QUESTION 2
Given the following information, you are to determine the following
Task |
Predecessor |
Duration |
A |
None |
8 |
B |
A |
5 |
C |
A |
10 |
D |
A |
15 |
E |
A |
10 |
F |
B |
12 |
G |
C, D |
12 |
H |
E, |
7 |
I |
G, H |
7 |
J |
F,G,I |
10 |
K |
J |
12 |
We prepare a project network as shown below:
Refer Legend for identifying Early start, early finish, late start, late finish and slack for each activity as shown in each box.
ES = Early start, EF = Early finish, ID = Activity name, SLK = Slack, LS = Late start, LF = Late finish. Refer each box for corresponding values.
As seen from above, project duration is 64 days
As seen from above, the critical path is A-D-G-I-J-K. This is the path with zero slack
QUESTION 2 Given the following information, you are to determine the following Project network. Early, late...
Assignment for week 5Given the following information, draw the project network. Compute the early, late and slack times for the project network. which activities are on the critical path have only the start or finish of the activity on the critical path?ID duration finish to start finish to start additional lag lag predecessor lag Relationship A 2 none 0 none 0B 4 A 0 none 0C 6 A 0 finish-finish C to F 7D 8 A 0 none 0E 18...
Lecture Exercise #12 Critical Path Method . Determine the early start, early finish, late start, late finish times for each activity Identify the critical path Activity Time (days) Predecessor(s) . A 6 None B 7 None с 3 A D 2 A E 4 B F 6 B G 10 C, E D, F H 7 ))
9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activity. (20 points) Predecessor Duration (Days) Activity A, B C, D F,G 9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activity. (20...
QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration. (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B A 7...
QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B А 7...
21. Given the information in the following lag exercises, compute the early, late, and slack times for the project network. Which activities on the critical path have only the start or finish of the activity on the critical path? Lag 3 Interview 15 Def. New Features Order Comps Prototype Field Test Lag 5 Lag 10 10 Legend Description SL Duration
: A network consists of the following list. Times are given in weeks. Activity Preceding Duration A -- 9 B A 2 C A 12 D A 5 E B 6 F B 8 G C, F 3 H D 2 I H 8 J G, I 6 K E, J 2 Draw the network diagram. Find ES, EF, LS, LF, and the slack times for each of the activities. Which activities are critical? Determine the critical path(s). What is...
The following info is available for drawing a PERT network using AOA. *(More than one answer may be selected)* Activity Immediate Predecessors Activity Duration (days) A -- 10 B -- 13 C A 12 D B 15 E A 13 F C 16 G D,E 10 H G,F 5 a. the critical path includes: B, D, G, and H. b. the slack on activity G is not 11 days. c. there is one critical path. d. the total duration to...
Provide step by step please thank you, no exce Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest completion time (or early finish-EF), latest completion time (or late finish-LF), and slack for each of the following tasks (begin at time 0) the critical path on your network diagram. . Which tasks are on the critical path? Highligh Preceding Expected Critical Path? Activity Event Duration EF LF Slack A, D C,E D, E F, G...
Given the information in the following table: Activity Duration Predecessor A 4 None B 6 A C 4 A D 2 C E 4 B F 5 B, D G 3 C H 4 F, G I 2 E, H Construct the (AON) Activity on Node network diagram Find each activity’s ES, EF, LS and LS Identify all paths. Which path is the critical path? Calculate the slack for each activity. How long will it take to complete the project?