If you would like to reduce the overall completion time of the project by 1 day, which activity (A, B, C, D, E, F, G, or H) should be crashed?
First I have prepared network Diagram based on the above table:
Legend:
Current project completion time is 19 days
we will reduce project completion time by 1 day, hence, we will crash critical path activities and lowest cost activities, here, we can crash A or G, we will crash A as Crash cost per day for activity A=300 that is lowest one, hence, we will crash A
If you would like to reduce the overall completion time of the project by 1 day,...
The table below defines the activities and the normal time duration for each activities within a small project. You can decrease (crash) the durations at an additional expense. Table 1 summarizes the time-cost information for the activities to complete the project. Table 1: The time-cost information for the activities Activity Normal Completion Time (weeks) Immediate Predecessor Crash Time (weeks) Normal cost for activities Crash cost for activities/week A 2 - 1 1200 400 B 3 - 1 1400 500 C...
QUESTION 5 Given is a CPM project network diagram as shown below. A с F Start E H End B D Start A B E H End Activity day с 7 D 3 F 5 G 6 0 2 4 3 0 a) The Project Completion time = days. b) The Earliest Start time, Es, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C - days. d) The critical activities are (ex. Fill in answer...
Given below is the crashing data for a project along with other data. The project completion time is 20 davs. Determine: (a) the crash slope (i.e crash cost/day) for all activities, (b) the normal total project cost, (c) prioritized the list of activities for crashing from best to worst, (d) the best activity to crash if the project has to be completed in 19 days and alternative critical paths, if any, (e) the earliest time the project can be completed,...
Given is a CPM project network diagram as shown below. A F Start E H End B D G Start H Activity day А 6 B 3 с 8 D 7 E 4 F 9 G 4 End 0 0 6 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G - days. c) The Latest Finish time, LF, of Acitivity - dayy d) The critical activities are (ex. Fill in answer as: ABCD)
Given is a CPM project network diagram as shown below. A וד H End Start التا B D G A F H Activity day Start 0 B 8 с 3 D 5 E 6 وانما | End 0 8 4 a) The Project Completion time = days b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days d) The critical activities are = (ex. Fill in answer as:...
2. Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest completion time (EF), latest completion time (LF) and slack for each of the following tasks (begin at time 0). Which tasks are on the critical path? Highlight the critical path on your network diagram [5] Activity Preceding Expected EF LF Slack Critical Event Duration Path? A 4 A 5 C A 6 A 7 E A, D 6 C, E 4 G D, E...
Question 8-10, CHAPTER 18: A home-remodeling project consists of eight activities. The immediate predecessors and activity times in weeks are shown below. Activity Predecessor(s) Normal Time Crash Time Normal Cost $400 Crash Cost $700 1600 2000 800 1100 1000 NNW 600 1200 1450 800 800 500 650 400 600 900 1300 F G H1 1000 650 8. Draw the network for this project. (10 points) 9. Please indicate the Earliest Start, Earliest Finish, Latest Start, and Latest Finish on the...
Provide step by step please thank you, no exce Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest completion time (or early finish-EF), latest completion time (or late finish-LF), and slack for each of the following tasks (begin at time 0) the critical path on your network diagram. . Which tasks are on the critical path? Highligh Preceding Expected Critical Path? Activity Event Duration EF LF Slack A, D C,E D, E F, G...
QUESTION 1 Part1. The total expected project completion time is: A. 10 days B. 11 days C. 15 days D. none of the above Part 2. What is the effect of a delay of 1 day in distributing tickets? A. no impact B. the project will delay by one day C. the project will delay by more than one day D. same as the effect of a delay of 1 day in setting up radio ads Part 3. What is...
QUESTION 5 Given is a CPM project network diagram as shown below. А F Start E H End B D G Start A B C D E F G H End Activity day 0 6 زر 8 7 4 9 4 6 0 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G= days. c) The Latest Finish time, LF, of Acitivity C = days. d) The critical activities are = (ex. Fill in...