is necessary to know which of following?

a. The mean and variance of each activity

b. The mean of each activity on the CP

c. The sd of only the activities on the CP

d. Each activity's probability of completion

e. The distribution of activity times

2. The sd of a path is computed as:

a. the sum of the sd of all activities on the path

b. the square root of the sum of the sd of all activities on the path

c. the sum of variances of all activities on the path

d. the square root of the sum of variances of all activities on the path

e None of above

3. An activity has an optimistic time estimate of three days, a most like time estimate of eight days, and a pessimistic time estimate of ten days. The expected duration of the activity is?

4. Activity C in a project network has an optimistic time estimate of five days, a most like time estimate of seven days, and a pessimistic time estimate of nine days. The expected duration of the activity is?

5. There are four activities on the critical path, and they have sd of 1,2,4 and 2 days. The sd of the critical path is?

6. There are four activities on the critical path. Coincidentally, their sd are all equal to 4. The sd of the critical path is therefore equal to?

7. The project management strategy of injecting additional resources in order to reduce the length of the project is called?

8. In crashing a project, a manager will generally focus on activities which:

a. are not on the critical path

b. are the least costly to crash

c. are costly to crash and are on the critical path

d. are on the cp and are the least costly to crash

e. none of above

9. At which point does crashing of a project cease?

a. when the project is completed

b. when no additional crashing is possible

c. when the cost to crash equals or exceeds the benefit of crashing

d. all of above

e. none of above

10. which of the following are ways of crashing an activity?

a. using overtime

b. hiring more workers

c. using specialized equipment

d. all of the above

e. none of the above

11. When using linear programming to make crashing decisions, the objective is to minimize

a. the total cost of crashing the project

b. the total of the durations of the activities on the cp

c. the latest finish time of the finish node

d. the total number of activities on the cp

e. none of the above

12. PERT/Cost

a. finds the penatly cost if a project is not completed on time

b. compares the actual budget with the planned budget

c. shows management where to focus attention during the project

d. a and b only

e. b and c only

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. b - The mean of each activity on the CP

2. d. the square root of the sum of variances of all activities on the path

3. Pert Estimate = (Optimistic + (4 X Most Likely) + Pessimistic)/6

Pert Estimate = (3+(4*8)+10)/6 = 45/6 = 7.5 days

4. Pert Estimate = (Optimistic + (4 X Most Likely) + Pessimistic)/6

Pert Estimate = (5+(4*7)+9)/6 = 42/6 = 7

Add a comment
Know the answer?
Add Answer to:
1. When finding the approximate probability of project duration, it is necessary to know which of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 5. A project has critical path activities A, B, and C. A is the predecessor of B. B is the predec...

    5. A project has critical path activities A, B, and C. A is the predecessor of B. B is the predecessor of C. The duration estimate for activity A, B and C is shown in the following table. Fill the table with mean duration, standard deviation, and variance for activities and the whole project (critical path). Determine what is the probability of completing this project within 80 days? (10 points) Activity Optimistic Pessimistic Most likely Mean Standard Variance deviation duration...

  • It was determined on the following project that the duration for the tasks contained some uncertainty....

    It was determined on the following project that the duration for the tasks contained some uncertainty. After more research, the optimistic and pessimistic values were determined. 1. a. Calculate the expected time and variance (using the 95 percent level of confidence) for each activity. b. Determine the critical path and time for completion c. Calculate the probably that the project will finish in 30 days. Calculate the probably of completing the project in 27 days. Other than the critical path,...

  • 1. Sid Orland is involved in planning a scientific research project. The activities are displayed in the following...

    1. Sid Orland is involved in planning a scientific research project. The activities are displayed in the following diagram. Optimistic, most likely, and pessimistic time estimates are displayed in the following table. Figure for Problem 1. r e 14 16 E 4 H 4 7 11 7 11 16 20 G 5 0 33 611 16 11 16 D 3 Most Likely Pessimistic Activity Optimistic 4 4 (a) Determine the expected times and variances for each activity along the critical...

  • 1. State whether each of the following statement is true or false. a) The sequence of...

    1. State whether each of the following statement is true or false. a) The sequence of activities in a project is depicted by the precedence (0.5 mark) (0.5 mark) relationships. The critical path is the shortest path through the project network. Slack is the amount of time an activity can be delayed without delaying the project. In PERT, three time estimates (optimistic, most likely and pessimistic) provide an estimate of the mean and variance for each activity based on the...

  • Use a PERT network to establish the expected duration for the project described in the table...

    Use a PERT network to establish the expected duration for the project described in the table below:    (SHOW the PERT NETWORK) Activity Predecessors Duration a        m       b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400         600 D B, C 4 6 8 200                             600 E B, C 6 9 12 400 300 F C 4 6 14...

  • The table below gives the optimistic, most-likely, and pessimistic time estimates (in weeks) for all activities in a project. (Statistical tables are available in appendix I) Activ Predecessor totm t...

    The table below gives the optimistic, most-likely, and pessimistic time estimates (in weeks) for all activities in a project. (Statistical tables are available in appendix I) Activ Predecessor totm t 2.0 5.0 8.0 3.0 4.0 5.0 4.06.08.0 5.0 6.0 7.0 3.0 6.0 9.0 D, E (i) Calculate the estimated time and variance for each task (ii) Draw the AON diagram and identify the critical path. (iii) What is the expected critical path duration and estimate a standard deviation for the...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • need help Crashing 6. When deciding on whether or not to crash project activities, a project...

    need help Crashing 6. When deciding on whether or not to crash project activities, a project manager was faced with the following information. Activities of the critical path are highlighted with an asterisk: 1992 Normal Crashed Activity A B* Extra Cost $4,000 $3,000 $3,500 D* Cost $5,000 $10,000 $3,500 $4,500 $1,500 $7,500 $3,000 $2,500 Duration 4 weeks 5 weeks 2 weeks 6 weeks 3 weeks 8 weeks 7 weeks 6 weeks $4,000 $2,500 Duration 3 weeks 4 weeks 1 week...

  • Given below is the crashing data for a project along with other data. The project completion...

    Given below is the crashing data for a project along with other data. The project completion time is 20 davs. Determine: (a) the crash slope (i.e crash cost/day) for all activities, (b) the normal total project cost, (c) prioritized the list of activities for crashing from best to worst, (d) the best activity to crash if the project has to be completed in 19 days and alternative critical paths, if any, (e) the earliest time the project can be completed,...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 nar Case Study A Table 1 below contains activities associated with a...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT