a) Project completion time is determined by the critical path which is A-D-G = 3+7+4 = 14 weeks
Other path = BEG = 2+6+4 = 12 weeks
b) The project can be shortened by crashing activities on the critical path.
Crashing cost / week= (Crash cost of activity - Normal cost) / Crashed weeks
First activity to crash is D by 2 weeks at lowest per crashing cost of (1700 -1400) / 4 = $75 per week , Total cost at the step = 75*2 = 150 ----(1)
Next we should crash D and G by 2 weeks for an additional total per week cost of 75 + (2000-1500) / 2 = $325 / week , Total cost at the step = 325*2 = 650 ----(2)
c) Now the path ADG is 8 weeks, BEG is 10 weeks
Crash E by 2 weeks at a per week cost of (1200- 900)/ 3= $100 / week, Total cost at the step = 100*2 = 200----(3)
Next, one should crash activity A and activity E by 1 week at total cost per week crashing cost of (2050-1400) / 1 + 100 = $750 , Total cost here = $750----(4)
Total cost of crashing project to 7 weeks= (1) + (2) + (3) + (4) = 150 + 650 + 200 + 750 = $1750
Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3...
Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table: Activity A Normal Time (weeks) 3 Crash Time (weeks) 2 B 2 1 1 Normal Cost $1,200 $2,000 $400 $1,500 $950 $4,500 $1,600 Total Cost with Immediate Crashing Predecessor(s) $1,800 $2,800 $400 $1,820 A $1,250 B $5,500 с $2,300...
For the following project: Normal Time Crash Time Normal Cost Crash Cost Immediate (weeks 4. Activity Predecessor (weeks) $2,600 $2,800 $2,000 $2,200 $500 $2,300 $900 $3,000 $500 $2,600 $1,200 $4,200 $1,400$2,000 4 D, E How long will the project take? What is the total cost to complete the project in normal time? If the project is to be shortened by 1 week, which activity will be reduced and how much will the cost be increased? What is the maximum time...
Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table: Activity Normal Time(weeks) Crash Time(weeks) Normal Cost Total Cost with Crashing Immediate Predecessor(s) A 3 2 $ 1,200 $1,800 — B 2 1 $2,100 $2,900 __ C 1 1 $400 $400 — D 7 3 $1,300...
Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 A None None None B Cost Normal Crash 1000 1600 2000 2700 300 300 1300 1600 2 1 С 1 1 D A 7 3 E 6 3 B с 1000 5000 F 2 850 4000 1500 NA G D. E 4 2000 What's the normal project completion time? Identify the critical path If you'd like to shorten the project by one week, which activity should you...
Kampel Products makes a vento comerciales C related data are in the following table o ng r eso de Nom e Act Crash Time Normal wek) Court $1.000 $2300 SD 51.000 5900 $4500 $1,300 Cost with dia Casing Predeces) 100 $100 $100 5700 51125 $5500 52 300 thing the activities a) Based on the given information regarding the activities for the project the project completion date wooks b) To reduce the duration of the project 10 weeks at the least...
Lecture Exercise #13 Project Crashing Time (weeks) Cost Activity Predecessori s) Normal Crash Normal Crash A None 3 2 1000 1600 B None 2 1 2000 2700 C None 1 1 300 300 D A 7 3 1300 1600 E B 6 3 850 1000 F с 2 1 4000 5000 D, E 2000 G 4 2 1500 What's the normal project completion time? Identify the critical path If you'd like to shorten the project by one week, which activity...
Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,0003,300B...648,0009,000CA114,0004,000 DA543,5004,000EB434,7505,500FC222,0002,000 GD114,0004,000HD,F323,5003,750IE,G323,0004,250JE215,0007,000Since no indirect cost nor penalty cost information is offered, please consider the schedule and crash cost issues only.1. Using Table of Crashing Decision, what is the earliest completion time of this project if normal times are used for all activities?A. fewer than 13 weeks; B. 13 weeks; C. 14 weeks; D. more than 14 weeks2. Using Table of Crashing Decision, what is the minimum time schedule for this project?A. fewer than 8 weeks; B. 8...
1) Based on the given information regarding the activities for the project, the project length= ___ weeks. 2) The total cost required for completing this project on normal time= $____ 3) For reducing the duration of the project by one week, the activity that should be crashed first is activity ___. 4) The cost of the project based on the first activity selected for crashing will increase by $___. 5) The maximum weeks by which the project can be reduced...
The information about a project is shown below. Duration Immediate Budgeted Cost Activity (weeks) Predecessor(s) ($/week) A T 3 none 40,000 в з А 22,000 C2A 17,000 D 3 B 27,000 E5C 16,000 The above table shows that the budgeted cost of activity E is $16,000 per week. NOTE: Do not use any comma in your answer. The cumulative budgeted cost at the end of week 4 is dollars The cumulative Juugeleu cost at the NOTE: Do not use any...
2. What is the cost of the third crash? 3.What is the cost of the fifth crash? 4.What is the total cost of all crashes that should be done to minimize costs? Use this info for questions 9 through 13. Chuck's Custom Boats (CCB) builds customer luxury yachts. CCB has landed a contract with a mysterious New York real estate developer, Mr. T. Relevant data on the project are shown below. The complication is that Mr. T wants delivery in...