Problem 5-13

A construction project is broken down into the following 10 activities:

ACTIVITY IMMEDIATE
PREDECESSOR
TIME (WEEKS)
1 5
2 1 3
3 1 4
4 1 2
5 2,3 6
6 3 4
7 4 2
8 5 4
9 6,7 7
10 8,9 5

b-1. What is the critical path?

1-3-5-8-10
1-3-6-9-10
1-4-7-9-10
1-2-5-8-10

b-2. How many weeks will the project take to complete?

Number of weeks            

c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which activities would you shorten to cut the project by four weeks? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.)

Cut activity 3 by 3 weeks.
and then reduce activity 6 or 9 by one week.
Cut activity 6 by 4 weeks.
Reduce activities 6 and 9 by a total of 3 weeks.
and then reduce activity 3 by one week.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

3 N 5 4 5 8 5 5 10 4 1 4 3 6 7 9 2 2 4 7

Answer b-1=

Different paths with durations =

1-2-5-8-10=5+3+6+4+5=23
1-3-5-8-10=5+4+6+4+5=24
1-3-6-9-10=5+4+4+7+5=25
1-4-7-9-10=5+2+2+7+5=21

So the critical path = 1-3-6-9-10 as it has longest duration

Answer b=2

Number of weeks = length of critical path =25

Answer c= The options are

Cut activity 3 by 3 weeks.

and then reduce activity 6 or 9 by one week.

Reason- When activity 3 is reduced by 3 weeks, no change will occur to the critical path

In the case of reducing activity 6 or 9 by one week, it will change the critical path to  1-3-5-8-10

Add a comment
Know the answer?
Add Answer to:
Problem 5-13 A construction project is broken down into the following 10 activities: ACTIVITY IMMEDIATE PREDECESSOR...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A construction project is broken down into the following 10 activities:

    Problem 5-13 A construction project is broken down into the following 10 activities:b-1. What is the critical path? 1-4-7-9-10 1-3-6-9-10 1-2-5-8-10 1-3-5-8-10 b-2. How many weeks will the project take to complete? Number of weeks _______ c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which activities would you shorten to cut the project by four weeks? (You may select more than one answer. Single-click the...

  • The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...

    The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 3 B A 9 C A 5 D C 2 E B D 7 F D 6 G E F 4 b. What is the critical path? A-B-D-F-G A-B-E-G A-C-D-F-G A-C-D-E-G c. How many weeks will it take to complete the project? Number of weeks             d. How much slack does activity B have? Slack of activity B             week(s)

  • A senior manager has finished reviewing the latest draft of an upcoming project. the following table...

    A senior manager has finished reviewing the latest draft of an upcoming project. the following table provides information about the project including the normal time for each activity, activity sequence and information about costs to shorten some of the activities and therefore the project duration. As he prepares ro review rhe proposal with the owners he is concerned about the project duration and expects the owners will want the project shortened. Activity Precedes Normal Time. (week) Crashing Costs ($000) 1st...

  • 1. Consider the following information: Activity Predecessor Duration (weeks) A None 2 B A 4 C...

    1. Consider the following information: Activity Predecessor Duration (weeks) A None 2 B A 4 C A 3 D A 2 E B 3 F C 6 G C, D 5 H E, F 6 I G 5 J H, I 5 Activities B and H can be shortened by a minimum of 2 time units. Which activity would you shorten to reduce the project duration of 2 weeks. Why? (be specific)

  • Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3...

    Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...

  • A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8...

    A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8 B - 10 C A 3 D A 7 E B, C 6 F B, C 7 G D, E 5 H F 3 Draw the AON diagram Identify all the possible paths What is the critical path? Can activity B be delayed without delaying the completion of the project? If so, by how many days?

  • A=8 B=6 E=5 G=4 C=7 F=9 D=7 The following activities are part of a project to...

    A=8 B=6 E=5 G=4 C=7 F=9 D=7 The following activities are part of a project to be scheduled using CPM. Determine the critical Path. How many weeks will it take to complete the project? Suppose F could be shortened by two weeks and B by one week. How would this affect the completion date? OBJECTIVE QUESTION 14 The following activities are part of a project to be scheduled using CPM. B-6 A-8 G-4 D-7 E-5 F-9 a. Determine the critical...

  • Activity No. Activity Time (weeks) Immediate Predecessors 1 Collect requirements 6 2 Analyze processes 2 1...

    Activity No. Activity Time (weeks) Immediate Predecessors 1 Collect requirements 6 2 Analyze processes 2 1 3 Analyze data 4 2 4 Design processes 18 2 5 Design data 6 3 6 Design screens 6 3,4 7 Design reports 12 4,5 8 Program 10 6,7 9 Test and Document 14 7 10 Install 4 8,9 Construct a network diagram & calculate the earliest expected completion time/s

  • Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 A None None...

    Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 A None None None B Cost Normal Crash 1000 1600 2000 2700 300 300 1300 1600 2 1 С 1 1 D A 7 3 E 6 3 B с 1000 5000 F 2 850 4000 1500 NA G D. E 4 2000 What's the normal project completion time? Identify the critical path If you'd like to shorten the project by one week, which activity should you...

  • chedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 5 B A...

    chedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 5 B A 3 C A 4 D B 6 E C D 8 F D 2 G F 4 H E G 3 b. What is the critical path? A-B-D-E-H A-B-D-F-G-H A-C-E-F-G-H A-C-E-H c. How many weeks will it take to complete the project? d. Which activities have slack, and how much? B 1 week H 2 weeks F 4 weeks. C 5 weeks F 2...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT