PLEASE SOLVE FOR ALL :) determine ES, EF, LS, LF, and slack for each Dave Fletcher...
also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Time Activity (weeks) А 7 Immediate Predecessor(s) Time Activity (weeks) E 3 F 7 G 11 H 8 Immediate Predecessor(s) B B CE D. B с D 2 3 A A Dave's earliest...
I need Activity A-H Myo Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Time Immediate TimeImmediate Activity (weeks) Predecessorís) Activity (weeks) Predecessors) G 10 C, E D. F Dae'sarlest start (ES) and eariest fnish (EF) are
Question 24 (20 points) Use the following table of related activities with their activity times (weeks). Q24-1) Type your answers by the order of ES, EL, LS, LF, Slack for each activity. For example, A. Х, Х, Х, Х, Х Q24-2) Determine the critical path. Immediate Activity Activity Predecessor Time ESEFLSLqslack (weeks 4 C A DIB E A FIB G C,D H |D,F 7 6 5 4 6 G, H, I J Question 24 (20 points) Use the following table...
Question 5 For the project depicted below, a) Compute the ES, EF, LS, and LF times for the network. b) Explain how the ES for Activity 3 is obtained. c) Explain how the LF time for Activity 1 is obtained. d) What is the critical path for the project? e) How long do you expect the project to take to complete? Activity 4 Activity 2 ES= EF= wks LSELF ES= EF T=5 wks LSELF= Activity 1 ES= EF= T=6 wks...
Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 6 6 N/A B none 5 2 $500 C A 3 2 $1000 D A, B 4 2 $2000 E C, D 5 2 $1250 F D 6 2 $1000 *Shortest possible time for the task 1. Draw the project network and list...
(3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). (3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). po Problem . Example a 100 For all starting activities, ES is taken as 0. Activities 1-2, 1-3 gets ES of O. Find EF-ES +time. Activity Time ES E F LS L...
A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...
What is the critical path? Start-A-D-G-End O Start-A-D-F-End Start-A-E-G-End O Start-B-E-G-End What is the EF (earliest finish) of activity E? o o ООООО < N N What is the LS (latest start) of activity E? ООООО The list of activities, their times (in weeks), and precedence relationships for a new project are given below. Activity Immediate Predecessor Activity Time A L - L 4 B - 1 2 C - A, B F DL 4 G C, D, E What...
for each problem I have this setup so far. I need help on each part and im not too sure if I am on the right track for each question on the picture. this chapter is on project management for statistics 1. A project is shown by the following network. The durations of activities (in weeks) are indicated on the arrows. a. Identify all of the paths, compute the length of each, identify the critical path and the b. Determine...