Question

QUESTION 2 Given the following information, you are to determine the following Project network. Early, late...

QUESTION 2

Given the following information, you are to determine the following

  • Project network.
  • Early, late and slack activity times.
  • Project duration.
  • Critical path

Task

Predecessor

Duration

A

None

8

B

A

5

C

A

10

D

A

15

E

A

10

F

B

12

G

C, D

12

H

E,

7

I

G, H

7

J

F,G,I

10

K

J

12

0 0
Add a comment Improve this question Transcribed image text
Answer #1

We prepare a project network as shown below:

Refer Legend for identifying Early start, early finish, late start, late finish and slack for each activity as shown in each box.

ES = Early start, EF = Early finish, ID = Activity name, SLK = Slack, LS = Late start, LF = Late finish. Refer each box for corresponding values.

As seen from above, project duration is 64 days

As seen from above, the critical path is A-D-G-I-J-K. This is the path with zero slack

Add a comment
Know the answer?
Add Answer to:
QUESTION 2 Given the following information, you are to determine the following Project network. Early, late...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT