Question

What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4​ days?

Normal Crash Time Normal Total Cost Activity Time (days) (days) Cost with Crashing Immediate Predecessor(s) S300 S600 $750 $1,200 $1,100 $500 $650 $1,500 $1,650 2

A)By how many days should each activity be crashed to reduce the project completion time by 4​ days? Fill in the table below. ​(Enter your responses as whole numbers.​)

Each Activity Should be Reduced BY (days) Activity

B) The total cost of crashing the project by 4 days is $. (Enter your response as a whole number.)

1 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

(a)

Let us first look at the network diagram -

Hence, the possible network paths and their durations are -

AD --> 6+5 = 11 days
B --> 7 days
CE --> 6+4 = 10 days

Hence, the project duration is 11 days (duration of the longest path which is the critical path)

The project duration has to be crashed by 4 weeks => Required project Duration = 7 days

For path AD, A can be crashed by 1 day and D can be crashed by 3 days, bringing duration to 7 days

Path B need not be crashed

For Path CE, C can be crashed by 1 day and E can be crashed by 2 days, bringing duration to 7 days

Hence, the Activities should be crashed as below -

Activity Each activity should be reduced by (days)
A 1
B 0
C 1
D 3
E 2

(b) Cost of crashing = cost of crashing A + Cost of crashing C + cost of crashing D + Cost of crashing E

= (1100-800) + (650-600) + (1500-750) + (1650-1200) = $1,550

Add a comment
Know the answer?
Add Answer to:
What is the minimum cost of crashing the following project that Roger Solano manages at Slippery...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • What is the minimum cost of crashing the following project that Roger Solano manages at Slippery...

    What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Crash Time Normal Activity Time (days) (days) Cost $800 $250 $600 $750 $1,200 Uw > A Awarw Total Cost with Crashing Immediate Predecessor(s) $1,100 $600 $650 $1,500 $1,650 OD By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.)...

  • What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 da...

    What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Please show work and calculations. NORMAL CRASH TIME ACTIVITY (DAYS) (DAYS) TIME NORMAL CRASH COST IMMEDIATE COST PREDECESSOR(S) 900 $1,000 B 300 400 C 4 3 500 600 5 3 900 1,200 A 5 1,000 1,600 C LO LO C Ln LLI NORMAL CRASH TIME ACTIVITY (DAYS) (DAYS) TIME NORMAL CRASH COST IMMEDIATE COST PREDECESSOR(S) 900 $1,000 B 300...

  • What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days?...

    What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? IMMEDIATE PREDECESSOR(S) ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) NORMAL TIME (DAYS) 9 7 5 6 CRASH TIME NORMAL (DAYS) COST 7 200 6 800 4 600 4 1,100 6 1,200 CRASH COST 300 875 675 1,300 1,875 9 A,B с The minimum cost of crashing the following project at Sawaya Robotics by. 4 days is $ whole number)....

  • Given below is the crashing data for a project along with other data. The project completion...

    Given below is the crashing data for a project along with other data. The project completion time is 20 davs. Determine: (a) the crash slope (i.e crash cost/day) for all activities, (b) the normal total project cost, (c) prioritized the list of activities for crashing from best to worst, (d) the best activity to crash if the project has to be completed in 19 days and alternative critical paths, if any, (e) the earliest time the project can be completed,...

  • Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3...

    Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...

  • For the following project: Normal Time Crash Time Normal Cost Crash Cost Immediate (weeks 4. Activity...

    For the following project: Normal Time Crash Time Normal Cost Crash Cost Immediate (weeks 4. Activity Predecessor (weeks) $2,600 $2,800 $2,000 $2,200 $500 $2,300 $900 $3,000 $500 $2,600 $1,200 $4,200 $1,400$2,000 4 D, E How long will the project take? What is the total cost to complete the project in normal time? If the project is to be shortened by 1 week, which activity will be reduced and how much will the cost be increased? What is the maximum time...

  • 1) Based on the given information regarding the activities for the project, the project length= ___...

    1) Based on the given information regarding the activities for the project, the project length= ___ weeks. 2) The total cost required for completing this project on normal time= $____ 3) For reducing the duration of the project by one week, the activity that should be crashed first is activity ___. 4) The cost of the project based on the first activity selected for crashing will increase by $___. 5) The maximum weeks by which the project can be reduced...

  • Solve the following project crashing problem adopted from Heizer et al. (2016). Attempt the question before looking up the solution on Page 855 of Heizer et. al. 2016 3.32Kimpel Products makes pi...

    Solve the following project crashing problem adopted from Heizer et al. (2016). Attempt the question before looking up the solution on Page 855 of Heizer et. al. 2016 3.32Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are given in the following table: NORMAL CRASH TIME TIME NORMALI CRASH! IMMEDIATE ACTIVITY (WEEKS) (WEEKS) COST...

  • QUESTION 27 What is the cost of crashing the project represented in the table below, by...

    QUESTION 27 What is the cost of crashing the project represented in the table below, by 3 days? Immediate Normal Crash Normal Crash Activity Predecessors Time/Days Time/Days Cost Cost А 3 2 $200 $500 B А 3 2 $350 $550 С А 2 1 $300 $250 D B&C 3 $500 $550 E С 2 $500 $900 F D&E . $500 $1,000 NN $150 $450 $550 $2450 $2750 QUESTION 1 According to Michael Porter, the primary activities in a value chain...

  • Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's...

    Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: To Cost Normal Time (weeks) Crash Time Normal with Activity (weeks) Cost Crashing Immediate Predecessor(s) $2.700 A $2,000 7 $2,300 S3,100 3 $500 $500 S2,300 $2,580 A E 5900 $1.275 F F $3.400 2 S4,800 C G $1,500 $2.100 D, E a) Based on...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT