Lecture Exercise #12 Critical Path Method . Determine the early start, early finish, late start, late...
Lecture Exercise #12 Critical Path Method Determine the early start, early finish, late start, late finish times for each activity Identify the critical path . Activity А Time (days) 6 7 3 Predecessor(s) None None B с A 2 A E 4 B F 6 B 10 C. E D. F H 7 Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 2 1 А B None None None с 1 1 Cost Normal Crash 1000...
8.6: From the following network data, determine the critical path, early start, early finish, late start, late finish, total float, and free float for each activity. Highlight the critical path. E B 3 С F A 2 K N o G 2
9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activity. (20 points) Predecessor Duration (Days) Activity A, B C, D F,G
9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activity. (20...
QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B А 7...
21. Using the CPM method, calculate early start (ES), late start (LS), early finish (EF), late finish (LF) and total float (TF) for each activity in the following network and answer the questions 21-1. The ES of activity His: a) 18 b) 22C) 5 d) 2 21-2. The LF of activity B is: a) 20 b) 22c) 18d) 19 ) 13 d) 59 21-3. The TF of activity A is: a) 5 b ) 17 c) 18 21-4. The project...
QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration. (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B A 7...
early start early finish Timo - - - ---- A 20 late finish Number of workers C 20 required daily for D 5 each activity E 10 F 10 G 15 E ---- FE G ------- - DH Activities GA 1 2 3 4 5 6 7 8 (a) On this diagram, show the total daily workers required (loading) assuming early start times for all activities. Show what portion of the total labor loading each day comes from each activity....
also needs daves latest start and latest finish:
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...
QUESTION 2 Given the following information, you are to determine the following Project network. Early, late and slack activity times. Project duration. Critical path Task Predecessor Duration A None 8 B A 5 C A 10 D A 15 E A 10 F B 12 G C, D 12 H E, 7 I G, H 7 J F,G,I 10 K J 12
QUESTION 1 Please use the information below to draw and solve the network on a piece of paper by: Complete the forward and backward pass Identify the critical path Fill in the requested information (Example: ESA Early Start of Activity A; LFA Late Finish of Activity A, etc) Relationship Activity Contract sign Predecessor Activity ID Duration 3 А Survey В 2 А Target market C Data В,С D 7 collection Presentation 2 FS Lag 3 E В Analyze F 2...