Question

A critical path of the project outlined below has been determined of BFH. What is the...

A critical path of the project outlined below has been determined of BFH. What is the slack time for activity F?

Activity

Time (weeks)

Immediate predecessors

A

7

-

B

8

-

C

2

A

D

2

A

E

3

B

F

5

B

G

9

C,e

h

8

D,f

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Below is the screenshot of the formula applied -

XJ 5 2020 - Excel FILE fx Σ HOME INSERT PAGE LAYOUT FORMULAS DATA REVIEW VIEW Dynamics AX ? A e Define Name Fx Use in Formula

Below is the screenshot of the result -

x] FILE HOME INSERT PAGE LAYOUT FORMULAS DATA REVIEW VIEW fx E Insert Function ? A e AutoSum Recently Financial Logical Text

From above -

Slack of Activity F = 0

Add a comment
Know the answer?
Add Answer to:
A critical path of the project outlined below has been determined of BFH. What is the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • QUESTION 20 The critical path of the project outlined below has been determined of B-F-H. What...

    QUESTION 20 The critical path of the project outlined below has been determined of B-F-H. What is the slack time for activity F? Time Immediate Activity (wks) Predecessor(s) A 7 B B с 2 А D 2 А E 3 B F 5 G 9 CE H 8 DF B

  • QUESTION 17 The critical path of the projected below as been determine what they Activity Time...

    QUESTION 17 The critical path of the projected below as been determine what they Activity Time Immediate Predecessor A 7 8 C 2 A D A E F 5 G CE 8 D. QUESTION 17 A B The critical path of the project outlined below has been mined of B-F-H. What is the slack time for activity F? Time Immediate Activity (wks) Predecessor(s) 7 8 с 2 А A E B F G 9 CE H 8 DF D 2...

  • Consider the following project where times are in weeks. Activity Duration Immediate Predecessors A B с...

    Consider the following project where times are in weeks. Activity Duration Immediate Predecessors A B с D E F G H A.B B A с E,F 8 12 7 4 2 3 7 3 DF a) Determine the activity schedule (ES, EF, LS, and LF) as well as slack using the information from the table above (11 marks) b) Determine all the possible paths of this project and determine the shortest possible time this project can be completed? (4 marks)...

  • also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity...

    also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...

  • The following activities of a hospital expansion project has been identified in the following table. First,...

    The following activities of a hospital expansion project has been identified in the following table. First, all activities of the project are listed. Next, the immediate predecessor(s) of each activity is identified (activity relationships). Please plot the activity network diagram and answer the following questions. Hospital Expansion Project Activity Description Immediate predecessor(s) Activity Time (Weeks) A Select administrative and medical staff - 12 B Select site and do site survey - 9 C Select equipment A 10 D Prepare final...

  • Please help me find the critical path and the slack. I've been struggling on this for...

    Please help me find the critical path and the slack. I've been struggling on this for awhile Screen Shot 2020-04-20 at 3.45.19 PM Z o @ Q Search A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) <MOOW LUI b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Slack (weeks) Yes No Yes Yes | <mo...

  • Operation management

    The following activities are part of a project to be scheduled using CPM.Activity Immediate predecessors Time(Weeks)A - 6B A 3C A 7D C 2E B,D 4F D 3G E,F 7i) Draw the networkii) What is the critical path?iii) How many weeks will it take to complete the project?iv) How much slack does activity B have?

  • A project for improving a billing process has the following precedence relationships and activity times: Activity...

    A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) B, C I Q7 Moow E F, G b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Yes Slack (weeks) D 0 Yes 0 0 00000000 @ Tm I

  • The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...

    The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 3 B A 9 C A 5 D C 2 E B D 7 F D 6 G E F 4 b. What is the critical path? A-B-D-F-G A-B-E-G A-C-D-F-G A-C-D-E-G c. How many weeks will it take to complete the project? Number of weeks             d. How much slack does activity B have? Slack of activity B             week(s)

  • Problem 3 A project for improving a billing process has the following precedence relationships and activity...

    Problem 3 A project for improving a billing process has the following precedence relationships and activity times: Activity Time (weeks) Activity Immediate Predecessor(s) A В 7 C 7 A В, С D 14 Е 10 5 D E Н F, G a. Choose the correct network diagram below. O A. O B. в O C. O D. S в Problem 3 Question Help O D. O C b. Calculate the slack for each activity. Which activities are on the critical...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT