Question

Which one of the following is not a step in using critical path method? A. determine...

Which one of the following is not a step in using critical path method?

A. determine the critical path

B. determine the sequence of the activities and the immediate predecessor relationships

C. identify each activity and its completion time

D. determine the throughput rate for each activity

0 0
Add a comment Improve this question Transcribed image text
Answer #1

D. determine the throughput rate for each activity

This is not an activity to be pursued during the critical path method because this is not required in calculating the critical path or sequence as well.

Add a comment
Know the answer?
Add Answer to:
Which one of the following is not a step in using critical path method? A. determine...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Please help me find the critical path and the slack. I've been struggling on this for...

    Please help me find the critical path and the slack. I've been struggling on this for awhile Screen Shot 2020-04-20 at 3.45.19 PM Z o @ Q Search A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) <MOOW LUI b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Slack (weeks) Yes No Yes Yes | <mo...

  • Lecture Exercise #12 Critical Path Method . Determine the early start, early finish, late start, late...

    Lecture Exercise #12 Critical Path Method . Determine the early start, early finish, late start, late finish times for each activity Identify the critical path Activity Time (days) Predecessor(s) . A 6 None B 7 None с 3 A D 2 A E 4 B F 6 B G 10 C, E D, F H 7 ))

  • QUESTION 17 The critical path of the projected below as been determine what they Activity Time...

    QUESTION 17 The critical path of the projected below as been determine what they Activity Time Immediate Predecessor A 7 8 C 2 A D A E F 5 G CE 8 D. QUESTION 17 A B The critical path of the project outlined below has been mined of B-F-H. What is the slack time for activity F? Time Immediate Activity (wks) Predecessor(s) 7 8 с 2 А A E B F G 9 CE H 8 DF D 2...

  • B. Determine the project’s critical path and duration.(this is number b wuestion) please answer t...

    b. Determine the project’s critical path and duration.(this is number b wuestion) please answer this two b and c questions Reliable Garage is completing production of the J2000 kit car. The following data are available for the project Activity Activity Time (days) Immediate Predecessor(s 10 D, E,G A-B-C-D-H 4 4 A-B-C-F-G-H b. Determine the pr A-B-C-E-H The critical path isand the project duration is I duration. day(s). (Enter your response as a whole number.) c. Calculate the slack for each...

  • A project for improving a billing process has the following precedence relationships and activity times: Activity...

    A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) B, C I Q7 Moow E F, G b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Yes Slack (weeks) D 0 Yes 0 0 00000000 @ Tm I

  • also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity...

    also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...

  • Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A...

    Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...

  • What is the critical path? Start-A-D-G-End O Start-A-D-F-End Start-A-E-G-End O Start-B-E-G-End What is the EF (earliest...

    What is the critical path? Start-A-D-G-End O Start-A-D-F-End Start-A-E-G-End O Start-B-E-G-End What is the EF (earliest finish) of activity E? o o ООООО < N N What is the LS (latest start) of activity E? ООООО The list of activities, their times (in weeks), and precedence relationships for a new project are given below. Activity Immediate Predecessor Activity Time A L - L 4 B - 1 2 C - A, B F DL 4 G C, D, E What...

  • Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and...

    Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and finish, and slack for each task. Activity Duration (Days) Immediate Predecessor none none none KUHIGT mono 00 00 ONTHOOOO D, E G, J, K b. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) Task Earliest Start s+ Start (ES) Earliest Completion (EC) Immediate Predecessors None None None B C...

  • The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning...

    The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning Company are given in the following table. Assume that the activity times are independent. Activity Immediate Predecessor a (time weeks) m (time weeks) b (time weeks) A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 Calculate the expected time (mean) and variance for each activity, then answer the following: a. What is the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT