Please help me find the critical path and the slack. I've been struggling on this for awhile
ACTIVITY |
DURATION |
ES |
EF |
LS |
LF |
SLACK |
CRITICAL |
A |
4 |
0 |
4 |
0 |
4 |
0 |
YES |
B |
7 |
0 |
7 |
2 |
9 |
2 |
|
C |
5 |
4 |
9 |
4 |
9 |
0 |
YES |
D |
11 |
9 |
20 |
9 |
20 |
0 |
YES |
E |
9 |
7 |
16 |
12 |
21 |
5 |
|
F |
4 |
20 |
24 |
20 |
24 |
0 |
YES |
G |
3 |
16 |
19 |
21 |
24 |
5 |
|
H |
9 |
24 |
33 |
24 |
33 |
0 |
YES |
ES = MAX(EF OF ALL PREDECESSORS); 0 FOR FIRST ACTIVITY
EF = ES + DURATION
LF = MIN(LS OF ALL SUCCESSOR ACTIVITIES); MAX EF AS LF FOR LAST ACTIVITY
LS = LF - DURATION
SLACK = LF- EF
CRITICAL PATH = LONGEST PATH WITH 0 SLACK:
CRITICAL PATH = A--C--D--F--H
DURATION OF PROJECT = 33
** Leaving a thumbs-up would really help me out. Let me know if you face any problems.
Please help me find the critical path and the slack. I've been struggling on this for...
A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) B, C I Q7 Moow E F, G b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Yes Slack (weeks) D 0 Yes 0 0 00000000 @ Tm I
Problem 3 A project for improving a billing process has the following precedence relationships and activity times: Activity Time (weeks) Activity Immediate Predecessor(s) A В 7 C 7 A В, С D 14 Е 10 5 D E Н F, G a. Choose the correct network diagram below. O A. O B. в O C. O D. S в Problem 3 Question Help O D. O C b. Calculate the slack for each activity. Which activities are on the critical...
Can someone please help me with this Operations Management Question? The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) MO OWO 10ம் ONNON b. What is the critical path? O O O O A-C-D-E-G A-B-E-G A-B-D-F-G A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
Which one of the following is not a step in using critical path method? A. determine the critical path B. determine the sequence of the activities and the immediate predecessor relationships C. identify each activity and its completion time D. determine the throughput rate for each activity
QUESTION 17 The critical path of the projected below as been determine what they Activity Time Immediate Predecessor A 7 8 C 2 A D A E F 5 G CE 8 D. QUESTION 17 A B The critical path of the project outlined below has been mined of B-F-H. What is the slack time for activity F? Time Immediate Activity (wks) Predecessor(s) 7 8 с 2 А A E B F G 9 CE H 8 DF D 2...
Please show me the answer and how to place it on a spreadsheet. Thanks. 13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project. Table EX 13.7 Activity Predecessor Duration (Weeks) A – 6 B – 2 C A 4 D B 5 E B 2 F C, D 4 G C, D 7 H E, G 5 I F 4 Construct an activity on node network for the project. Identify the paths and path...
What is the critical path? Start-A-D-G-End O Start-A-D-F-End Start-A-E-G-End O Start-B-E-G-End What is the EF (earliest finish) of activity E? o o ООООО < N N What is the LS (latest start) of activity E? ООООО The list of activities, their times (in weeks), and precedence relationships for a new project are given below. Activity Immediate Predecessor Activity Time A L - L 4 B - 1 2 C - A, B F DL 4 G C, D, E What...
Question 24 (20 points) Use the following table of related activities with their activity times (weeks). Q24-1) Type your answers by the order of ES, EL, LS, LF, Slack for each activity. For example, A. Х, Х, Х, Х, Х Q24-2) Determine the critical path. Immediate Activity Activity Predecessor Time ESEFLSLqslack (weeks 4 C A DIB E A FIB G C,D H |D,F 7 6 5 4 6 G, H, I J Question 24 (20 points) Use the following table...
PLEASE SOLVE FOR ALL :) determine ES, EF, LS, LF, and slack for each Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) E 4 A R 6 5 C A G 10 C, E D 1 A H 6 D.F Dave's...
also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...