Question

The following is a table of activities associated with a project at Rafay Ishfaqs software firm in Chicago, their durations

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity can be computed using the following formulae.

ES of the starting activities = 0
ES of all other activities = Max. (EF of their immediate predecessors)
EF of an activity = Its ES + Its duration

LF of ending activity = Max. (their EF)
LF of all other activities = Min. (LS of their immediate successors)
LS of an activity = Its LF - Its duration

Slack = LF - EF

Activity Predecessors Successors Duration ES EF LS LF Slack
A - B, C 3 0 3 0 3 0
B A E 2 3 5 4 6 1
C A F 5 3 8 3 8 0
E B F 2 5 7 6 8 1
F C, E - 3 8 11 8 11 0

The critical path is constituted of activities with zero slack.

(b) Activities on the critical path are A-C-F

(c) The total completion time for the project = 11 weeks

(d) and (e)

Activity Slack
A 0
B 1
C 0
E 1
F 0
Add a comment
Know the answer?
Add Answer to:
The following is a table of activities associated with a project at Rafay Ishfaq's software firm...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following is a table of activities associated with a project at Rafay Ishfaq's software firm...

    The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Activity A (start) B с E F(end) Duration (weeks) 3 8 3 4 Precedes B, C F E F 2 This exercise contains only parts b, c, and d. b) The activities on the critical path are A-B-F c) The total project completion time for Rafay Ishfaq's software firm is 13 weeks. (Enter your...

  • The following is a table of activities associated with a project at Rafay Ishfaq's software firm...

    The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what adivities each must precede Activity Duration (weeks) Precedes A (start) Fendi This exercise contains only parts and d. b) The activities on the critical path are c) The total project completion time for Rafay Ishlad's software firm is weeks. (Enter your response as a whole number) d) Determine the slack time for each of the activities. (Enter your...

  • The following is a table of activities associated with a project at Rafay​ Ishfaq's software firm...

    The following is a table of activities associated with a project at Rafay​ Ishfaq's software firm in​ Chicago, their durations and what activities each must​ precede: Activity Duration​ (weeks) Precedes A​ (start) 2 ​B, C B 2 E C 6 F E 3 F F​ (end) 4 — This exercise contains only parts​ b, c, and d. ​b) Define the critical​ path, listing all critical activities in chronological order. Critical path activities are the activities that lie on the longest...

  • The following is a table of activities associated with a project at Rafay Ishfaq's software firm...

    The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Duration (weeks) Activity A (start) Precedes B, C Crash Cost/Week $400 $100 $200 $300 $400 F F (end) 2 Suppose that Rafay is only given 5 weeks (instead of 7) to complete the project. By how many weeks should each activity be crashed in order to...

  • The following is a table of activities associated with a project at Rafay​ Ishfaq's software firm...

    The following is a table of activities associated with a project at Rafay​ Ishfaq's software firm in​ Chicago, their​ durations, what activities each must precede and the crash cost to reduce duration per​ week: Activity Duration​ (weeks) Precedes Crash​ Cost/Week A​ (start) 2 ​B, C $ 370 B 2 E $ 130 C 4 F $ 200 E 1 F $ 150 F​ (end) 2 — $ 420 Suppose that Rafay is only given 5 weeks​ (instead of 8​) to...

  • Suppose that Rafay is only given 7 weeks (instead of 10) to complete the project ....

    Suppose that Rafay is only given 7 weeks (instead of 10) to complete the project . By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. Activity Each Activity Should be Reduced BY (weeks) A (weeks)- ? B (weeks)- ? C (weeks)- ? D (weeks)- ? E (weeks)- ? F (weeks)- ? What is the total crashing cost ? The following is a...

  • QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are s...

    QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are shown follow. Time Immediate Activity (weeks) Predecessor 2 5 В 4 C 5 В 6 В.С D,E F What are the slack times of Activities D and E? 0 and 0, respectively 1 and 1, respectively 2 and 0, respectively 0 and 1, respectively 1 and 0, respectively shown follow. A firm is planning a project for the...

  • A Question 11 The following table provides a list of activities in a project, along with...

    A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...

  • The following activities of a hospital expansion project has been identified in the following table. First,...

    The following activities of a hospital expansion project has been identified in the following table. First, all activities of the project are listed. Next, the immediate predecessor(s) of each activity is identified (activity relationships). Please plot the activity network diagram and answer the following questions. Hospital Expansion Project Activity Description Immediate predecessor(s) Activity Time (Weeks) A Select administrative and medical staff - 12 B Select site and do site survey - 9 C Select equipment A 10 D Prepare final...

  • The table below defines the activities and the normal time duration for each activities within a...

    The table below defines the activities and the normal time duration for each activities within a small project. You can decrease (crash) the durations at an additional expense. Table 1 summarizes the time-cost information for the activities to complete the project. Table 1: The time-cost information for the activities Activity Normal Completion Time (weeks) Immediate Predecessor Crash Time (weeks) Normal cost for activities Crash cost for activities/week A 2 - 1 1200 400 B 3 - 1 1400 500 C...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT