Activity |
Duration |
Predecessor |
A |
4 |
None |
B |
6 |
A |
C |
4 |
A |
D |
2 |
C |
E |
4 |
B |
F |
5 |
B, D |
G |
3 |
C |
H |
4 |
F, G |
I |
2 |
E, H |
(a) Network Diagram -
(b)
Earliest Start (ES) = the earliest time when the activity can begin
Earliest Finish (EF) = ES + Activity Duration
Latest Finish (LF) = the latest time by when the activity can be finished without changing the project completion duration
Latest Start (LS) = LF - Activity Duration
Earliest | Earliest | Latest | Latest | |||
Activity | Predecessor | Duration | Start Time | Finish Time | Start Time | Finish Time |
A | - | 4 | 0 | 4 | 0 | 4 |
B | A | 6 | 4 | 10 | 4 | 10 |
C | A | 4 | 4 | 8 | 4 | 8 |
D | C | 2 | 8 | 10 | 8 | 10 |
E | B | 4 | 10 | 14 | 15 | 19 |
F | B, D | 5 | 10 | 15 | 10 | 15 |
G | C | 3 | 8 | 11 | 12 | 15 |
H | F, G | 4 | 15 | 19 | 15 | 19 |
I | E, H | 2 | 19 | 21 | 19 | 21 |
(c) Possible Network Paths and their durations are are -
ABEI --> 4+6+4+2 = 16
ABFHI --> 4+6+5+4+2 = 21
ACDFHI --> 4+4+2+5+4+2 = 21
ACGHI --> 4+4+3+4+2 = 17
Hence, critical path is path with longest duration = ABFHI & ACDFHI
(d) Slack = LS-ES = LF-EF
Earliest | Earliest | Latest | Latest | ||||
Activity | Predecessor | Duration | Start Time | Finish Time | Start Time | Finish Time | Slack |
A | - | 4 | 0 | 4 | 0 | 4 | 0 |
B | A | 6 | 4 | 10 | 4 | 10 | 0 |
C | A | 4 | 4 | 8 | 4 | 8 | 0 |
D | C | 2 | 8 | 10 | 8 | 10 | 0 |
E | B | 4 | 10 | 14 | 15 | 19 | 5 |
F | B, D | 5 | 10 | 15 | 10 | 15 | 0 |
G | C | 3 | 8 | 11 | 12 | 15 | 4 |
H | F, G | 4 | 15 | 19 | 15 | 19 | 0 |
I | E, H | 2 | 19 | 21 | 19 | 21 | 0 |
(e) Time taken to complete the project = longest duration = 21
Given the information in the following table: Activity Duration Predecessor A 4 None B 6 A...
tual code de a Activity Predecessor Normal time A 2 B 3 C B A С 5 G. F H 15 HH 2 D И N M, J 1 - Calculate early start (ES), early finish (EF), late start (LS) and late finish (LF) for each activity - Draw Activity on Arrow network (AOA) - Draw Activity on Node network (AON) - Calculate slack of each activity - Determine the critical paths. There must be at least 2 critical paths...
Please show me the answer and how to place it on a spreadsheet. Thanks. 13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project. Table EX 13.7 Activity Predecessor Duration (Weeks) A – 6 B – 2 C A 4 D B 5 E B 2 F C, D 4 G C, D 7 H E, G 5 I F 4 Construct an activity on node network for the project. Identify the paths and path...
: A network consists of the following list. Times are given in weeks. Activity Preceding Duration A -- 9 B A 2 C A 12 D A 5 E B 6 F B 8 G C, F 3 H D 2 I H 8 J G, I 6 K E, J 2 Draw the network diagram. Find ES, EF, LS, LF, and the slack times for each of the activities. Which activities are critical? Determine the critical path(s). What is...
Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity on Node (AON) diagram to reflect the flow of these activities. Calculate the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity. Calculate the slack for each activity. Identify all activities on the Critical Path. Use the data to calculate the probability the project will finish in 20 weeks (Hint: z-score). Activity A 8 с D E...
9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activity. (20 points) Predecessor Duration (Days) Activity A, B C, D F,G 9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activity. (20...
Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...
A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8 B - 10 C A 3 D A 7 E B, C 6 F B, C 7 G D, E 5 H F 3 Draw the AON diagram Identify all the possible paths What is the critical path? Can activity B be delayed without delaying the completion of the project? If so, by how many days?
Consider the following project where times are in weeks. Activity Duration Immediate Predecessors A B с D E F G H A.B B A с E,F 8 12 7 4 2 3 7 3 DF a) Determine the activity schedule (ES, EF, LS, and LF) as well as slack using the information from the table above (11 marks) b) Determine all the possible paths of this project and determine the shortest possible time this project can be completed? (4 marks)...
For each of the following predecessor tables (Tables A-C): 1. 2. 3. 4. 5. Draw a corresponding AON network. Compute EST and EFT for each activity and complete the table. Compute LST and LFT for each activity and complete the table. Find and mark the critical path. Determine the total float and free float and complete the table. Table B Activity Duration Preceding Activity ES EF LSLF TF FF 0 60600 4 A, B 10 D, E C,F.G C, G...
A network consists of the following list. Times are given in weeks. Activity Preceding Time (weeks) Activity Predecessor Duration A 4 B 9 C A 5 D B A 3 E D C 4 Calculate the ES, EF, LS, LF, slack for each activity. List the critical activities for this project.