Question

The following activities of a hospital expansion project has been identified in the following table. First,...

  1. The following activities of a hospital expansion project has been identified in the following table. First, all activities of the project are listed. Next, the immediate predecessor(s) of each activity is identified (activity relationships). Please plot the activity network diagram and answer the following questions.

    Hospital Expansion Project

    Activity

    Description

    Immediate predecessor(s)

    Activity Time (Weeks)

    A

    Select administrative and medical staff

    -

    12

    B

    Select site and do site survey

    -

    9

    C

    Select equipment

    A

    10

    D

    Prepare final construction plans and layout

    B

    10

    E

    Bring utilities to the site

    B

    24

    F

    Interview applicants and fill positions in nursing, support staff, maintenance, and security

    A

    10

    G

    Purchase and take delivery of equipment

    C

    35

    H

    Construct the hospital

    D

    40

    I

    Develop an information system

    A

    15

    J

    Install the equipment

    E, G, H

    4

    K

    Train nurses and support staff

    F, I, J

    6

    1) What are the project paths for hospital expansion project?

    a.

    AFK, AIK, ACGJK, BDHJK, BEJK

    b.

    AFK, AIK, ABDJK, BCGJK, BEJK

    c.

    AFK, AJK, ACGJK, BDHJK, BEIK

    d.

    AFK, AIK, ABGJK, BCHJK, BEJK

2) What is the project completion time in weeks?

a.

33 weeks

b.

43 weeks

c.

67 weeks

d.

69 weeks

3) Is activity H, constructing the hospital, a critical activity for this project? Please select the answer with the most appropriate justification.

a.

Yes, because H has the longest activity time of 40 weeks.

b.

Yes, because H is on the path with the most activities.

c.

Yes, because H is on the path with the longest total activity time.

d.

No, A should be the critical activity because A precedes the most number of activities (C, F, and I).

4) What is the slack of the activity C?  

a.

2

b.

4

c.

6

d.

8

5) What is the slack of the activity H?  

a.

0

b.

5

c.

36

d.

40

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Activity Preceding Activity Duration, D Early start, ES=Max of early finish of preceeding activities Early finish, EF = ES + D Late finish, LF= Min of LS of successor activities Late start, LS= LF - D Total slack= LF-EF Activities on the critical path Critical activity, activities with 0 slack time
A 12 0.00 12.00 14.00 2.00 2.00
B 9 0.00 9.00 9.00 0.00 0.00 B YES
C 10 12.00 22.00 24.00 14.00 2.00
D 10 9.00 19.00 19.00 9.00 0.00 D YES
E 24 9.00 33.00 59.00 35.00 26.00
F 10 12.00 22.00 63.00 53.00 41.00
G 35 22.00 57.00 59.00 24.00 2.00
H 40 19.00 59.00 59.00 19.00 0.00 H YES
I 15 12.00 27.00 63.00 48.00 36.00
J 4 59.00 63.00 63.00 59.00 0.00 J
K 6 63.00 69.00 69.00 63.00 0.00 K
Paths All crash Activity Duration (days)
AFK 28.00
AIK 33.00
ACGJK 67.00
BDHJK 69.00 Critical Path
BEJK 43.00

Answer 1
Project paths for the hospital expansion project

a.

AFK, AIK, ACGJK, BDHJK, BEJK



Answer 2
Project completion time in weeks
(d) 69 weeks


Answer 3
Is activity H, constructing the hospital, a critical activity for this project

() Yes, because H is on the path with the longest total activity time


Answer 4

Slack of the activity C.  
(a) 2 weeks

Answer 5
Slack of the activity H?  
(a) 0

Dear Student,
Please ask, if you have any doubts through the comment section. Do rate the answer.

Add a comment
Know the answer?
Add Answer to:
The following activities of a hospital expansion project has been identified in the following table. First,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT