There are 2 paths for completing the project:
A-B-E-F => 1+1+2+2 = 6 weeks
A-C-F=> 1+4+2 = 7 weeks
Hence Critical Path is ACF and 7 weeks
The objective is to crash project from 7 to 5 weeks.
First we evaluate the Crticial path
Activity | Crash cost per week | Rank (l - h) |
A | 400 | 2 |
C | 200 | 1 |
F | 400 | 2 |
Hence we crash C by a week. Total Crash cost is $ 200 ...(1)
So we have two critical paths A-C-F and A-B-E-F of 6 weeks. We further need to crash 1 more week. Hence we evaluate again as follows:
Activity | Crash cost per week | Rank (l - h) |
A | 400 | 4 |
B | 100 | 1 |
C | 200 | 2 |
E | 300 | 3 |
F | 400 | 4 |
Hence, for ABEF we crash B by 1 week and for ACF we crash C by one week. So we have, Total Crash Cost 100+200 = 300$ ...(2)
Our New critical paths are ABEF and ACF and duration is 5 weeks.
So,
Activity | Reduced by weeks |
A | 0 |
B | 1 |
C | 2 |
E | 0 |
F | 0 |
Total Crash cost = (1) +(2) above => 200 + 300 = 500.
The following is a table of activities associated with a project at Rafay Ishfaq's software firm...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Activity Duration (weeks) Precedes Crash Cost/Week A (start) 2 B, C $ 370 B 2 E $ 130 C 4 F $ 200 E 1 F $ 150 F (end) 2 — $ 420 Suppose that Rafay is only given 5 weeks (instead of 8) to...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Duration(Weeks) Activity Precedes 3 A(start) В.С В 2 5 C F E 2 F F(end) b- The activites on the critical path are: A C- F c- The total project completion time for Rafay Ishfaq's software firm is weeks. d- Determine the slack time for each of the activities. e- What is the total...
Suppose that Rafay is only given 7 weeks (instead of 10) to
complete the project . By how many weeks should each activity be
crashed in order to meet the deadline? Assume that you can crash an
activity down to 0 weeks duration.
Activity
Each Activity Should be Reduced BY (weeks)
A
(weeks)- ?
B
(weeks)- ?
C
(weeks)- ?
D
(weeks)- ?
E
(weeks)- ?
F
(weeks)- ?
What is the total crashing cost ?
The following is a...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Activity A (start) B с E F(end) Duration (weeks) 3 8 3 4 Precedes B, C F E F 2 This exercise contains only parts b, c, and d. b) The activities on the critical path are A-B-F c) The total project completion time for Rafay Ishfaq's software firm is 13 weeks. (Enter your...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what adivities each must precede Activity Duration (weeks) Precedes A (start) Fendi This exercise contains only parts and d. b) The activities on the critical path are c) The total project completion time for Rafay Ishlad's software firm is weeks. (Enter your response as a whole number) d) Determine the slack time for each of the activities. (Enter your...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Activity Duration (weeks) Precedes A (start) 2 B, C B 2 E C 6 F E 3 F F (end) 4 — This exercise contains only parts b, c, and d. b) Define the critical path, listing all critical activities in chronological order. Critical path activities are the activities that lie on the longest...
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: To Cost Normal Time (weeks) Crash Time Normal with Activity (weeks) Cost Crashing Immediate Predecessor(s) $2.700 A $2,000 7 $2,300 S3,100 3 $500 $500 S2,300 $2,580 A E 5900 $1.275 F F $3.400 2 S4,800 C G $1,500 $2.100 D, E a) Based on...
1) Based on the given information regarding the activities for
the project, the project length= ___ weeks.
2) The total cost required for completing this project on normal
time= $____
3) For reducing the duration of the project by one week, the
activity that should be crashed first is activity ___.
4) The cost of the project based on the first activity selected
for crashing will increase by $___.
5) The maximum weeks by which the project can be reduced...
I just need the last two parts of the question answered.
PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) $1,050 $2,000 $2,560 $2,600 $1,300 $2,600 $2,200 $1,800 $2,400 4 $4,200 $5,540 $2,050 4...
Use a PERT network to establish the expected duration for the project described in the table below: (SHOW the PERT NETWORK) Activity Predecessors Duration a m b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400 600 D B, C 4 6 8 200 600 E B, C 6 9 12 400 300 F C 4 6 14...