Slack time for critical path activities is always 0
So if the critical path is determined as B-F-H then the slack time for activity F is "0".
Please give thumbs up/ likes if you find this answer helpful. Thank you!
QUESTION 17 The critical path of the projected below as been determine what they Activity Time...
QUESTION 20 The critical path of the project outlined below has been determined of B-F-H. What is the slack time for activity F? Time Immediate Activity (wks) Predecessor(s) A 7 B B с 2 А D 2 А E 3 B F 5 G 9 CE H 8 DF B
A critical path of the project outlined below has been determined of BFH. What is the slack time for activity F? Activity Time (weeks) Immediate predecessors A 7 - B 8 - C 2 A D 2 A E 3 B F 5 B G 9 C,e h 8 D,f
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Time Activity (weeks) А 7 Immediate Predecessor(s) Time Activity (weeks) E 3 F 7 G 11 H 8 Immediate Predecessor(s) B B CE D. B с D 2 3 A A Dave's earliest...
Question 8 (1 point) Given the following information, what is the critical path? Time (days) Activity Immediate Predecessor(s) 10 A, D E, F C-F-G B-D-F-G B-D-E-G A-E-G Question 9 (1 point) Saved
b. Determine the project’s critical path and duration.(this is number b wuestion) please answer this two b and c questions Reliable Garage is completing production of the J2000 kit car. The following data are available for the project Activity Activity Time (days) Immediate Predecessor(s 10 D, E,G A-B-C-D-H 4 4 A-B-C-F-G-H b. Determine the pr A-B-C-E-H The critical path isand the project duration is I duration. day(s). (Enter your response as a whole number.) c. Calculate the slack for each...
also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...
Please help me find the critical path and the slack. I've been struggling on this for awhile Screen Shot 2020-04-20 at 3.45.19 PM Z o @ Q Search A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) <MOOW LUI b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Slack (weeks) Yes No Yes Yes | <mo...
Question 24 (20 points) Use the following table of related activities with their activity times (weeks). Q24-1) Type your answers by the order of ES, EL, LS, LF, Slack for each activity. For example, A. Х, Х, Х, Х, Х Q24-2) Determine the critical path. Immediate Activity Activity Predecessor Time ESEFLSLqslack (weeks 4 C A DIB E A FIB G C,D H |D,F 7 6 5 4 6 G, H, I J Question 24 (20 points) Use the following table...
D Question 6 5 pts Project B: What is/are the critical path(s) for this project? Activity Immediate Predecessor Activity Duration 6 A,B D,E G,F BDFH BEGH and CGH BEFH BEGH
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) А 7 B 6 2 3 B.D D b. What is the critical path? Оооо A-C-D-E-G A-B-D-F-G A-B-E-G O A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)