Question

Kimpel Products makes pizza ovens for commercial use. James​ Kimpel, CEO, is contemplating producing smaller ovens...

Kimpel Products makes pizza ovens for commercial use. James​ Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following​ table:

                                                                                                                                 

Activity

Normal Time​(weeks)

Crash Time​(weeks)

Normal Cost

Total Cost with Crashing   

Immediate​ Predecessor(s)

A

3

2

$ 1,200

$1,800

B

2

1

$2,100

$2,900   

__

C

1

1

$400

$400

D

7

3

$1,300

$1,620

A

E

6

3

$850

$1,075

B

F

2

1

$4,500

$5,500

C

G

4

2

$1,500

$2,000

​D, E

​a) Based on the given information regarding the activities for the​ project, the project completion date​ = ___ weeks

b) To reduce the duration of the project to 10 weeks at the least? cost, the following is the order of what needs to be followed while crashing the activities:

The first activity to crash is ___ by 2 weeks at a per week crashing cost of ____ dollars.

Next, one should crash activity (answer from above) and activity ____ by 2 weeks weeks for an additional total per week crashing cost of ____ dollars.

c) New requirements are to reduce the project to 7 weeks. Continuing to crash the activities from 10 weeks based on the above crashing already completed, the following is the order for crashing:

Next activity to crash in order is ___ by 2 weeks weeks at a per week crashing cost of ____ dollars.

Next, one should crash activity ___and activity E by 1 week at a total per week crashing cost of ___ dollars.

Total cost of crashing the project to 7 weeks = ___ dollars.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

With the given data, we compute the below table :

Normal Crashed (weeks) Costs Time Crashed Earliest Earliest Latest Latest Finish Start Finish Max Crashing Cost Immediate Start Predecessors Time Cost (weeks) Cost $ Difference Crashing per day Activity Slack=LS-ES (days) (CC-NC)/ (NT ES EF NC CT CC- NC 600 800 NT- CT 1,200 2,100 1,800 2,900 600 800 12 10 10 14 14 10 1,300 850 4,500 1500 1,620 1,075 5,500 2,000 320 75 12 1,000 1,000 D, E 10 14 10

a) The project completion date = 14 weeks

b) The critical path is the one having activities having zero slack and has the longest completion time.

There are 3 paths :

Path 1 = A-D-G = 3+7+4 = 14 weeks : CRITICAL PATH

Path 2 = B-E-G = 2+6+4 = 12 weeks

Path 3 = C-F = 1+2 = 3 weeks

A-D-G is the critical path and here Activity D has the lowest per week crashing cost.

So, we crash Activity D by 2 weeks at cost of $80 per week

Path 1 = A-D-G = 3+5+4 = 12 weeks : CRITICAL PATH

Path 2 = B-E-G = 2+6+4 = 12 weeks : CRITICAL PATH

Path 3 = C-F = 1+2 = 3 weeks

Now, B-E-G also becomes critical path along with A-D-G and we crash the activity G to reduce both these paths

So, we crash Activity G by 2 weeks at cost of $250 per week

c) Now the 3 paths are :

Path 1 = A-D-G = 3+5+2 = 10 weeks : CRITICAL PATH

Path 2 = B-E-G = 2+6+2 = 10 weeks : CRITICAL PATH

Path 3 = C-F = 1+2 = 3 weeks

To complete the project to 7 weeks, we need to crash both the critical paths by 3 weeks.

G had a maximum crashing of 2 weeks and already done above. So further crashing is not possible for G.

D can be crashed further by 2 weeks at cost of $80 per week

E can be crashed further by 2 weeks at cost $75 per week

A can be crashed by 1 week at cost of $600 per week

E can be crashed further by 1 week at cost $75 per week

The final paths are :

Path 1 = A-D-G = 2+3+2 = 7 weeks : CRITICAL PATH

Path 2 = B-E-G = 2+3+2 = 7 weeks : CRITICAL PATH

Path 3 = C-F = 1+2 = 3 weeks

Total Cost of crashing the project to 7 weeks = 2*80 + 2*250 + 2*80 + 2*75 + 1*600 + 1*75 = 160+500+160+150+600+75

Total Cost of crashing the project to 7 weeks = $1,645

Add a comment
Know the answer?
Add Answer to:
Kimpel Products makes pizza ovens for commercial use. James​ Kimpel, CEO, is contemplating producing smaller ovens...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens...

    Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table: Activity A Normal Time (weeks) 3 Crash Time (weeks) 2 B 2 1 1 Normal Cost $1,200 $2,000 $400 $1,500 $950 $4,500 $1,600 Total Cost with Immediate Crashing Predecessor(s) $1,800 $2,800 $400 $1,820 A $1,250 B $5,500 с $2,300...

  • Kampel Products makes a vento comerciales C related data are in the following table o ng...

    Kampel Products makes a vento comerciales C related data are in the following table o ng r eso de Nom e Act Crash Time Normal wek) Court $1.000 $2300 SD 51.000 5900 $4500 $1,300 Cost with dia Casing Predeces) 100 $100 $100 5700 51125 $5500 52 300 thing the activities a) Based on the given information regarding the activities for the project the project completion date wooks b) To reduce the duration of the project 10 weeks at the least...

  • Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3...

    Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...

  • Solve the following project crashing problem adopted from Heizer et al. (2016). Attempt the question before looking up the solution on Page 855 of Heizer et. al. 2016 3.32Kimpel Products makes pi...

    Solve the following project crashing problem adopted from Heizer et al. (2016). Attempt the question before looking up the solution on Page 855 of Heizer et. al. 2016 3.32Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are given in the following table: NORMAL CRASH TIME TIME NORMALI CRASH! IMMEDIATE ACTIVITY (WEEKS) (WEEKS) COST...

  • The following is a table of activities associated with a project at Rafay Ishfaq's software firm...

    The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Duration (weeks) Activity A (start) Precedes B, C Crash Cost/Week $400 $100 $200 $300 $400 F F (end) 2 Suppose that Rafay is only given 5 weeks (instead of 7) to complete the project. By how many weeks should each activity be crashed in order to...

  • Development of a new deluxe version of a particular toy is being considered by T-O-Y Inc....

    Development of a new deluxe version of a particular toy is being considered by T-O-Y Inc. The activities necessary for the completion of this project along with the relevant information for each activity are listed in the following table. The Total Crash Time represents the time for that activity after it has been crashed the maximum crash time allowed for that activity. For example, we can reduce the time for Activity A by one week to 3 weeks after crashing...

  • Suppose that Rafay is only given 7 weeks (instead of 10) to complete the project ....

    Suppose that Rafay is only given 7 weeks (instead of 10) to complete the project . By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. Activity Each Activity Should be Reduced BY (weeks) A (weeks)- ? B (weeks)- ? C (weeks)- ? D (weeks)- ? E (weeks)- ? F (weeks)- ? What is the total crashing cost ? The following is a...

  • Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's...

    Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: To Cost Normal Time (weeks) Crash Time Normal with Activity (weeks) Cost Crashing Immediate Predecessor(s) $2.700 A $2,000 7 $2,300 S3,100 3 $500 $500 S2,300 $2,580 A E 5900 $1.275 F F $3.400 2 S4,800 C G $1,500 $2.100 D, E a) Based on...

  • I just need the last two parts of the question answered. PM.66 Real estate developer Russell Call was working with a fe...

    I just need the last two parts of the question answered. PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) $1,050 $2,000 $2,560 $2,600 $1,300 $2,600 $2,200 $1,800 $2,400 4 $4,200 $5,540 $2,050 4...

  • I ONLY need help on letters G and I. According to the answers I've tried for...

    I ONLY need help on letters G and I. According to the answers I've tried for these, it is NOT Activity G for the letter G and not $2,120 for letter I. M5_A5. A computer installation project is being reviewed. Assume the project has to be completed in 16 weeks. Crash the project as necessary (crashing one week at a time). The relevant information is in the table below. CRASH STANDARD STANDARD CRASH IMMEDIATE ACTIVITY TIME TIME COST PREDECESSORS COST...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT