(a) Network Diagram -
Hence, the correct network diagram is (C)
(b) Possible network paths and their duration are -
ACFH --> 1+1+7+3 = 12
BEFH --> 4+2+7+3 = 16
BDGH --> 4+5+2+3 = 14
Hence, critical path is the path with longest duration = B-E-F-H
(c) Length of critical path = 16 weeks
The following represent activities in Marc Massoud's Construction Company project: Activity Immediate Predecessor(s) Time (weeks) Activity...
A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8 B - 10 C A 3 D A 7 E B, C 6 F B, C 7 G D, E 5 H F 3 Draw the AON diagram Identify all the possible paths What is the critical path? Can activity B be delayed without delaying the completion of the project? If so, by how many days?
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 3 B A 9 C A 5 D C 2 E B D 7 F D 6 G E F 4 b. What is the critical path? A-B-D-F-G A-B-E-G A-C-D-F-G A-C-D-E-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
From this schedule of activities: Activity Immediate Predecessor Activity Time A --- 4 B A 2 C B 3 D B 5 E A 1 F C, D 3 G E, F 2 a. Draw the PERT/CPM network b. Complete the forward and backward pass c. Determine the critical path d. Determine the total duration of the project.
Schedule the following activities using CPM: Table 2 ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 8 B A 4 C A 4 D C 8 E B, D 2 F D 6 G E, F 2 Question 25 (1 point) What is the critical path? (Show your diagram and calculations) Question 25 options: A-C-D-E-G A-B-E-G A-B-D-E-G A-C-D-F-G A-B-D-F-G How many weeks will it take to complete the project? What is B slack time?
Q5: A construction project consists of activities, immediate predecessors (IPA) and duration in weeks are as shown in the following table. Draw the project network diagram, find the critical path and calculate the corresponding project completion time. Also, find the total float as well as the free float for each activity and the non- critical activities. (10 Marks) ТРА Duration (Weeks) Activity A B نما 4 с 14 D A 10 E F A BD BD с F.H 5 4...
1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 200 | 1200 | 500 | 700 | 1200 | 800 | 1800 | 1500 | 400 (a) Construct the activity-on-node (AoN) network for the relations among the activities in the (b) Using the activity-on-node (Ao) network developed in part (a), determine the critical path and the minimum time required to complete the project. Develop the earliest start and finish times, the latest finish...
chedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 5 B A 3 C A 4 D B 6 E C D 8 F D 2 G F 4 H E G 3 b. What is the critical path? A-B-D-E-H A-B-D-F-G-H A-C-E-F-G-H A-C-E-H c. How many weeks will it take to complete the project? d. Which activities have slack, and how much? B 1 week H 2 weeks F 4 weeks. C 5 weeks F 2...
Problem 5-13 A construction project is broken down into the following 10 activities: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) 1 — 5 2 1 3 3 1 4 4 1 2 5 2,3 6 6 3 4 7 4 2 8 5 4 9 6,7 7 10 8,9 5 b-1. What is the critical path? 1-3-5-8-10 1-3-6-9-10 1-4-7-9-10 1-2-5-8-10 b-2. How many weeks will the project take to complete? Number of weeks c. If activities 1 and 10 cannot be shortened,...
F: The activities in the following table describe the construction of a new house. Activity Predecessor(s) Duration(days) A: Clear site B: Bring utilities to site Excavate D: Pour foundation E: Outside plumbing B, C Frame house D G: Do electric wiring H: Lay floor Lay roof F Inside plumbing E, H K: Shingling Outside sheathing insulation F.J M: Install windows and outside doors F Do brick work L, M 0: Insulate walls and ceiling GJ Cover walls and ceiling 0...
PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....