Given below is the crashing data for a project along with other data. The project completion...
What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? A)By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) B) The total cost of crashing the project by 4 days is $. (Enter your response as a whole number.) Normal Crash Time Normal Total Cost Activity Time (days) (days)...
What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Crash Time Normal Activity Time (days) (days) Cost $800 $250 $600 $750 $1,200 Uw > A Awarw Total Cost with Crashing Immediate Predecessor(s) $1,100 $600 $650 $1,500 $1,650 OD By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.)...
If you would like to reduce the overall completion time of the project by 1 day, which activity (A, B, C, D, E, F, G, or H) should be crashed? The list of activities of a data analysis project, their precedence relationships, and their activity times (in number of days) are given in the table below. Activity ID Predecessors Activity Time (Days) A 3 B А 4 с B 2 D с 5 E B 7 F с 2 G...
Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...
Below is a four-activity project network presented in activity-on-node form, along with information on crashing opportunities for each activity: Crash Cost Per Activity Normal Minimum Possible Time Time Complete the following tabulation of crashing cost vs. project length: Step ProjectIncremental Crashing Cost/Da Total Crashing Cost Activities to Crash Length 16 Below is a four-activity project network presented in activity-on-node form, along with information on crashing opportunities for each activity: Crash Cost Per Activity Normal Minimum Possible Time Time Complete the...
Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,0003,300B...648,0009,000CA114,0004,000 DA543,5004,000EB434,7505,500FC222,0002,000 GD114,0004,000HD,F323,5003,750IE,G323,0004,250JE215,0007,000Since no indirect cost nor penalty cost information is offered, please consider the schedule and crash cost issues only.1. Using Table of Crashing Decision, what is the earliest completion time of this project if normal times are used for all activities?A. fewer than 13 weeks; B. 13 weeks; C. 14 weeks; D. more than 14 weeks2. Using Table of Crashing Decision, what is the minimum time schedule for this project?A. fewer than 8 weeks; B. 8...
What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? IMMEDIATE PREDECESSOR(S) ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) NORMAL TIME (DAYS) 9 7 5 6 CRASH TIME NORMAL (DAYS) COST 7 200 6 800 4 600 4 1,100 6 1,200 CRASH COST 300 875 675 1,300 1,875 9 A,B с The minimum cost of crashing the following project at Sawaya Robotics by. 4 days is $ whole number)....
What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Please show work and calculations. NORMAL CRASH TIME ACTIVITY (DAYS) (DAYS) TIME NORMAL CRASH COST IMMEDIATE COST PREDECESSOR(S) 900 $1,000 B 300 400 C 4 3 500 600 5 3 900 1,200 A 5 1,000 1,600 C LO LO C Ln LLI NORMAL CRASH TIME ACTIVITY (DAYS) (DAYS) TIME NORMAL CRASH COST IMMEDIATE COST PREDECESSOR(S) 900 $1,000 B 300...
1) Based on the given information regarding the activities for the project, the project length= ___ weeks. 2) The total cost required for completing this project on normal time= $____ 3) For reducing the duration of the project by one week, the activity that should be crashed first is activity ___. 4) The cost of the project based on the first activity selected for crashing will increase by $___. 5) The maximum weeks by which the project can be reduced...
.8-6. A project consists of 12 activities, represented by the project network below, where number by each arc represents the duration (in days) of the associated activity 4 12 4 12 10 a) Find the earliest time, latest time, and slack for each event as well as the slack for each activity. Also identify the critical path. (b) The project has been scheduled to be completed in the minimum possible time.If all previous activities have begun as early as possible...