A senior manager has finished reviewing the latest draft of an upcoming project. the following table provides information about the project including the normal time for each activity, activity sequence and information about costs to shorten some of the activities and therefore the project duration. As he prepares ro review rhe proposal with the owners he is concerned about the project duration and expects the owners will want the project shortened.
Activity |
Precedes |
Normal Time. (week) |
Crashing |
Costs ($000) |
|
1st Week |
2nd Week |
3rd Week |
|||
Start |
A,b |
0 |
- |
- |
- |
a |
C |
3 |
11 |
14 |
- |
b |
D |
7 |
15 |
16 |
23 |
c |
D |
5 |
12 |
13 |
- |
d |
E,f |
6 |
20 |
22 |
25 |
e |
G |
4 |
12 |
15 |
- |
f |
H |
5 |
10 |
12 |
- |
g |
End |
4 |
15 |
15 |
- |
h |
End |
4 |
8 |
9 |
- |
Suggest why the owners or the project manager may wish to shorten the project.
Draw the appropriate PERT Diagram and identify the critical path and project completion time assuming the project is not shortened.
The project manager thinks the owners may ask him to shorten the project by 4 weeks. Prepare the lowest cost crashing plant that will reduce the project duration by 4 weeks.
If the indirect costs for the project total $18,000 per week, how many weeks would you recommend to the owners that the project be shortened? And Why?
1) The owners may wish to shorten the project to meet deadline set by clients or to reduce the total cost of the project.
2) PERT diagram is following:
3) Shorten the project by 4 weeks
Total crash cost = $ 60,000
4) Minimum cost schedule, given indirect cost of $ 18000 per week, is determined below:
A senior manager has finished reviewing the latest draft of an upcoming project. the following table...
I just need the last two parts of the question answered. PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) $1,050 $2,000 $2,560 $2,600 $1,300 $2,600 $2,200 $1,800 $2,400 4 $4,200 $5,540 $2,050 4...
Software Installation: You are the project manager of the software installation project (see figure & table) below. You would like to find the minimum-cost schedule for your project. There is a $1,000-per-week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,500 per week. Oo un D FINISH START START I Normal Normal Crash Crash Max reduction $ per Week Activity Time Cost Time Cost AI 5...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Duration (weeks) Activity A (start) Precedes B, C Crash Cost/Week $400 $100 $200 $300 $400 F F (end) 2 Suppose that Rafay is only given 5 weeks (instead of 7) to complete the project. By how many weeks should each activity be crashed in order to...
Megah Holding Sdn. Bhd is in progress to start their housing project. The list of activity and scheduled of the project is proposed as in Table 1. If the indirect costs for each duration is as follows, compute the direct and total cost for each duration. What is the optimum cost-time schedule? Indirect cost 27 weeks – RM 350 26 weeks – RM 270 25 weeks – RM 160 24 weeks – RM 100 12 weeks – RM 70 (12...
Use a PERT network to establish the expected duration for the project described in the table below: (SHOW the PERT NETWORK) Activity Predecessors Duration a m b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400 600 D B, C 4 6 8 200 600 E B, C 6 9 12 400 300 F C 4 6 14...
1) Based on the given information regarding the activities for the project, the project length= ___ weeks. 2) The total cost required for completing this project on normal time= $____ 3) For reducing the duration of the project by one week, the activity that should be crashed first is activity ___. 4) The cost of the project based on the first activity selected for crashing will increase by $___. 5) The maximum weeks by which the project can be reduced...
need help Crashing 6. When deciding on whether or not to crash project activities, a project manager was faced with the following information. Activities of the critical path are highlighted with an asterisk: 1992 Normal Crashed Activity A B* Extra Cost $4,000 $3,000 $3,500 D* Cost $5,000 $10,000 $3,500 $4,500 $1,500 $7,500 $3,000 $2,500 Duration 4 weeks 5 weeks 2 weeks 6 weeks 3 weeks 8 weeks 7 weeks 6 weeks $4,000 $2,500 Duration 3 weeks 4 weeks 1 week...
Question 2. (30%) The following table provides the information necessary to construct project network and calculate a total project cost. In case of activity crash, the information includes crash cost for each activity. Activity Immediate predecessor(s) Activity time (weeks) Normal cost (x1000$) Additional cost for crashing one week (x1000$) Normal After maximum crash A - 16 12 2,000 300 B - 14 9 1,000 160 C A 8 6 500 100 D A 5 4 600 700 E B 4...
Lecture Exercise #13 Project Crashing Time (weeks) Cost Activity Predecessori s) Normal Crash Normal Crash A None 3 2 1000 1600 B None 2 1 2000 2700 C None 1 1 300 300 D A 7 3 1300 1600 E B 6 3 850 1000 F с 2 1 4000 5000 D, E 2000 G 4 2 1500 What's the normal project completion time? Identify the critical path If you'd like to shorten the project by one week, which activity...
A project manager discovers that his team has neglected to complete the network diagram for the project. the network diagram is shown below. however the project manager has some information available, specifically that each activity a-g, has a different duration between one and seven weeks. also the slack time for each of the activity is known as shown belowDuration (weeks): 1,2,3,4,5,6,7 Slack time (weeks): 0,0,0,1,1,3,7 A D E G B FINISH START C F Using the clues provided below, determine...